You'll find that our CA0-001 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CA0-001 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) Certification practice test comfortably within the allotted time.

Question # 4

Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Question # 5

Which of the following risk management processes uses brainstorming as a technique?

A.

Identify Risks

B.

Monitor and Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

Question # 6

What process determines which risks might affect the project?

A.

Qualitative risk analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Quantitative risk analysis

Question # 7

What are three basic types of project phase-to-phase relationships?

A.

Sequential, Overlapping, Non-overlapping

B.

Sequential, Iterative, Overlapping

C.

Sequential, Non-overlapping, Iterative

D.

Iterative, Overlapping, Non-overlapping

Question # 8

Which statement is true about the project management body of knowledge?

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Question # 9

The project management processes presented in the PMBOK Guide should:

A.

Always be applied uniformly

B.

Be selected as appropriate by the sponsor

C.

Be selected as appropriate by the project team

D.

Be applied based on ISO guidelines.

Question # 10

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination