You'll find that our PMI-PBA exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-PBA sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Professional in Business Analysis practice test comfortably within the allotted time.

Question # 11

After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides

enough information to check if the requirement has been met.

Which of the following would work best in this case?

A.

User stories

B.

Functional specifications

C.

Flow chart

D.

Prototyping

Question # 12

While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis

favors a custom-developed solution, either built internally or using contract labor.

To prepare the recommendation, what should the business analyst do?

A.

Perform solution evaluation.

B.

Formulate a weighted-ranking matrix.

C.

Review the stakeholder analysis.

D.

Recommend the SVP ' s choice, as it is most likely to be adopted.

Question # 13

When eliciting requirements, a good time to consider using the interviewing method is when:

A.

attempting to obtain sign-off on requirements from stakeholders.

B.

there is not enough time to gather requirements from many different sources.

C.

there are communication challenges among stakeholders.

D.

assembling a requirements traceability matrix.

Question # 14

Which statement accurately depicts what changes can be made to requirements after they are baselined?

A.

Requirements can be changed only with sponsor approval.

B.

Requirements can be changed through a defined process.

C.

Requirements cannot be changed once development begins.

D.

Requirements cannot be changed once user acceptance testing begins.

Question # 15

The requirements traceability matrix should primarily be used to:

A.

identify the risks associated with dependent requirements.

B.

define a convention to map the requirements to their sources.

C.

ensure that all requirements have been met.

D.

address the responsibility owner for each requirement.

Question # 16

After a project was delivered, the business analyst learns of a project objective with no associated requirement. What would have helped determine this issue before delivery?

A.

Context diagram

B.

Use cases

C.

Process flow

D.

Tracing requirements

Question # 17

Which of the following is a method for requirements change control?

A.

Communication management

B.

Scope analysis

C.

Requirements management

D.

Baselining

Question # 18

During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?

A.

Requirements cards

B.

Requirements baseline

C.

Requirements management tool

D.

Requirements traceability matrix

Question # 19

A document is being created that will detail the customer ' s needs for a product and will include a functional model, a data model, and a glossary of terms. This document is called a:

A.

standard operating manual.

B.

business case.

C.

project charter.

D.

requirements specification.

Question # 20

The project team is working on test scripts to test a solution. Which source can be used for building tests of end-to-end business processes across business functions and systems?

A.

Prototype model

B.

Feature model

C.

Context diagram

D.

Use case