Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Project Management Professional (PMBOK 7th Version)

Last Update 13 hours ago Total Questions : 2191

The Project Management Professional (PMBOK 7th Version) content is now fully updated, with all current exam questions added 13 hours ago. Deciding to include PMP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Project Management Professional (PMBOK 7th Version) practice test comfortably within the allotted time.

Question # 151

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

A.

Recruit the best resources within the organization to be part of the virtual team

B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls

C.

Identify the types and quantities of resources required for each work package or activity

D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress

E.

Verify if team members are on more than one team and cannot devote enough time to this team

Question # 152

A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.

What should the project manager do to address this issued

A.

Schedule a meeting with critical stakeholders to review the issue and decide on the next steps

B.

Put the project on hold and release the resources until the issue is resolved

C.

Inform the product owner and log the issue in the risk register to monitor closely for next steps.

D.

Contact the company that owns the patent of the similar tool to compare the similarities and differences with the current project.

Question # 153

A project manager has received an updated earned value analysis report The following are the key findings from the report

•Budget at completion = USS1 million

•Earned value = US$0 7 million

•Actual cost = US$0 75 million

•Cost performance index = 0 933

Based on this information, what should the project manager conclude about project performance ' ?

A.

The project will be completed exactly as planned

B.

The project will be easier to complete than planned

C.

The project will be difficult to complete as planned.

D.

The project will not be completed as planned

Question # 154

An organization has historically executed most projects using a predictive approach The organization now wants to change over to an agile approach

Which strategy will be useful to effectively help prepare the organization for this change?

A.

Create a task force of executives who will monitor agile projects on a daily basis

B.

Add multiple layers of managers who will be accountable for the agile execution

C.

Improve organizational readiness by addressing impediments to agile in the organization.

D.

Take a big bang approach of moving the whole organization to agile at once

Question # 155

The customer ' s project manager changes during the final stage of a project How can the project manager avoid a project closure delay’

A.

Update the stakeholder engagement plan

B.

Review the latest project status report and update the stakeholders

C.

Escalate the case to the customer ' s management team

D.

Issue the project payment invoice to the customer in advance

Question # 156

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client A potential design problem is identified by the development team After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed The design is already approved.

What should be the project manager ' s next steps?

A.

Conduct a proof of concept to make sure there are no problems in the revised design

B.

Amend the design specifications and pass them to the development team for reprogramming

C.

Make a change request and get format approval from the project owner

D.

Inform the client of the problem and follow the change request process

Question # 157

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

A.

Perform a risk assessment and define a risk response action plan.

B.

Proceed with the project using management reserves to cover any delays or losses.

C.

Propose a pause in this phase to save labor costs and asset depreciation.

D.

Establish new partnerships with other suppliers in anticipation of any delays.

Question # 158

A project manager is responsible for building a bridge The high-level elements of the project are handled using a predictive approach The software responsible for retracting the bridge has been developed based on agile principles During software development, the workflow is often interrupted by various delays or impediments due to lack of information

How should the project manager handle this situation?

A.

Apply lean manufacturing to limit the team’s work

B.

Increase retrospectives to deliver results fast

C.

Make work visible using kanban boards.

D.

Incorporate small batches of work into the project

Question # 159

During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path

What should the project manager do to avoid future delays?

A.

Submit a change request.

B.

Add additional resources to the project

C.

Update the scope of work.

D.

Review the risk management plan

Question # 160

During the third iteration, the team encounters a major delay that has not had significant improvements over the last few weeks What should the project manager do?

A.

Retrospect frequently and suggest improvements.

B.

Incorporate a predictive approach for this element.

C.

Implement mitigation strategies for this element

D.

Request additional team members to help with improvements

Question # 161

A project manager receives a voicemail from a business analyst on the project team The business analyst indicates that an internal stakeholder is upset that they were not included before the project began The stakeholder is asking for an addition to the requirements traceability matrix

What should the project manager do to improve the stakeholder relationship?

A.

Consult the project scope document to make sure the addition is in scope.

B.

Update the stakeholder engagement plan to ensure the stakeholder is included in the project stakeholder list

C.

Initiate a project change request so the change control board (CCB) can decide if it is in scope.

D.

Engage the stakeholder to solicit more information before responding to the request

Question # 162

A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task

What should the project manager do?

A.

Ask the team member to follow the approved communications management plan to communicate their issue

B.

Schedule a meeting with the concerned team member to review and update the issue log together

C.

Review the risk register with the team member to find the proper response action for this issue.

D.

Ask the team member to raise a change request to assess the issue in detail

Question # 163

Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?

A.

Sent the meeting minutes to the stakeholders after the kick-off meeting

B.

Reviewed all the approvals immediately after the kick-off meeting was over

C.

Ran separate kick-off meetings for each culture and time zone

D.

Validated each stakeholder ' s understanding during the kick-off meeting

Question # 164

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals

What two options will help the team initially address this obstacle? (Choose two)

A.

Escalate the issue to the project sponsor.

B.

Review and update dependencies

C.

Schedule a retrospective.

D.

Conduct a root cause analysis.

E.

Create a risk management plan.

Question # 165

A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments What should the project manager suggest that the product owner do next?

A.

Ensure that the impediments are captured and prioritized based upon the highest valued features

B.

Estimate the financial impact of the impediments and request additional funding

C.

Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment

D.

Capture the impediments and inform management that their assistance is neededin resolving the impediments

Question # 166

In a financial company, a strategic project has been planned to use a predictive approach. During project planning, the product leader requests

that milestones be submitted for review. There is a defined scope and an established deadline to conclude the project.

What should the project manager do first to meet the product leader ' s expectations?

A.

Change the project charter to indicate that the approach will be different.

B.

Inform the product leader that they must wait until the end of the project.

C.

Meet with the software team to review the possibility of monthly milestone reviews.

D.

Modify the project management plan to use an agile framework to incorporate milestones.

Question # 167

A project team Is trying to meet the milestone target dates in order to receive a bonus promised by the project sponsor. Unforeseen challenges and poor communication among the team members resulted in mistakes and delays. Tensions are high, and the sponsor is concerned.

What should the project manager do?

A.

Discuss with the team how the project objectives can be met.

B.

Request that the sponsor increase the bonus for high performers.

C.

Schedule a team-building activity to boost the team ' s morale.

D.

Organize a team meeting to remind the team of the ground rules.

Question # 168

An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.

What should the project manager do?

A.

Establish a project schedule

B.

Assign a team leader

C.

Recognize the team ' s contributions

D.

Establish a team charter

Question # 169

A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager ' s peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.

What should the project manager do first?

A.

Register a new risk in the risk management plan.

B.

Ask for additional resources and review the project estimate.

C.

Review organizational process assets (OPAs) and perform analogous estimating.

D.

Complete a bottom-up estimation for the project activities.

Question # 170

A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team ' s time.

What should the project manager do?

A.

Raise a change request.

B.

Purchase the application.

C.

Create a decision tree.

D.

Analyze assumptions and constraints.

Question # 171

A team needs to implement a mandatory compliance regulation in a product, which is required for its release. While nearing the product release, when completeness was

being verified, it was found that the compliance part was not implemented in the project.

What should the project manager do next?

A.

Get an exception approval from the legal team.

B.

Request the team to implement the compliance.

C.

Ask the stakeholder to descope the compliance.

D.

Obtain approval from management and release.

Question # 172

Anew engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the

project manager before acting.

What should the project manager do?

A.

Obtain related training for the new team member.

B.

Determine the appropriate level of decision-making authority and empower the engineer.

C.

Make all of the decisions for the engineer in order to keep the workflow on track.

D.

Replace the resource with an experienced engineer.

Question # 173

A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.

How should the project manager handle this situation?

A.

Remind the contractor to join the meetings and submit their report as this is their commitment.

B.

File a claim for not fulfilling the contract terms in accordance with alternative dispute resolution.

C.

Compromise with the contractor to only attend the weekly meetings without submitting the reports.

D.

Assess the situation as a risk and reach out to the contractor to check the origin of this resistance.

Question # 174

After a project review meeting, a key stakeholder tells another stakeholder that they do not trust the project status report. The second stakeholder approaches the project manager and mentions the conversation.

What should the project manager do?

A.

Request that the sponsor ask the key stakeholder to be attentive during the project review meeting.

B.

Present the status report in a chart and assume that everyone understands the report.

C.

Email the status report to all stakeholders and ask them to review it and provide feedback.

D.

Schedule a meeting with the key stakeholder to address the issue and obtain direct feedback.

Question # 175

A project manager has been tasked with developing a project schedule with fully detailed requirements. The project manager reaches out to subject matter experts (SMEs) for their initial thoughts on task duration. The project manager is concerned when these estimates appear to differ significantly. What should the project manager do to help with the estimate development?

A.

Ask the SMEs to hold up cards that show their estimate, discuss the highest and lowest estimates, and then estimate again.

B.

Recommend using an iterative approach, with a focus on estimates, that the SMEs agree with.

C.

Use historical information to help guide the estimates that were proposed by the SMEs.

D.

Escalate to the project sponsor and explain the differences in the estimations coming from the SMEs.

Question # 176

In an ongoing project, stakeholders have been approaching team members for status

reports and changes without consulting the project manager. What should the project

manager do to ensure a successful project?

A.

Send the project charter to all stakeholders for information.

B.

Send an email to all stakeholders directing them to approach the project managerdirectly.

C.

Review the stakeholder engagement plan and inform the stakeholders.

D.

Review the change management plan and ask the change control board (CCB) to beinvolved.

Question # 177

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Question # 178

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

A.

Provide mentoring for the key team members on agile practices and support the teamwith training and encouragement.

B.

Create an agile conduct guideline and ensure that all team members follow the rulesstated in the document.

C.

Replace the key team members with new resources who are already aware of the agilemindset.

D.

Provide directions to the team members on how to accelerate the company ' stransformation, bringing the project back on track.

Question # 179

A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?

A.

Add the situation to the project risk register to be managed

B.

Identify competitors that are qualified to replace the current supplier

C.

Inform the purchasing department that manages the supplier relationship

D.

Use the issue log to record the situation immediately

Question # 180

A project team has transitioned to full-time remote working. The project manager

started noticing that some team members have not been completing their assigned tasks by

the planned dates despite reminders during weekly team meetings. This has the potential for

delaying the project delivery.

How should the project manager resolve this situation?

A.

Communicate the delivery dates twice a week to the team members to ensure timelydelivery.

B.

Set up review sessions with each of the team members to identify the root cause ofdelays.

C.

Mentor the team members to work in a remote work environment to ensureproductivity.

D.

Talk to the resource managers regarding the delay and request additional resources

Question # 181

An agile project has a documented list or requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.

What should the project manager recommend?

A.

Ensure the product owner determines the priority based on a product roadmap. release plan, and iteration plan.

B.

Ask the team to prioritize the high-priority items based on what they feel is a logical sequence to build.

C.

Ask the team to prioritize the high-priority Items based on the release plan and what allows tor testing most effectively.

D.

Discard the current categorization of requirements as high, medium, and low and prioritize numerically.

Question # 182

During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

A.

Allow the agile team to decide what they are able to deliver in each iteration

B.

Ask the team for additional feedback and add tasks to the task board,

C.

Hold a brainstorming session to identify the root cause of the complaints.

D.

Document the customer ' s complaints and critical issues in the issue log.

Question # 183

A company ' s project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has

identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.

What should the project manager do first?

A.

Investigate the reasons for the disagreement to understand the gap among the stakeholders and search for consensus.

B.

Discuss the situation with the stakeholders to evaluate other adaptive tools for the project.

C.

Schedule training sessions for the stakeholders on the benefits of the adaptive tools.

D.

Update the risk register and escalate the disagreement to the project sponsor and distribute the status to the team.

Question # 184

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?

A.

Fast track this dependency to avoid delaying the project.

B.

Perform Integrated Change Control.

C.

Include the dependency in the project schedule.

D.

Ask IT to prioritize the needed system to meet the schedule.

Question # 185

A technology project is delivering new functionality on a new platform. Several team resources are starting to train their teams, but they are asking questions about the training that the project will provide.

What should the project manager ' s first action be?

A.

Indicate that on the new technology is the functional manager ' s responsibility.

B.

Review the project charter to determine if the training is in scope and, if not, put in a change request.

C.

Consult with the organizational change management specialist as to what the training plan includes.

D.

Document the skill requirements for the product to determine what training is needed.

Question # 186

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.

What should the project manager do next?

A.

Validate if the project charter changed from the original one.

B.

Meet with these stakeholders to review the project charter.

C.

Check if these stakeholders attend regular project meetings.

D.

Review the project charter to validate this claim.

Question # 187

At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting

with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.

What should the project manager do to assess the priorities and meet the new objective?

A.

Submit a change order request with the new project objective to the project management office (PMO).

B.

Initiate a crashing routine to gain extra time for the added feature.

C.

Communicate the results and negotiate the needed resources and time with the stakeholder.

D.

Ask the project team to work overtime in order to accommodate the new changes.

Question # 188

A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.

What should the project manager do to address this issue?

A.

