Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

BCS Foundation Certificate in IS Project Management

Last Update 1 day ago Total Questions : 625

The BCS Foundation Certificate in IS Project Management content is now fully updated, with all current exam questions added 1 day ago. Deciding to include ISEB-PM1 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our ISEB-PM1 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these ISEB-PM1 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any BCS Foundation Certificate in IS Project Management practice test comfortably within the allotted time.

Question # 181

What are three basic types of project phase-to-phase relationships?

A.

Sequential, Overlapping, Non-overlapping

B.

Sequential, Iterative, Overlapping

C.

Sequential, Non-overlapping, Iterative

D.

Iterative, Overlapping, Non-overlapping

Question # 182

What is the function of a Project Management Office (PMO)?

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations ' or the client ' s overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization ' s business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Question # 183

You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor ' s work involves digging the holes and setting the lamp poles in concrete. The subcontractor ' s performance is not meeting the contract requirements.

Which of the following is not a valid option?

A.

You document the poor performance in written form and send the correspondence to the subcontractor.

B.

You terminate the contract for poor performance and submit a change request through Contract Administration.

C.

You agree to meet with the subcontractor to see whether a satisfactory solution can be reached.

D.

You submit a change request through Contract Administration demanding that the subcontractor comply with the terms of the contract.

Question # 184

: 560

Which schedule format usually shows both the project network logic and the project’s critical path

A.

schedule activities with activity date information?

B.

Schedule table

C.

Schedule network diagram

D.

Bar chart

E.

Milestone chart

Question # 185

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?

A.

Analogous

B.

Parametric

C.

Bottom-up

D.

Top-down

Question # 186

Management wants to be sure that the project is following defined quality standards.

Which of the following should they look at?

A.

Risk management plan

B.

WBS

C.

Statement of work

D.

Quality audit

Question # 187

In which domain of project management would a Pareto chart provide useful information?

A.

Scope Management

B.

Time Management

C.

Communications Management

D.

Quality Management

Go to page: