Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Project Management Professional (PMBOK 7th Version)

Last Update 13 hours ago Total Questions : 2191

The Project Management Professional (PMBOK 7th Version) content is now fully updated, with all current exam questions added 13 hours ago. Deciding to include PMP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Project Management Professional (PMBOK 7th Version) practice test comfortably within the allotted time.

Question # 51

A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.

What should the project manager do next?

A.

Replan the remaining iterations according to the new installation dates

B.

Update the product backlog m order to address the delays

C.

Review the procurement agreements to address the situation

D.

Find another vendor who can fulfill the delivery dates

Question # 52

A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users.

What should the project manager do next?

A.

Discuss the issue with the team member in a one-on-one meeting.

B.

Ask the team member to justify the delay during a team meeting.

C.

Review the human resources (HR) policies for relevant corrective actions.

D.

Escalate the performance issue to the team member ' s functional manager.

Question # 53

A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.

Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)

A.

Schedule regular meetings with the key stakeholder to provide updates and receive feedback,

B.

Share weekly status reports with detailed information about the project and team performance.

C.

Submit performance reports and task assignments to keep the stakeholder informed.

D.

Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders.

E.

Provide training to the team on emotional intelligence and status reporting techniques.

Question # 54

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?

A.

Conduct a consensus-building session to decide how to approach the next set of work.

B.

Escalate the issue to the product owner for resolution.

C.

Add this conflict to the agenda for discussion at the next daily standup meeting.

D.

Conduct a planning session to decide how to approach the next set of work.

Question # 55

A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory-How should the project manager support their claim to the vendor?

A.

Share unsuccessful results from previous projects with a similar scope

B.

Provide the failed test results along with the agreed-upon acceptance criteria

C.

Show that the acceptance criteria were changed by the vendor without approval.

D.

Document in the risk log that the issues in the system were already identified

Question # 56

Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?

A.

Sign the contract as per the original terms but allow the successful bidder to submit a new contract price.

B.

Amend the contract terms and sign a revised contract with the successful bidder.

C.

Retender the entire scope because the terms of the contract have changed significantly.

D.

Discuss the new terms with the successful bidder to assess its impact on the contract price.

Question # 57

During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?

A.

Update the communication styles for enrolled team members in the communications management plan.

B.

Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM)

C.

Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.

D.

Update the resource calendar for enrolled team members in the resource management plan

Question # 58

A product owner has indicated there is strong customer interest in adding a new set of functionalities to a product. Using agile approaches, the project manager evaluates the new functionalities of the product.

What should the project manager do?

A.

Negotiate with the product owner to determine which functionality should be pushed out of the scope of the project.

B.

Discuss with the team how this change in scope impacts development at the next retrospective to determine next steps.

C.

Negotiate with the product owner to determine what might be removed from the backlog that is of similar size.

D.

Add the functionality to the product backlog for inclusion once a change request is created and approved.

Question # 59

A project manager is leading a project with a risk management plan detailing strategy and actions if any of the identified risks become an issue. One of the identified risks becomes an issue, but the project manager acknowledges that the response considered in the risk management plan may not be the best.

What should the project manager do?

A.

Adopt the action prescribed in the risk management plan since it was agreed to beforehand.

B.

Submit a change request to perform a different issue response than what is registered in the risk management plan.

C.

Escalate the issue to the project sponsor and register the new risk response in the project documents.

D.

Meet with the project team and sponsor to reevaluate all issue responses registered in the risk management plan.

Question # 60

A project is in its fourth iteration out of eight, with a delivery performance of 95%. A project stakeholder asks the project manager about the status of a specific deliverable that is not visible in the status report.

What should the project manager do?

A.

Invite the stakeholder to the next iteration review.

B.

Include the deliverable in the status report and resend it to the stakeholder.

C.

Invite the stakeholder to the next daily meeting.

D.

Schedule a meeting with the stakeholder to review the status report.

Question # 61

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder in order to provide necessary resources. However, the stakeholder is refusing to get involved because the stakeholder believes there is no benefit in using the project deliverable.

What should the project manager do to resolve this?

A.

Meet with the stakeholder to discuss the impact of the deliverable.

B.

Escalate to the project sponsor due to the political nature of the issue.

C.

Consider the stakeholder as a risk and evaluate possible solutions with the project team.

D.

Improve communication with the stakeholder to obtain their assistance in the future.