Request that the project team change their task deliverables to reflect the project sponsor ' s requirements.

B.

Set up a daily standup and request that the project sponsor attend to understand the project ' s tasks and deliverables.

C.

Ask the project team to compile a project scope document and obtain approval from the project sponsor.

D.

Facilitate a stakeholder alignment session so that the team and project sponsor are in agreement with the deliverables.

Question # 189

A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.

What should the project manager do next?

A.

Ensure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.

B.

Consider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.

C.

Document the kick-off meeting and close out the planning phase after the meeting is held.

D.

Limit to one kick-off meeting in the project ' s first phase in order to control the budget.

Question # 190

A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager ' s location. The project has a strict

schedule and budget, and the project manager is concerned about their ability to deliver it.

What should the project manager do?

A.

Request a budget extension to get local resources experienced in agile.

B.

Plan to have the agile resources temporarily relocate to the project manager ' s location.

C.

Engage the agile resources through video conferencing on a daily basis.

D.

Advise the sponsor that the project will be delayed as agile training will be required.

Question # 191

When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined. What should the project manager do?

A.

Work with the business analysts to track and collect the missing data and build the KPIs.

B.

Coordinate with the benefit owner to track and collect the missing data and build the KPIs.

C.

Forward the issue to the benefit owner and ask them to collect the missing data and build the KPIs.

D.

Ask the program manager to track and collect the missing data and work to build the KPIs.

Question # 192

A company just started managing a project using an agile approach Due to this change, the general manager is worried about the scope definition process for upcoming projects What should the project manager do to ensure the project scope is completely defined?

A.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations

B.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk

C.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

D.

Ask the general manager to review every requirement to ensure an projects will deliver the requested products

Question # 193

A business transformation project has a four-phase delivery plan. The project team has successfully delivered one phase of the project.

To further enhance team performance and empower team members, which two actions should the project manager take? (Choose two)

A.

Encourage team members to cross-check decisions with the project manager.

B.

Vet all of the decisions before execution.

C.

Allow team members to make limited decisions.

D.

Organize and assign team members to tasks where they have strengths.

E.

Support team members to make decisions in their areas of strength.

Question # 194

A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.

What should the project manager do next?

A.

Suggest that the team member contact the IT department.

B.

Facilitate a priority resolution of the issue with the IT department.

C.

Update the issue log and escalate the problem to the product owner.

D.

Ask the other team members to step in and do the work.

Question # 195

An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.

What should the project manager, who is responsible for this project, do to mitigate this risk?

A.

Ensure that the executive leadership team approves all scope that is being proposed by the multiple agile teams to avoid misalignment.

B.

Propose a governance model that empowers the teams while providing the necessary oversight to the executive leadership team.

C.

Propose a multilayered gate system based on risks and financial expenditures, involving the executive leadership team as needed.

D.

Assure the executive leadership team that the current governance model will not be affected by the agile approach.

Question # 196

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

A.

Hold an emergency project team meeting to discuss the situation.

B.

Ask the human resources (HR) manager for an external replacement.

C.

Log the situation in the issue log.

D.

Update the key stakeholders on the issue.

Question # 197

A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received, demanding that the project be stopped.

What should the project manager do first?

A.

Register the issue and escalate it to the project sponsor.

B.

Execute the contingency plan defined in the risk management plan.

C.

Meet with the project stakeholders to define a mitigation plan.

D.

Estimate the cost of changing the project location.

Question # 198

A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.

How should the project manager plan and manage the project?

A.

Refuse to manage the project as there is too much risk in developing this kind of project without a product owner.

B.

Define the project ' s requirements, prepare a long-term detailed plan, and manage the project according to it.

C.

Convince the client that a product owner is needed, as the project manager is not able to run an agile project without all the relevant roles in place,

D.

Agree up front on a minimum viable product (MVP), establish deadlines for review, and run the project with a backlog and weekly sprints.

Question # 199

A project manager who Is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder ' s current role, previous and current projects in which they participated, and their level of organizational influence.

In what type of analysis should the project manager use this information?

A.

Regression analysis

B.

Stakeholder analysis

C.

Qualitative risk analysis

D.

Decision tree analysis

Question # 200

A team is developing an experimental program to be used by the public. What should

the project manager do to ensure the desired benefits are achieved?

A.

Ensure that the project team fully tests the program.

B.

Ensure a review is done with a representative group of users.

C.

Meet with government officials to review policy requirements.

D.

Document the features fully and update the specifications.

Go to page: