You'll find that our Prince2-Foundation exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these Prince2-Foundation sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PRINCE2 7 Foundation written Exam practice test comfortably within the allotted time.

Question # 61

How should the Team Manager report that tolerances are forecast to be exceeded?

A.

Create an Exception Report

B.

Create a Highlight Report

C.

Raise an issue

D.

Grant a concession

Question # 62

Which is part of quality control?

A.

Undertake quality reviews

B.

Write Product Descriptions

C.

Provide assurance that the project is being conducted properly

D.

Document the customer's quality expectations

Question # 63

Which is NOT one of the PRINCE2 integrated elements?

A.

Tailoring PRINCE2 to the project environment

B.

The processes

C.

The products

D.

The themes

Question # 64

What theme estimates the cost of delivering the project?

A.

Business Case

B.

Change

C.

Plans

D.

Progress

Question # 65

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

A.

Benefits

B.

Quality

C.

Risk

D.

Scope

Question # 66

Who carries out audits that are independent of the project?

A.

Quality assurance

B.

Project Assurance

C.

Project Support

D.

Project Manager

Question # 67

Which two roles are linked by the Managing Product Delivery process?

A.

Corporate or programme management and Project Board

B.

Project Board and Project Manager

C.

Project Manager and Team Manager

D.

Team Manager and external supplier

Question # 68

Why is change management important in a project?

A.

It provides clarity on how the culture of an organization needs to adapt over time

B.

It provides processes and management products to use when requesting a change

C.

It provides confidence that the project can meet is objectives and has continued business Justification

D.

It provides a controlled and bidirectional flow of information to key Influencers

Question # 69

Which is a purpose of the 'managing a stage boundary' process?

A.

To enable the project board to approve the continuation of the project

B.

To exercise overall control over the project while delegating day-to-day management

C.

To assign work to be controlled by the team manager

D.

To define the work that needs to be done to deliver the project product

Question # 70

Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience