You'll find that our ISEB-PM1 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these ISEB-PM1 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any BCS Foundation Certificate in IS Project Management practice test comfortably within the allotted time.

Question # 121

A project manager has made a change to the project.

What should she do NEXT?

A.

Assign resources.

B.

Revise the project management plan and/or project documents.

C.

Evaluate impact.

D.

Request change control board involvement.

Question # 122

A ________ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

A.

Parametric

B.

Bottom up.

C.

Budget

D.

Top down.

E.

Definitive.

Question # 123

Your team is split between two buildings on either side of town. As a result, the team isn ' t very cohesive because the members don ' t know each other very well. The team is still in the storming stage because of the separation issues.

Which of the following should you consider?

A.

Training

B.

Co-location

C.

Corrective action

D.

Conflict resolution

Question # 124

In which of the following contract types does the buyer have the most cost risk?

A.

Cost plus percentage of costs (CPPC)

B.

Cost plus fixed fee (CPFF)

C.

Cost plus award fee (CPAF)

D.

Cost plus incentive fee (CPIF)

Question # 125

You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks. You should:

A.

See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis

B.

Inform your senior management of the problem and tell them that you will get back to them after you assessed the situation

C.

Look for someone to blame before you see the sponsor

D.

Do nothing until the slippage occurs

E.

Immediately inform the sponsor and ask for advice

Question # 126

Company A is launching a new communications satellite system. Resource B was assigned combined projects of design, construction, integration, and launch of the satellite.

Resource B ' s role is that of a:

A.

Project manager

B.

Portfolio manager

C.

Work breakdown manager

D.

Program manager

Question # 127

Information collected on the status of project activities being performed to accomplish the project work is known as what?

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Question # 128

Which of the following is not true for a Responsibility Assignment Matrix (RAM):

A.

Defines what project member is responsible for each activity

B.

Defines responsibilities for each WBS component

C.

Defines all people associated with each activity

D.

Text description of roles, responsibilities, authorities

Question # 129

Smoothing out resource requirements from period to period is called resource _____.

A.

None of the other alternatives apply.

B.

Leveling.

C.

Quantification

D.

Partitioning

E.

Allocation.

Question # 130

The decision to approve or reject a particular change request is made in which of the following processes?

A.

Perform Integrated Change Control

B.

Monitor and Control Project Work

C.

Develop Project Management Plan

D.

Direct and Manage Project Execution

Question # 131

To which process is work performance information an input?

A.

Contract administration

B.

Direction and management of project execution

C.

Create WBS

D.

Qualitative risk analysis

Question # 132

The project team reviews identified risks and the risk response strategy. For one of the risks, the team realizes that the implementation of the risk response would generate another risk.

This new risk is which of the following types of risk?

A.

Secondary

B.

Primary

C.

Residual

D.

Tertiary

Question # 133

Planning activities such that predetermined resource availability pools are not exceeded is called:

A.

Manpower planning.

B.

Manpower leveling.

C.

Resource leveling.

D.

Manpower contingency planning.

E.

Resource limited planning.

Question # 134

Which statement is true about the project management body of knowledge?

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Question # 135

A project manager is asked to select a contract type for a new software development project that has complete, detailed requirements.

Which is the BEST contract to choose?

A.

Cost reimbursable (CR)

B.

Fixed price (FP)

C.

Time and material (T & M)

D.

Cost plus fixed fee (CPFF)