You'll find that our PMI-002 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-002 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) Certification practice test comfortably within the allotted time.

Question # 31

Your project team is composed of team members in three countries plus a contractor team in a fourth country. What tool would optimize communication?

A.

Extranet-based electronic document repository

B.

Manual filing system

C.

War loom

D.

Verbal

Question # 32

Conformance to specifications document is one description of _________.

A.

Quality

B.

Scope

C.

Integration

D.

Procurement

Question # 33

Which of the following is not part of project scope management?

A.

Verify Scope

B.

Collect Requirements

C.

Create WBS

D.

None of the above

Question # 34

How many communication channels will be required in a project in which 10 individual are participating?

A.

45

B.

12

C.

10

D.

5

Question # 35

Which type of network diagram is also referred to activity-on-arrow (AOA) diagrams?

A.

Precedence Diagramming Method (PDM)

B.

Gant Cnart Diagram (GCD)

C.

Dependency Diagramming Method (DDM)

D.

Arrow Diagramming Method (ADM)

Question # 36

Your upcoming project includes project team members from a foreign country. To make certain that cultural differences do not interfere with team performance, thereby affecting the success of the project, which is your first course of action ?

A.

Provide diversity training to all the team members.

B.

Collocate the project team.

C.

Inform the team members of the organization ' s rules and standards.

D.

Perform team building exercises.

Question # 37

Which of the following statement is true about project charter?

A.

Provides a high level definition of the effort and its stakeholders

B.

Announces who is the project engineer

C.

Tells the newspapers and media when the project will end

D.

Announces who is the project sponsor

Question # 38

Tools and techniques used during the Plan Quality process include which of the following:

A.

Benefit/cost analysis

B.

Control charts

C.

Cost of Quality

D.

All of the above

Question # 39

Which of the following statements concerning bottom up estimating is true?

A.

The cost and accuracy of bottom-up estimating is driven by the size of the individual work items

B.

Smaller work items increase both cost and accuracy

C.

Larger work items increase both cost and accuracy

D.

Both A and B are true

Question # 40

Work packages are described in the __________.

A.

Work breakdown structure

B.

Work charter

C.

Statement of work

D) Q Work project plan

Question # 41

Activity Resource Requirements is an input to ____________ :

A.

Estimate Activity Durations

B.

Control Schedule

C.

Sequence Activities

D.

Estimate Activity Resources

Question # 42

Which describes how cost variances will be managed?

Cost management plan

Cost baseline

Cost estimate

Chart of accounts

Question # 43

The __________ task relationship is defined by the activity duration:

A.

Start-to-start

B.

Finish-to-finish

C.

Start-to-finish

D.

None of the above

Question # 44

What is the primary purpose of a milestone chart?

A.

To show task dependencies.

B.

To show resource constraints.

C.

To show significant events in the project such as completion of key deliverables.

D.

To highlight the critical path.

Question # 45

If BCWP =400, ACWP = 410, and BCWS = 350, what is the cost performance index?

A.

0-413

B.

0-82

C.

1-06

D.

1-142