Last Update 12 hours ago Total Questions : 2191
The Project Management Professional (PMBOK 7th Version) content is now fully updated, with all current exam questions added 12 hours ago. Deciding to include PMP practice exam questions in your study plan goes far beyond basic test preparation.
You'll find that our PMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Project Management Professional (PMBOK 7th Version) practice test comfortably within the allotted time.
A project manager is leading a project and is asked to negotiate on behalf of their organization. The organization requires that three quotes from different suppliers be acquired prior to submitting a purchase request to the finance department. What should the project manager do to align with this requirement?
A newly hired team member just joined the project team and reports directly to the
project manager. In the first week, this new member tells the project manager that there is a
task priority conflict with hard, dependent tasks on the critical path.
What should the project manager do to handle the conflict?
During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project ' s key performance indicators (KPIs). This team has delivered good performance on similar projects in the past
What should the project manager do next to improve this situation?
The operations director complains to the CEO about the outcome of a project ' s first sprint The operations department will not be able to support a new product due to poor performance indicators The project team facilitator asks for feedback from the project team and is informed that performance information is available in the application server log
How should this complaint be addressed?
A company is planning a digitization project. Which action should the project
manager take first when defining the project scope?
Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?
An organization that is running several simultaneous projects suddenly experiences a surge of resignations, leading to a lack of talent. Consequently, some of the projects have been missing key milestones. What should the project manager do to recover from the delays?
A project management plan needs to be updated due to recent product requirements changes, but the latest version of the document is missing. What should the project manager do to prevent this from happening again?
Five vendors are contributing to a project with an impending deadline. Two vendors are behind on their deliverables and rarely provide status updates. What should the project manager do?
A project manager is working on a large event and developing budgets for sign-off. The stakeholders and project sponsor are all working remotely using various tools to ensure that all documentation is tracked and handled discretely and appropriately. The primary stakeholder has missed several deadlines for the milestone sign-offs, resulting in the project manager being forced to find alternative suppliers for items, now at higher costs. When questioned regarding the delays, the stakeholder says the notifications hadn’t appeared in their email inbox. How should the project manager proceed?
A project manager is leading a hybrid project in which one technical team executes tasks using an agile approach, while a second team executes other tasks using a predictive framework. These teams are struggling to cooperate effectively, and several delays have occurred in transmitting information and coordinating activities.
What should the project manager do?
In a project management team meeting, one of the team members always argues with the project manager about the objective, timeline, and deliverable of any assigned task.
What should the project manager do to manage this conflict?
A project manager is working in a constantly changing business environment. In order to address this situation, the project manager has decided to use a collaborative leadership style.
Which landscape describes the project environment?
A project manager is managing a project that will engage resources from multiple countries in different time zones. What should the project manager do to ensure that team members are effective?
A project is on its third iteration out of nine. During the daily meetings, the project team realizes that some deliverable approvals are delayed because a key stakeholder is out of the office.
A project management office (PMO) is following the execution of an organization ' s critical project. Some of the project phases are experiencing serious delays due to an international supply chain crisis. Project team members suggested revisiting the planned project phases to maintain the project ' s value delivery.
What should the project manager do?
During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.
What should the project manager do next?
During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.
How should the project manager properly address this situation?
A project is impacting several business units with different expectations and priorities. The project manager leading this project is meeting every month with each of these groups individually. During these meetings, each group has expressed dissatisfaction with the project and uses every opportunity to replace other groups ' priorities with their own.
What should the project manager do to address these challenges?
An important project to build a new airport was suddenly stopped because of the complaints from residents in the surrounding communities. The residents stated that they were not consulted and that the project would cause ecological and pollution damage.
What should that project manager have done first in order to avoid this situation?
A company is working on the prototype of a new contract document that includes visual elements. The product owner shared the project sponsor ' s feedback about the elements to be included, but the project team pushed back. However, when the project sponsor spoke with the team, they confirmed that all of the changes are possible.
How should the project manager mitigate this situation?
A project manager is asked to manage an agile project, allowing the company to comply with a new upcoming regulation. After the project kickoff, the scope is modified to have the project team work on specific tasks, while a global team will manage the program for several countries in parallel. The project management plan has not yet been shared, and the deadline to complete the project is fixed.
What should the project manager do to handle the scope change?
A project team used agile approaches to create a minimum viable product (MVP). Currently, the team is discussing the possible next steps.
What should be the next step?
A project team is experiencing communication issues during project execution. The project manager realizes that the communications management plan needs to be reviewed.
Which are three fundamental actions the project manager should take? (Choose 3)
A project manager is working on a global project and realizes that one team member is not performing as expected. The project manager meets with the team member to find out what is causing this low performance. The project manager discovers the team member is experiencing conflict and feels uncomfortable with the team. The team member then asks to be moved to another project.
What should the project manager do?
Customers are concerned about the quality of an interim software system for a project. The quality control team has approved the software, but the customers are complaining that some functions do not comply with the requirements.
What should the project manager do to prevent this from happening again?
A project manager who has been working on an ongoing volatile project is retiring. A new project manager is collaborating with the retiring project manager to ensure a smooth transition.
What should the new project manager first discuss, review, and clarify during the transition meetings?
A project manager is working on an ongoing construction project. The designer notifies the project manager about materials that were not included in the budget due to a technical mistake.
What should the project manager have done to avoid this situation?
A project manager was appointed to lead an already approved project. While reviewing the benefits management plan, the project manager finds out that the information about the forecasted value of the project may not be accurate.
What should the project manager do?
During a meeting with the customer, it was observed that the features delivered during the last few iterations were not meeting the planned expectations.
What should the project manager do?
A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time
What should the project manager do next?
A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.
What should the project manager do in this scenario?
A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.
What should the project manager do?
An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but
the agile coach and technical writer feel that is an inconvenient time for them.
How does the project lead ensure adherence to agile practices?
A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?
A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?
A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity
issues joining team calls during the day.
What should the project manager do?
A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay
What should the project manager do next?
An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story
What should the agile leader do1?
project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team ' s performance?
A project manager is leading a contract for a new market that was awarded to their company. The client has the desire to jump-start the market with informal sector traders. What should the project manager do?
A project has a very demanding and sensitive business stakeholder who functions as a subject matter expert (SME). The project manager has assigned two different team members to work with the stakeholder. However, both team members have complained that the stakeholder is difficult to work with.
What should the project manager do first?
A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director ' s reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.
What should the project lead do?
A transformation project that is composed of agile streams has come to an end.
How should the project manager collect the experience gained during this project?
In an ongoing project, there is an argument between two subject matter experts (SMEs) on what the correct approach to design should be. The project manager suggests that the two SMEs meet and come to a consensus.
Which conflict resolution approach did the project manager use?
A team member is not getting along with one of the project sponsors. The sponsor has requested to move the team member to another project.
What should the project manager do next to resolve the situation?
A multinational company is embarking on an ambitious organizational change project. The objectives of the project include the complete transformation of the organization ' s structure, role catalog, and global locations in which supporting services are to be delivered.
What should the project manager advise as an essential component of the project?
In a hybrid project, the project manager has identified a few stakeholders. According to the stakeholder matrix, the head of development has a high rating of power/influence and a high likelihood of conflict.
Which action should the project manager avoid?
The key stakeholder of an agile project has low visibility of the project ' s progress. The stakeholder expresses a concern to the project manager about whether or not the scope is moving in the right direction.
What should the project manager do?
A project lead has asked a project team to update a 200-page project report and send it to the project sponsor. The team mentioned that nobody reads the report and it takes time away from higher priority work. The project lead responded that they have to show all the work that they performed in every iteration.
What should the project lead do first?
