Last Update 1 week ago Total Questions : 1250
The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 1 week ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.
You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.
How should a project manager plan communication for a project which has uncertain requirements?
In the Define Activities process, the schedule management plan is used to:
Which item is a formal proposal to modify any document, deliverable, or baseline?
Scope, schedule, and cost parameters are integrated in the:
A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?
Which tool or technique is used in the Perform Integrated Change Control process?
Which of the following sets are inputs to the Collect Requirements process?
Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?
Which of the following are outputs from the process of creating a work breakdown structure (WBS)?
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
A project manager should document the escalation path for unresolved project risks in the:
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
Lessons learned are created and project resources are released in which Process Group?
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:
A regression line is used to estimate:
The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:
Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:
An input to Conduct Procurements is:
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
Stakeholder satisfaction should be managed as a key project:
The features and functions that characterize a result, product, or service can refer to:
Which of the following is an example of an internal factor that influences the outcome of the project?
If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?
What purpose does the hierarchical locus of stakeholder communications serve?
A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
What type of meeting is held to discuss prioritized product backlog items?
Which action should the project manager take after the team finishes executing the scope?
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
A tool or technique used in the Control Procurements process is:
An input to the Plan Procurement Management process is:
The Identify Stakeholders process is found in which Process Group?
Which item is an input to the Define Activities process?
A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
A key benefit of the Manage Communications process is that it enables:
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
Market conditions and published commercial information are examples of which input to the Estimate Costs process?
A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.
Which process is the project manager executing?
In which Knowledge Area is the project charter developed?