You'll find that our PMI-002 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-002 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) Certification practice test comfortably within the allotted time.

Question # 16

You are a project manager for your organization. Management has asked you to help them determine which projects should be selected for implementation. In a project selection model, which one of the following is the most important factor?

A.

Business needs

B.

Type of constraints

C.

Budget

D.

Schedule

Question # 17

According to the PMBOK guide, the project statement of work(SOW) should contain or reference to all the following elements except ?

A.

Business need, strategic plan, product scope description

B.

Requirements, business need, stakeholder expectations

C.

Strategic plan, product scope description, stakeholder influences, and business need

D.

Project purpose, business case, stakeholder influences, product scope description

Question # 18

You are the project manager and have just completed the Collect Requirements and Define Scope process. What should you do next?

A.

Create WBS

B.

Verify Scope

C.

Value analysis

D.

Control Scope

Question # 19

You are managing a project that will implement a new MARKETING software package. You have assigned the resources and want to keep the IT manager in the loop by informing your decisions. Which type of organizational structure are you working in?

A.

Projectized

B.

Strong Matrix

C.

Weak Matrix

D.

Functional

Question # 20

Project management processes is organized into:

A.

Initiating, planning, executing, controlling, and closing

B.

Initiating, planning, contracting, executing, and closing

C.

Designing, developing, testing, and implementing

D.

Initiating, planning, contracting, developing, and closing

Question # 21

Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of:

A.

Enterprise benefits measurement methods when selecting a project

B.

Integral parts of the SOW

C.

Ways to ensure stakeholder commitment

D.

Project selection methods

Question # 22

Which one of the following comes first in the project plan?

A.

Scope Statement

B.

Quality Plan

C.

WBS

D.

Development Plan

Question # 23

The primary output of the project closing process ____________.

A.

To formalize and distribute all information pertaining to the project closing

B.

Lessons learned

C.

To get customer and sponsor approval

D.

Milestone list

Question # 24

How many communication channels exist in a team of 10 members?

A) 45

B) 10

C) 30

D 20

Question # 25

_________ is always the lowest risk for the buyer if the scope of work is not well defined.

A.

Cost plus incentive fee

B.

F ' xed P|ice

C.

Time and material

D.

" ' s^ ' s nc* ' elated to price

Question # 26

You are the project manager and you have created a contract for your customer. The contract must have ________.

A.

Offer and consideration

B.

Start date and acceptance of start date

C.

Signatures and the stamp of a notary public

D.

Signatures of all stakeholders

Question # 27

_______ is the road map for the execution of the project.

A.

Project plan

B.

sow

C.

WBS

D.

Strategic planning

Question # 28

Customer formally accepts the deliverables of each project phase. This process is known as ________.

A.

Verify Scope

B.

Quality Assurance

C.

Quality Control

D.

Quality Measurement

Question # 29

Which process group is for detailed resource assignments and responsibilities?

A.

Human resources management plan

B.

Project charter

C.

Aplan

D.

Project management plan

Question # 30

During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.

A.

Alternative identification

B.

" ' s^ assessment

C.

Alternative selection

D.

Product analysis