You'll find that our PMI-002 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-002 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) Certification practice test comfortably within the allotted time.

Question # 4

Which of the following situations will cause schedule activity duration estimates to directly influence the cost estimates EXCEPT:

A.

When resource cost rate information is unavailable from commercial databases

B.

When resources are applied per unit of time of duration of schedule activity

C.

When union labor with regularly expiring collective bargaining agreements are involve

D.

When seasonal cost variations are involve

E.

When project budget includes interest rate changes

Question # 5

You are project manager and the monthly report to the client showed zero schedule variance. However, member of the team know that a milestone has been missed which will cause an overall delay to the project. Which one of the following is being inadequately reported?

A.

Communication plan variance

B.

Resource management plan

C.

Critical path status

D.

Risk analysis

Question # 6

Your project sponsor has asked you to produce a Risk Management Plan for your current project. Which of the following best describes the plan you should adopt for your project?

A.

The plan must include the predefined risk management policies as they relate to the organization

B.

The plan must ensure that the level of details and risk management efforts are commensurate with the level of risk and importance of the project

C.

The plan must be predefined templates as defined by the organization

D.

The plan must include the predefined roles and responsibilities as they relate to risk management.

Question # 7

What is the BEST way to accomplish resource planning?

A.

Identify required resources and allocate them to all project activities.

B.

Identify required resources in the project charter.

C.

Identify available resources and allocate them to all activities in the current phase of the project.

D.

Identify the resources that performed past similar projects, and allocate them to all project activities.

Question # 8

Which statement is not true regarding the issue logs?

A.

Issue logs are written logs that document person responsible for resolving for specific issue by a target date.

B.

Issue logs are tool of Manage Stakeholder Expectations process.

C.

Issue logs are tool of manage project team process.

D.

Issue logs describe the ground rules and conflict management procedures to manage the project.

Question # 9

The work breakdown structure:

A.

Is used to break down the project Into manageable pieces

B.

Is set and does not change throughout the project

C.

Is needed as part of the project charter

D.

None of the above

Question # 10

Estimate At Completion (EAC) is a periodic evaluation of total:

A.

Forecasted project cost.

B.

Cost of the unfinished work.

C.

Resources projected at project complain

D.

Value of work performed to date.