You'll find that our CA0-001 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CA0-001 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) Certification practice test comfortably within the allotted time.

Question # 61

With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively. The mean is _____.

A.

30.0

B.

22.5

C.

25.0

D.

27.5

Question # 62

Based on the PMBOK, who is ultimately responsible for the project quality?

A.

Project team

B.

Project manager

C.

QA manager

D.

Validation engineer

Question # 63

How many communication channels will be required in a project in which 5 individual are participating?

A.

10

B.

12

C.

4

D.

5

Question # 64

How many communication channels will be required in a project in which 10 individual are participating?

A.

45

B.

12

C.

10

D.

5

Question # 65

Which of the following is ensuring that all features and functions are included in a product or service

A.

Project scope

B.

Project verification

C.

Project control

D.

Product scope

Question # 66

You are working with an organization and you found that one stakeholder not disclosing all of the costs involved with an upcoming project. Rather, this CAPM is constructing a WBS that does not include all the tasks necessary to get the project done. What you should do?

A.

Talk to the CAPM about the WBS to see if you can rework it to reflect actual costs of the project

B.

Confront the other project manager immediately

C.

Mail t0 PMI headquarters

D.

Ignore it

Question # 67

A change requests can occur due to:

A.

An external event such as a change in government regulation.

B.

An error or omission in defining the scope of the product.

C.

An error or omission in defining the scope of the project.

D.

all of the above

Question # 68

Which of the following plans is not done during the writing of a project plan?

A.

Executive Communication

B.

Risk Management

C.

Quality Management

D.

Scope Statement

Question # 69

Project scope is:

A.

The work that must be done in order to deliver a product with the specified features and functions.

B.

The features and functions that are to be included in a product or service.

C.

A narrative description of work to be performed under contract.

D.

a and b

Question # 70

You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

A.

Schedule

B.

Assumption

C.

Constraint

D.

Planning process

Question # 71

Which of the following must be measured regularly to identify variances from the plan.

A.

Stakeholder requirements

B.

Project performance

C.

Control Schedule

D.

Project controls

Question # 72

A _______ is a series of actions bringing about a result.

A.

Project plan

B.

Process

C.

Schedule

D.

Flowchart

Question # 73

You have a piece of equipment that was purchased for your project recently for $5,000 and is expected to last 5 years in production. At the end of the five years, the expected worth of the equipment is $2,000. Using the straight-line deprecation, what is the amount that can be written off each year?

A.

$600

B.

$1200

C.

$3000

D.

$100

Question # 74

Another term for top down estimating is:.

A.

Analogous estimating

B.

Life-cycle costing

C.

Parametric modeling

D.

Bottom up estimating

Question # 75

You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?

A.

Create WBS

B.

Vei* < fy Scope

C.

Value analysis

D.

Control Scope

Go to page: