Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

BCS Foundation Certificate in IS Project Management

Last Update 1 hour ago Total Questions : 625

The BCS Foundation Certificate in IS Project Management content is now fully updated, with all current exam questions added 1 hour ago. Deciding to include ISEB-PM1 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our ISEB-PM1 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these ISEB-PM1 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any BCS Foundation Certificate in IS Project Management practice test comfortably within the allotted time.

Question # 166

What are assigned risk ratings based upon?

A.

Root cause analysis

B.

Assessed probability and impact

C.

Expert judgment

D.

Risk Identification

Question # 167

What is the lowest level in the WBS at which the cost and activity durations for the work can be reliably estimated and managed?

A.

Work product

B.

Work package

C.

Project deliverable

D.

Scope baseline

Question # 168

Which type of analysis is used as a general management technique within the Plan Procurements Process?

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

Question # 169

The major difference between PERT and CPM networks is:

A.

PERT is measured in days whereas CPM uses weeks or months.

B.

PERT addresses only time whereas CPM also includes cost and resource availability.

C.

PERT requires three time estimates whereas CPM requires one-time estimate.

D.

PERT is used for construction projects whereas CPM is used for R & D.

E.

PERT requires computer solutions whereas CPM is a manual technique.

Question # 170

Using the following data, what is the Schedule Performance Index (SPI)?

EV = $500

PV= $750

AC= $1000

BAC= $1200

A.

0.67

B.

1.50

C.

0.75

D.

0.50

Question # 171

Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?

A.

Performance organizations

B.

Schedule baselines

C.

Performance measurements

D.

Change requests

Question # 172

Which of the following is generally the MOST CORRECT use of a project network diagram?

A.

Showing the project schedule

B.

Documenting activity interdependencies

C.

Defining project resources

D.

Defining the project costs

Question # 173

The resource calendars document is an output of which process?

A.

Estimate Activity Resources

B.

Acquire Project Team

C.

Develop Schedule

D.

Develop Project Team

Question # 174

During what process is the quality policy determined?

A.

Initiating

B.

Executing

C.

Planning

D.

Controlling

Question # 175

In what type of contract is the seller reimbursed for all allowable costs for performing the contract work and receives a predetermined fee based upon achieving certain performance objectives as set forth in the contract?

A.

Cost-plus-fixed-fee

B.

Cost-plus-incentive-fee

C.

Firm-fixed-price

D.

Fixed-price-incentive-fee

Question # 176

Which of the following is the definition of a project?

A.

Temporary endeavor undertaken to create a temporary business process or product

B.

Temporary endeavor undertaken to create a unique product, service, or result

C.

Permanent endeavor that produces repetitive outputs

D.

Temporary endeavor that produces repetitive outputs

Question # 177

While preparing your risk responses, you realize that you have not planned for unknown risk events. You need to make adjustments to the project to compensate for unknown risk events. These adjustments are based on your past project experience when unknown risk events occurred and knocked the project off track.

What should you do?

A.

Include a management reserve in the budget to try to compensate for the unknown risks, and notify management to expect unknown risks to occur.

B.

Document the unknown risk items and calculate the expected monetary value based on probability and impact that may result from the occurrence.

C.

Determine the unknown risk events and the associated cost, then add the cost to the project budget as reserves.

D.

With the stakeholders, determine a percentage of the known risk budget to allocate to a management reserve budget.

Question # 178

The LEAST effective form of communication for complex situations is:

A.

formal

B.

verbal - face to face and formal

C.

informal

D.

written

E.

verbal - face to face

Question # 179

The sponsor has informed you that the resources for your project will be cut. The sponsor wants to know how long the project will take if only nine resources each month are committed to your project.

What is this activity called?

A.

Crashing

B.

Floating

C.

Leveling

D.

Fast tracking

Question # 180

A project manager you are mentoring comes to you for help because he is about to face his first procurement audit. You might explain that he should NOT worry about such an audit because it:

A.

Identifies successes and failures that warrant transfer to other procurements.

B.

Makes sure the contract is being followed.

C.

Makes sure costs are in line with the project.

D.

Makes sure the seller is following the contract.

Go to page: