Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)

Last Update 15 hours ago Total Questions : 1320

The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 15 hours ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.

Question # 4

" Tailoring " is defined as the:

A.

effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.

B.

act of creating a project team with the specialized skills required to produce a required product or service.

C.

action taken to bring a defective or nonconforming component into compliance with requirements or specifications.

D.

adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.

Question # 5

The zero duration of milestones in project planning occurs because milestones:

A.

Are unpredictable and challenge the Plan Schedule Management process.

B.

Occur at random times in the project plans.

C.

Represent a moment in time such as a significant project point or event.

D.

Represent both significant and insignificant points in the project and are difficult to anticipate.

Question # 6

Which of the following are three inputs to the risk register?

A.

Risk register updates, stakeholder register, and quality management plan

B.

Communication management plan, enterprise environmental factors, and activity duration estimates

C.

Risk management plan, activity cost estimates, and project documents

D.

Project scope statement, organizational process assets, and scope baseline

Question # 7

Which of the following is an example of tacit knowledge

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Question # 8

Which of the following is a tool and technique used in the Develop Schedule process?

A.

Three-point estimates

B.

Resource leveling

C.

Precedence diagramming method

D.

Bottom-up estimating

Question # 9

The Agile principle " welcome changing requirement, even late in development " relates to which agile manifesto?

A.

Working software over comprehensive documentation

B.

Individuals and interactions over processes and tools

C.

Customer collaboration over contract negotiation

D.

Responding to change over following a plan

Question # 10

Which of the following sets are inputs to the Collect Requirements process?

A.

Project charter and requirements documentation

B.

Project charter and business documents

C.

Project charter and stakeholder requirements

D.

Business documents and requirements traceability matrix

Question # 11

What is a tool or technique used in the Control Quality process?

A.

Attribute sampling

B.

Parametric estimating

C.

Statistical sampling

D.

Expert judgment

Question # 12

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?

A.

-2,000

B.

0

C.

1,000

D.

2,000

Question # 13

During what project management process does the project team begin identifying risks?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Question # 14

The following is a network diagram for a project.

The shortest non-critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

16

Question # 15

Which two processes should be used to influence costs in the early stages of a project?

A.

Estimate Costs and Determine Budget

B.

Plan Cost Management and Estimate Activity Durations

C.

Control Quality and Control Costs

D.

Plan Stakeholder Engagement and Plan Communications Management

Question # 16

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

Question # 17

When managing costs in an agile environment, what should a project manager consider?

A.

Lightweight estimation methods can be used as changes arise.

B.

Agile environments make cost aggregation more difficult.

C.

Agile environments make projects more costly and uncertain.

D.

Detailed cost calculations benefit from frequent changes.

Question # 18

Select three elements that apply to agile/ adaptive environments

A.

Frequent team checkpoints

B.

Colocation

C.

Access to information

D.

Virtual team members

E.

Geographically dispersed team

Question # 19

When the business objectives of an organization change, project goals need to be:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

Question # 20

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

A.

Perform Quality Control

B.

Quality Metrics

C.

Perform Quality Assurance

D.

Plan Quality

Question # 21

Risk exists the moment that a project is:

A.

planned.

B.

conceived.

C.

chartered.

D.

executed.

Question # 22

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram

Question # 23

A practitioner organized a requirements workshop with the client ' s frontline application users. The users explained that one of the challenges of the current application is that they must click on each input before entering data, which happens thousands of times a day.

Which technique did the practitioner use to identify this pain point?

A.

System thinking

B.

User acceptance testing

C.

Decision-making

D.

Active listening

Question # 24

The Verify Scope process is primarily concerned with:

A.

formalizing acceptance of the completed project deliverables.

B.

accuracy of the work deliverables.

C.

formalizing approval of the scope statement.

D.

accuracy of the work breakdown structure (WBS).

Question # 25

What causes replanning of the project scope?

A.

Project document updates

B.

Project scope statement changes

C.

Variance analysis

D.

Change requests

Question # 26

Funding limit reconciliation is a tool and technique used in which process?

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

Question # 27

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

A.

The customer and functional managers

B.

The risk owners and stakeholders

C.

The sponsors and stakeholders

D.

The project management team

Question # 28

Which tasks should a project manager accomplish in order to manage project scope correctly?

A.

Define. Validate, and Control Scope. Control Schedule; Control Costs and Manage Stakeholder Engagement

B.

Collect Requirements. Define Scope. Create WBS. Develop Schedule, and Manage Stakeholder Engagement

C.

Plan Scope Management; Collect Requirements; Define. Validate, and Control Scope; and Create WBS

D.

Define. Validate, and Control Scope. Control Costs. Manage Stakeholder Engagement, and keep budget under control

Question # 29

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Question # 30

A graphic display of project team members and their reporting relationships is known as a:

A.

Resource calendar.

B.

Project organization chart.

C.

Resource breakdown structure (RBS).

D.

Responsibility assignment matrix (RAM).

Question # 31

The diagram below is an example of a:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Question # 32

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

A.

Discussing with management

B.

Escalating to the sponsors

C.

Engaging regularly with stakeholders

D.

Engaging only with decision makers

Question # 33

The project manager implemented the stakeholder engagement plan and realized that some uploads should be made. Which components of the project management plan should be modified?

A.

Project charter and stakeholder engagement plan

B.

Risk management plan and stakeholder engagement plan

C.

Communications management plan and stakeholder engagement plan

D.

Project charter and communications management plan

Question # 34

A project ' s aim, from a business perspective, is moving an organization from one level to another to achieve a specific objective. What is the goal for a project ' s successful completion?

A.

Current state

B.

Future state

C.

Budgeted state

D.

Planned state

Question # 35

What is a tailoring consideration for the application of Project Risk Management processes?

A.

Project complexity

B.

Procurement criteria

C.

Communication technology

D.

Knowledge management

Question # 36

What can a project manager review to understand the status of a project?

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Question # 37

The staffing management plan is part of the:

A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

Question # 38

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Plan Quality

D.

Report Performance

Question # 39

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

A.

WBS directory

B.

Activity list

C.

WBS

D.

Project schedule

Question # 40

An adaptive project manager is handling a five-sprint cycle to deliver a minimum viable product (MVP). After the third sprint, the productivity of the team drops to 30% due to a change in the way the team operates.

Which of the following changes has caused this loss in productivity?

A.

Two of the team members have been working in silos using different methods to validate their performance.

B.

The team velocity was measured in the third sprint since the tool to measure velocity was introduced only in the third sprint.

C.

The team picked up technical debt items in the third sprint as technical debt can only be picked up after completing two sprints.

D.

Two of the team members were asked to do multitasking, which they did not do in the previous two sprints.

Question # 41

What does earned value (EV) measure?

A.

Budgeted work that has been completed

B.

Total costs incurred while accomplishing work

C.

Budget associated with planned work

D.

Cost efficiency of budgeted resources

Question # 42

A technique used to determine the cause and degree of difference between baseline and actual performance is:

A.

Product analysis.

B.

Variance analysis.

C.

Document analysis,

D.

Decomposition.

Question # 43

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

A.

Histograms

B.

Scatter diagrams

C.

Flowcharts

D.

Checksheets

Question # 44

In project management, a temporary project can be:

A.

Completed without planning

B.

A routine business process

C.

Long in duration

D.

Ongoing to produce goods

Question # 45

Match each tool or technique with its corresponding Project Cost Management process.

Question # 46

The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.

Which of the 5Cs of written communications does the project manager need to address?

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

Question # 47

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to determine if the solution provides the functionality for typical usage by a stakeholder with in-depth business knowledge.

Which evaluation technique is most effective for this situation?

A.

Day-in-the-life testing

B.

Exploratory testing

C.

User acceptance testing

D.

Integration testing

Question # 48

Managing procurement relationships and monitoring contract performance are part of which process?

A.

Conduct Procurements

B.

Plan Procurements

C.

Administer Procurements

D.

Close Procurements

Question # 49

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Question # 50

At the end of the third iteration, the project team gathers to discuss the stories to be implemented in the next iteration. What should the team do during this session?

A.

Run a spike to ensure all information available is correct and then decide which stories to implement.

B.

Develop a user story analysis based on the work done, depicting the current status, S-curve, schedule variance (SV), and planned value (PV).

C.

Plan the backlog by estimating and reprioritizing the user stories as new information becomes available.

D.

Bring up all risks for implementing the user stories and discuss possible solutions.

Go to page: