Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Managing Contractual Risk

Last Update 9 hours ago Total Questions : 120

The Managing Contractual Risk content is now fully updated, with all current exam questions added 9 hours ago. Deciding to include L5M3 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our L5M3 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these L5M3 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Managing Contractual Risk practice test comfortably within the allotted time.

Question # 11

A buyer and supplier have a contract and the supplier has committed a major breach. However, as they are the sole supplier to the buyer, the buyer has decided not to terminate the contract and instead to work with the supplier to remedy the situation. What is this called?

A.

affirmation of the contract

B.

conflict resolution

C.

awarding damages

D.

assigning liability

Question # 12

Which of the following will you put into box 3?

A.

anticipatory breach

B.

fundamental breach

C.

payment terms

D.

specification

Question # 13

John is a chocolatier and has a big order of Easter Eggs coming up in April. He also creates chocolates to sell all year round in his shop, but Easter Eggs represent a large proportion of his profits each year. John's chocolate making machine has just broken and he has ordered a new one to be delivered in February. However due to a delay, the manufacturer of the new machine can't deliver until May. What course of action can John take?

A.

John can claim for loss of his regular earnings but not for the easter eggs

B.

John can claim for the loss of the Easter Eggs but not his regular earnings

C.

John can claim for both the loss of the Easter Eggs and his regular earnings

D.

John cannot claim for any loss as these are in the future and he doesn't know what these would be

Question # 14

Robert has a contract with Farmer Ted who provides his manufacturing firm with potatoes. There is a contract in place, signed by both parties that Ted will deliver 2 tonnes of potatoes per week. Due to changes in demand, Robert would like Ted to start providing 3 tonnes of potatoes every three weeks. What must be in place for this change to occur?

A.

a variation clause and a new liquidated damage fee

B.

a variation clause and a signed agreement by both parties

C.

a notification of change and adequate compensation

D.

a notification of change and indemnity

Question # 15

What is the first stage in conflict resolution?

A.

assess the impact of the breach

B.

look at remedies available

C.

identify the nature and source of the conflict

D.

decide on the type of conflict resolution approach

Question # 16

Which of the following will you put into box 1?

A.

subcontracting

B.

reputational damage

C.

penalty clause

D.

consequential loss

Question # 17

Which of the following will you put into box 8?

A.

adjudication

B.

arbitration

C.

mediation

D.

litigation

Question # 18

Which of the following will you put into box 2?

A.

anticipatory breach

B.

fundamental breach

C.

payment terms

D.

specification

Question # 19

George is a procurement manager at a manufacturing company and is reviewing a contract he has with a supplier. He notes that there are multiple appendices to the contract and there is no Precedence of Documents. What does this mean for the contract?

A.

all clauses are considered equal

B.

clauses in the contract take precedent over clauses in the appendices

C.

the clauses that come first in the document, take precedent

D.

the contract is not valid

Question # 20

Which of the following processes is the most adversarial?

A.

mediation

B.

litigation

C.

adjudication

D.

negotiation

Go to page: