You'll find that our PMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Project Management Professional (2025 Version) practice test comfortably within the allotted time.
A project team member wants to select specific challenging tasks in the subsequent iteration. How can the project lead help the team member in the next iteration?
A project manager is managing a project that will engage resources from multiple countries in different time zones. What should the project manager do to ensure that team members are effective?
Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?
An organization in a regulated industry has decided to switch from a predictive to
an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum,
and the project manager is still accountable for the project outcomes. During the fourth sprint
demo, the customer notices that a feature is not compliant with the regulations.
What should the project manager do?
A project is being initiated, and almost every resource available on the project team is a recent university graduate. What should the project manager do to ensure their engagement with the project?
A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?
A project manager is assigned to a new project and is allocated with virtual team
members. Later, two more members from a recently acquired company join as additional
resources to the project team.
In order to ensure that there are no potential misunderstandings, what should the project
manager do?
A contractor delivering construction services to a company is using agile principles
to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design
changes or performing rework.
What should the project manager do to minimize the cost?
A team has been consistently delivering outcomes. However, based on their current performance, it was discovered that their velocity has decreased by 30%.
What should the project manager do to ensure the velocity is under control?
A multinational company is embarking on an ambitious organizational change project. The objectives of the project include the complete transformation of the organization's structure, role catalog, and global locations in which supporting services are to be delivered.
What should the project manager advise as an essential component of the project?
A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager
expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project
manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.
What engagement model should the project manager use for the technical architect role to ensure project success?
A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.
Which action should the project manager take next?
During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific
component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality
management plan and there is no reference to this component.
What should the project manager do next?
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.
What should the project manager do next ?
A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team
requests a change in the sprint goals and sprint backlog items.
What should the project manager do?
After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having 4 difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project.
Which phase of the Tuckman ladder of team formation is occurring?
A project manager is assigned to a technical research project. The project team has
already been assigned, and the main subject matter expert (SME) sends the project
manager a list of the technical skills required for the execution of this project.
What should the project manager do next?
A project manager is assigned to oversee the deployment of a new product that
will be used by the entire organization. A key success factor for the project is the timely
and successful adoption of the new solution by all entities.
What should the project manager do to ensure the success of this critical project?
The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?
A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.
How should the project manager ensure the acceptance criteria are ret?
A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?
A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.
What should the project manager do?
A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings
What should the project manager do?
A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.
What should the project manager do?
In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?
A project manager is working on a large project in another country and realizes that
only a few people from the project team are working on all of the releases. What should the
project manager do to prevent this in the future?
A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.
What should the previous project manager have done to prevent this issue?
An agile team was hired to work on a public service project. The team received a
list of vague ideas about the business and now needs to understand, develop, and prioritize a
list of functionalities.
Who will be responsible for this task?
A CEO of a general contracting company urgently asks the project manager to sign up two project team members to participate in a specific training course. Halfway
through the training, both team members complain that the training is too difficult, above their experience level, and that the material does not align with their tasks.
What should the project manager have done to prevent this situation?
A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.
Which stakeholders should the project manager consult with first to manage interdependencies?
An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.
How should the project manager improve team dynamics?
A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.
How should the project manager proceed?
A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.
How should the project manager approach this situation?
A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going
well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference
to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.
Which two things should the project manager do to help the teams collaborate better? (Choose two)
During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?
A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.
What should the project manager do?
A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff
What should the project manager do first?
In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain
What should the project manager do?
A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that
some stakeholders are working against the success targets of the project.
What should the project manager do to ensure successful project delivery? (Choose two)
A project manager has been assigned to a project that is in progress. The project
manager is looking for information regarding why the project is being completed.
What should the project manager do first?
A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days
What should the project manager do first to maintain the project team's performance level?
A new team member is assigned to a team that consistently delivers each iteration. The new team member is does not understand many of the processes followed and begins to negatively impact the schedule.
What should the project manager do?
A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.
What should the project manager do first?
A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.
When will the project manager be able to provide the requested information?
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.
What should the project manager do?
A customer discovered quality issues with the latest deliverables. However, the project team immediately resolved the issues.
Now that the project is back on track, what should the project manager do next?
The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team
Which two actions should the project manager take? (Choose two)