Question # 62

A project manager has been assigned to deliver a challenging project on time and within budget. The project manager needs to empower the team members by removing organizational impediments and facilitating collaboration.

What should the project manager do to lead the project?

A.

Use a servant leader approach.

B.

Assume the functional manager role.

C.

Perform the project sponsor activities.

D.

Act as the project owner.

Question # 63

During the final iteration of the execution phase, the project has a cost performance

index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.

How should the project manager avoid a budget shortfall?

A.

Follow the risk management plan.

B.

Reduce the team effort utilization.

C.

Look for cost-saving opportunities.

D.

Submit a change request to add to the management reserve.

Question # 64

A project team has developed the initial schedule using a network diagramming method and has arrived at the overall project duration. Upon examining the schedule, the project manager finds that there are several activities that may require buffers to mitigate or eliminate potential scheduling conflicts.

Match the following common terms with their explanations that evaluate the buffers or constraints.

Question # 65

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Question # 66

A project manager is assigned to a project related to taxes, which will be managed

using an agile approach. By reviewing lessons learned from a previous project, the project

manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

A.

Recognize the stakeholder ' s skills are important for the project and evaluate thepossibility of the stakeholder supporting the project team.

B.

Request the functional manager to assign the team from the lessons learned project tothe current project to avoid a learning curve.

C.

Ask the project team to review the lessons learned and have the team contact thestakeholder directly if there are any questions.

D.

Send a request to the project sponsor to hire the stakeholder and have them becomepart of the project team.

Question # 67

After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project ' s schedule and budget. What should the project manager do next?

A.

Perform a qualitative risk analysis and update the risk register.

B.

Submit a change request through the Integrated change control process.

C.

Update the issue log and discuss It in the next steering committee meeting.

D.

Estimate the associated costs and increase the project budget accordingly.

Question # 68

A project has recently Kicked off. The project manager observes that thete are different expectations among the project team members. These growing misunderstandings are affecting team productivity.

Which document should the project managefve?

A.

Project charter

B.

Stakeholder register

C.

Team charter

D.

Project organization charts

Question # 69

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

A.

Motivate the team and deploy the necessary resources.

B.

Find a way to maintain the project schedule.

C.

Impose authority on the project.

D.

Request additional resources from the sponsor and motivate the team.

Question # 70

A project manager has noticed that a critical team member is consistently arguing

with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

A.

Explain the impact of the scenario to the project team member.

B.

Remove the project team member from all future meetings.

C.

Talk to the client privately to highlight the situation.

D.

Recommend a performance improvement plan to the project team member.

Question # 71

A project leader is assigned to a new project and is asked to assemble an effective

five-member agile team. If the project leader has no restrictions, which team should they

choose?

A.

A team whose members work independently and are the best subject matter experts(SMES)

B.

A team whose members have more general aptitudes but like to work individually

C.

A team whose members have different skill sets and are spread out geographically

D.

A team whose members have more general aptitudes and can collaborate on different tasks

Question # 72

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

A.

Workstream leader and project sponsor

B.

Workstream leader alone

C.

Workstream leader and functional manager

D.

Workstream leader and project management office (PMO)

Question # 73

The change control board (CCB) has approved a change request to add a new

component within a product. The operations manager discovers the change after its approval

and complains that the implementation of the change will cause significant disruption to the

production line.

What should the project manager do first?

A.

Escalate the issue to the project sponsor, as the decision to add the component bringsmany benefits even though it will be disruptive to the production line.

B.

Lead a root cause analysis workshop with the design team to identify the failures thatled to the decision to add a component that was not compatible with the productionline.

C.

Meet with the operations manager to explain the background for the change andunderstand the operation manager ' s concerns about the change.

D.

Formally acknowledge the operation manager ' s concerns and raise a new risk that theproject may deliver late and over budget due to manufacturing difficulties.

Question # 74

A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.

What should the project manager do to avoid these challenges?

A.

Increase the project budget by 10% for team-related activities and awards.

B.

Plan to implement team-building strategies throughout the project.

C.

Ask the functional manager to motivate the team outside of the project.

D.

Colocate the team to encourage more motivational team activities.

Question # 75

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal andexternal resource requirements.

B.

Commit each team member ' s time and deliverables and aim for overall projectcompletion.

C.

Continue the project implementation without the site engineers to ensure the scheduleis maintained.

D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.

Question # 76

A project management plan needs to be updated due to recent product requirements changes, but the latest version of the document is missing. What should the project manager do to prevent this from happening again?

A.

Improve the configuration management process

B.

Register an issue for the missing documents

C.

Ensure the lessons learned register is up to date

D.

Review the quality assurance (QA) processes

Question # 77

A product owner asks a project manager for details about products that were added during the last iteration. What should the project manager do to gather this information and send it to the product owner?

A.

Evaluate the sprint backlog

B.

Evaluate the product backlog

C.

Evaluate the sprint increment

D.

Evaluate the product development cycle

Question # 78

During a status meeting, a project manager reported that a project is on track. However, the project sponsor thinks the project is behind schedule because a few tasks have already passed their planned finish dates but are still in progress. How should the project manager revise the report and demonstrate the project is on schedule?

A.

Use a network diagram to show that the delayed tasks are not on the critical path.

B.

Use a network diagram to show the task duration and dependencies among tasks.

C.

Use a Gantt chart to compare the actual schedule with the planned project schedule.

D.

Use a resource histogram to show that the resources are adequate to complete all tasks on time.

Question # 79

A project manager is assigned to a large complex project with cross-functional dependencies. The project enters a new phase requiring new stakeholders to be added with conflicting priorities. How should the project manager ensure successful engagement with the stakeholders?

A.

Invite all stakeholders to status meetings.

B.

Identify and categorize the stakeholders.

C.

Interact individually with the stakeholders.

D.

Recognize the diversity of the stakeholders.

Question # 80

Throughout the project, the project manager consistently checks the work performance data and finds that two stakeholders are not engaged in the project as expected. In addition, another stakeholder always complains that they are often involved in irrelevant meetings. What should the project manager do first?

A.

Communicate regularly with stakeholders and address issues.

B.

Perform a root cause analysis using the Ishikawa method.

C.

Review and update the stakeholder engagement plan.

D.

Remove those stakeholders from unwanted meetings.

Question # 81

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?

A.

Modify the daily standup meetings to include project status reporting.

B.

Escalate the issue to the change control board (CCB) and ask for advice.

C.

Adopt the role of supporting and empowering the project team to do the work.

D.

Change the approach for the project to a predictive approach.

Question # 82

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

A.

Review the work allocation and reassign some tasks to shorten the critical path.

B.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

C.

Ask the team members to work overtime to finish the tasks on time according to the schedule.

D.

Keep the task assignments unchanged since the project management plan has been approved.

Question # 83

A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?

A.

Determine a leadership style that is suitable for that location.

B.

Check if resources from headquarters can also be assigned to the project.

C.

Mentor the team members to perform project management.

D.

Assign a local resource to manage communication with the team.

Question # 84

A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed. What should the project manager do to deliver business value to the client?

A.

Use management reserve and crash the schedule

B.

Implement an agile project delivery approach

C.

Explain the need to follow the quality assurance (QA) schedule to the customer

D.

Adopt an incremental project delivery approach

Question # 85

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

A.

Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Question # 86

Three months after creating a project schedule, the scope of a project significantly changed, resulting in a schedule rebaselining. One month after rebaselining, the project is two weeks behind schedule with a cost performance index (CPI) of 0.93. What should the project manager do to help get the project back on schedule?

A.

Crash the project with two additional contract resources for the newly identified tasks.

B.

Meet with the project stakeholders and inform them that the project is going to be delayed.

C.

Manage the schedule’s critical path, as this was an approved scheduling change.

D.

Review the project schedule and find ways to fast-track the overall project schedule.

Question # 87

A company wants to show the commercial advantages of a product in a competitive market. They commissioned a project team to create a prototype. The team is building the prototype incrementally.

What should the project manager set as a priority?

A.

Implement the plan-do-check-action (PDCA) cycle.

B.

Deliver business value as soon as possible.

C.

Emphasize the use of Kanban methods.

D.

Ensure that the project sponsor knows the schedule.

Question # 88

In a fixed-budget project, the team has received a prioritized list of requirements and has nearly completed the first iteration. The CEO has decided to redirect the team to focus on creating a presentation for their upcoming technology summit. The CEO is not flexible about this request.

Which two actions should the project manager take? (Choose 2)

A.

Request the CEO to assign some of the functional team members to work on the presentation.

B.

Ask the team to work overtime to make up the time lost by supporting the technology summit.

C.

Determine a new target completion date for the project based on the redirection of the team.

D.

Divide the team to continue working on both the presentation and the project work.

E.

Attempt to complete the presentation work alone so that the timeline is not negatively impacted.

Question # 89

During the execution stage, the project manager discovered that one team member is not able to complete their work on time and is running later than expected. This delay may potentially impact a project milestone.

What should the project manager do first?

A.

Request the team member ' s manager to find a solution.

B.

Discuss with the team and assess the reasons that led to the delay.

C.

Discuss with senior management and seek their guidance.

D.

Assign more resources form other teams on the late work.

Question # 90

Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two

members are tense around each other and are taking everything personally.

What should the project manager do?

A.

Help the team members to resolve the conflict in a way that results in the best team performance.

B.

Offer a compromise that is acceptable to both team members, even if it may not be the best solution.

C.

Understand each team member ' s argument and select the one that results in less risk to the project.

D.

Send both team members to the human resources (HR) department for an acceptable resolution.

Question # 91

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client ' s needs.

What should the project manager do?

A.

Travel to the development team ' s office to push the schedule.

B.

Set up a meeting with key stakeholders to clarify requirements.

C.

Escalate to the project steering committee and request additional time.

D.

Create prototypes with the development team to confirm requirements.

Question # 92

A project manager had to schedule additional planning sessions to add requirements from an international stakeholder. The stakeholder expressed concern about the product not meeting the client ' s needs.

Which factor should the project manager have considered when developing the product?

A.

Stakeholder ' s location

B.

Responsibility matrix

C.

Stakeholder ' s needs

D.

Availability of resources

Question # 93

A project manager is leading a software development project with agile practices and has outsourced work to three well-qualified subcontractors. Over time, problems arise related to supply-chain management, and the project manager considers replacing the subcontractors with new suppliers. What should the project manager have done to avoid this problem?

A.

Hired more Scrum Masters so every Scrum Master manages one supplier.

B.

Escalated the issue to the product owner to seek possible solutions.

C.

Engaged the suppliers by category and validated the strategy with stakeholders.

D.

Created user stories for the suppliers and saved their qualification records to the backlog.

Question # 94

A project manager presents the project schedule to the customer, including the detailed phases for the whole project. The customer complains that the project timeline is longer than expected and does not want to wait until the end to see results. What should the project manager do first?

A.

Adjust the project schedule to include additional resources for all project tasks.

B.

Submit a change request to extend the project timeline.

C.

Evaluate the impact of changing the project framework to an incremental approach.

D.

Apply crashing techniques to all activities in the project schedule.

Question # 95

A project manager is leading a team that is delivering new software to a finance team. The new software will streamline the finance team’s monthly closing activities and reporting.

What should the project manager use to promote knowledge transfer for the new solution?

A.

Project documents

B.

User handbook

C.

End-user training

D.

Support portal

Question # 96

A project manager is leading a team delivering new software to a finance team. The new software will streamline the finance team’s monthly closing activities and reporting. What should the project manager use to promote knowledge transfer for the new solution?

A.

Support portal

B.

User handbook

C.

Project documents

D.

End-user training

Question # 97

A key stakeholder asks the project manager to complete all deliverables sooner than the agreed-upon schedule. The project is halfway complete and currently has a schedule performance index (SPI) of 0.9 and a cost performance index (CPI) of 1. What should the project manager do first before committing to the stakeholder?

A.

Add more resources to complete the remaining deliverables early.

B.

Review and analyze the risks associated with compressing the schedule.

C.

Prioritize critical activities and skip noncritical activities.

D.

Perform several activities in parallel to compress the schedule.

Question # 98

A project manager is preparing a large and complex international project. In order for the team to work well together in a virtual environment, the project manager needs to set up ground rules for good communication.

What should the project manager do first?

A.

Establish a communication channel.

B.

Create a communication protocol.

C.

Develop the stakeholder analysis.

D.

Distribute the risk register.

Question # 99

Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.

What should the project manager do next?

A.

Discuss the topic with the team members in a team meeting.

B.

Replace the two team members with other resources.

C.

Contact the functional managers of each team member.

D.

Schedule a meeting with both team members.

Question # 100

During project execution, a project manager is leading the team to work on the project schedule. During a meeting, the team has difficulty understanding the complexity of a task and is unable to provide an estimate for the required resources.

What should the project manager do first to resolve this issue?

A.

Register the issue as a risk in the risk register.

B.

Report to the sponsor that there is a new challenge in the project.

C.

Engage an external expert to provide the estimation.

D.

Refer to the organization ' s lessons learned from past projects.

Go to page: