You'll find that our APM-PFQ exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these APM-PFQ sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any APM Project Fundamentals Qualification (PFQ) practice test comfortably within the allotted time.

Question # 41

Which one of the following would best describe a post project review?

A.

It is a personal appraisal for each team member on completion Of the project.

B.

It appraises the products of the project.

C.

It considers all aspects of the management of the project.

D It involves only the project implementation team.

Question # 42

Understanding who stakeholders are and their needs is a key duty of

A.

the quality manager.

B.

the key users,

C.

the project manager.

D.

the business sponsor.

Question # 43

Which one of the following best characterises a project?

A.

An ongoing activity to maintain the company plant.

B.

A. transient endeavour carried out to meet specificobjectives.

C.

Continuous improvement of the company procedures.

D.

Manufacturing components for a new technology.

Question # 44

Which one of the following is the best description of project scope?

A.

Scope is detailed in the business case.

B.

Scope is the total work content of a project.

C.

Scope is an outcome of the scheduling and estimating processes.

D.

Scope defines what is NOT delivered by the project.

Question # 45

What is the likely decision to arise from the response stage of the risk management process?

A.

Whether to proceed with the project or recommend termination.

B.

Whether the process being used is robust enough for the project being undertaken.

C.

Whether to proactively invest to bring the exposure to risk within tolerable levels.

D.

Whether to use brainstorming or a workshop to decide on the best response.

Question # 46

Which one of the following statements is true?

A.

An increase in project scope is likely to increase project cost.

B.

A decrease in the project time is likely to increase project quality.

C.

An increase in the project quality requirements is likely to decrease project cost.

D.

A decrease in the project cost is likely to decrease project time.

Question # 47

When a project has completed the handover and closure phase:

A.

the project deliverables are ready for commissioning.

B.

the project deliverables are ready for handing over to the users.

C.

the project documentation must be disposed of.

D.

the capability is now in place for the benefits to be realised

Question # 48

One purpose of a typical project business case is to:

A.

carry out earned value analysis.

B.

allocate resources to the project.

C.

analyse cost-benefit of the project.

D.

plan project work packages

Question # 49

The implementation of risk management on A. project requires a cost allocation from the project budget. Which statement describes the most representative return from such an investment?

A.

A benefit to the project if potential opportunities are realised

B.

The cost of dealing with a risk should it occur is usually greater than the cost of managing that risk.

C.

Risk management in the project facilitates team building.

D.

It allows the organisation to assure stakeholders of project compliance with regard to risk management.

Question # 50

Which of the following is not an essential activity to verify the configuration of an output?

A.

Plan configuration management process and activities.

B.

Create records and reports to demonstrate traceability.

C.

Verify integrity of configuration before use.

D.

Dissemination of each configuration item.