You'll find that our Prince2-Foundation exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these Prince2-Foundation sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PRINCE2 7 Foundation written Exam practice test comfortably within the allotted time.

Question # 101

Which is a purpose of the Directing a Project process?

A.

Create and authorize the project mandate

B.

Ensure that work on products allocated to the team is authorized and agreed

C.

Control the day-to-day running of the project

D.

Delegate day-to-day management of the project to the Project Manager

Question # 102

How many roles make up the Project Board?

A.

One

B.

Two

C.

Three

D.

Four

Question # 103

The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual

products being worked on.

Which part of effective issue management is the project manager applying?

A.

Baselines

B.

Change budget

C.

Change control

D.

Issue resolution

Question # 104

The project manager needs to report to the project board on the status of the project's Issues.

A.

Project log

B.

Project brief

C.

Lessons report

D.

Change management approach

Question # 105

Which term is defined as the means by which an organization transitions to a desired future state?

A.

Change management

B.

Risk management

C.

Issue management

D.

Communication management

Question # 106

Which should provide guidance on how and when prototyping is to be used?

A.

Product description

B.

Quality management approach

C.

Quality register

D.

Sustainability management approach

Question # 107

Which TWO are objectives of the 'Managing a Stage Boundary' process?

    To confirm to the project board that there are no products outstanding for the stage

    To ensure that expectations are managed via accurate reporting to the project manager during a stage

    To ensure that the project management team is not distracted by delivering additional products during the stage

    To request the project board to approve work to start on the next stage

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question # 108

Which is the Issue Register NOT used for?

A.

Capture external events that are impacting a stage

B.

Record information about a deviation in stage tolerance

C.

Capture any threats or opportunities that might have an impact on a stage

D.

Record any problems identified when authorizing a Work Package

Question # 109

What should be recorded in a quality register?

1. Activities to ensure the products are fit for purpose

2. Identified threats and opportunities

3. Problems and concerns to be managed informally

4. Roles responsible for reviewing the project's products

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question # 110

What is a purpose of the communication management approach?

A.

To define how the project team intends to obtain responses from stakeholders

B.

To describe the techniques required to make the project product acceptable to stakeholders

C.

To describe the target organizational state and how the business will move to that new state

D.

To describe the processes used to engage with stakeholders in identifying uncertainties