Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

PMI Risk Management Professional (PMI-RMP) Exam

Last Update 12 hours ago Total Questions : 278

The PMI Risk Management Professional (PMI-RMP) Exam content is now fully updated, with all current exam questions added 12 hours ago. Deciding to include PMI-RMP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMI-RMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-RMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Risk Management Professional (PMI-RMP) Exam practice test comfortably within the allotted time.

Question # 1

A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team ' s tasks have yet to be completed.

What should the risk manager do next?

A.

Start a quantitative analysis to understand the impact.

B.

Crash the schedule to mitigate the risk consequences.

C.

Transfer the risk to the external team.

D.

Ask the risk owners to review the risk response plan.

Question # 2

During the project ' s lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?

A.

Carry out the agreed risk response action should the risk occur.

B.

Provide a numerical estimate of the overall effect of risk on the objectives.

C.

Track identified risks and maintain the viability of response plans.

D.

Develop the overall risk management strategy for risk integration. 

Question # 3

A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase. The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded.

Which analysis should the risk manager perform to demonstrate this to the stakeholders ' ?

A.

Monte Carlo analysis

B.

Pareto analysis

C.

Ishikawa analysis

D.

Qualitative risk analysis

Question # 4

The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

What is this an example of?

A.

Risk responses

B.

Risk triggers

C.

Risk registers

D.

Risk categories

Question # 5

Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project ' s budget.

What should the project manager do next?

A.

Request a budget relief using the management reserve.

B.

Conduct a risk reassessment and reserve analysis.

C.

Review the consequences of potential changes.

D.

Coach stakeholders on risk identification practices.

Question # 6

During a project ' s initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk ' s likelihood and impact with the risk manager.

What should the risk manager do?

A.

Assume the vendor will deliver on time and focus only on internal risks.

B.

Allocate contingency funds without first evaluating the risk ' s probability and impact.

C.

Wait indefinitely for the vendor ' s update before analyzing the risk.

D.

Assess the risk using a probability-impact matrix and prioritize it based on its score.

Question # 7

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

A.

Wait until the weather improves before sending the equipment.

B.

Ask the project sponsor to approve shipping the equipment.

C.

Proceed with the planned risk response to move the equipment.

D.

Request the shipment of the equipment to satisfy the client.

Question # 8

.

A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)

A.

Budget variance data from previously completed projects.

B.

Project scope and cost management plans from previous projects.

C.

Lessons learned from similar completed projects.

D.

Previous project risks that may be relevant to this project.

E.

Stakeholder analysis metrics from projects with similar risk profiles.

Question # 9

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X ' s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X ' s project manager avoid this situation in the future?

A.

Prepare a contingency response plan to implement when delays occur

B.

Ask the other project manager to officially confirm the new date in writing

C.

Request that the other project manager be added to relevant reports

D.

Request that the other project manager inform if any additional delays are expected

Question # 10

After completing the sprint on an agile project, a team updates the risk burndown chart and notices that risk exposure has increased to levels that could negatively affect project completion. What should the risk manager do to return the project ' s risk exposure to an acceptable level?

A.

Update the definition of done (DoD) to improve risk management.

B.

Review the acceptance criteria for upcoming stories.

C.

Prioritize risk mitigation stories for the next sprint.

D.

Check stories in the product backlog to identify risks.

Go to page: