You'll find that our Prince2-Foundation exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these Prince2-Foundation sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PRINCE2 7 Foundation written Exam practice test comfortably within the allotted time.

Question # 131

Identify the missing words in the following sentence.

The role of [ ? ] is assigned to the project manager if it is not allocated to another person.

A.

change authority

B.

project assurance

C.

project support

D.

senior user

Question # 132

The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.

In which step of the ‘issue management technique should the change authority request this information?

A.

Deciding on changes

B.

Implementing changes

C.

Assessing issues

D.

Capturing issues

Question # 133

Which statement about the 'manage by stages’ principle is CORRECT?

A.

The project board should authorize multiple stages at the same time

B.

The end of a stage should provide a control point for the project board

C.

A project should have fewer, longer stages when the risk exposure is high

D.

A project should have separate stages to plan, deliver and close the project

Question # 134

Which is an internal factor to consider when tailoring PRINCE??

A.

The safety legislation

B.

The environmental standards

C.

The industry's regulations

D.

The organization's procedures

Question # 135

When does the 'directing a project' process start?

A.

When the project manager submits the project brief for approval

B.

When the request to authorize a project is received

C.

After the project has been authorized by the business layer

D.

After the project mandate has been received

Question # 136

Which should define how tools will be used to support the information needs of the project team?

A.

Digital and data management approach

B.

Quality management approach

C.

Issue management approach

D.

Commercial management approach

Question # 137

Which control is time-driven?

A.

The creation of a highlight report

B.

The completion of the PID

C.

The creation of an exception report

D.

The end of the financial year

Question # 138

Which TWO are objectives of the 'closing a project’ process?

1. To confirm to the project board that each stage’s products are approved

2. To review whether the project was delivered within time and cost tolerances

3. To confirm whether operational staff are happy to take ownership of the products

4. To confirm that there is authority to close the project

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question # 139

The senior user needs to ensure that the outputs will be used effectively to achieve the outcomes and realize the benefits.

Which element of effective business case management is the senior user applying?

A.

Estimating the cost of the project product

B.

Establishing business justification

C.

Planning benefit reviews during the project

D.

Aligning products to business objectives and tolerances

Question # 140

Identify the missing word(s) in the following sentence:

[ ? ] dependency is one between two products of a project, over which the project team has control.

A.

An internal

B.

A schedule-driven

C.

An external

D.

A resource-driven