You'll find that our PMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Project Management Professional (PMBOK 7th Version) practice test comfortably within the allotted time.

Question # 401

A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?

A.

Projects with the least duration

B.

Projects that maximize the business value

C.

Projects with maximum revenue generation

D.

Projects with the least associated risks

Question # 402

A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?

A.

Document the new stakeholders ' concerns in the meeting minutes.

B.

Schedule an ad hoc meeting with the new stakeholders to discuss concerns.

C.

Use social media environments to share the project information

D.

Use the project management information system (PMIS) to share information.

Question # 403

A project manager is leading a project that is in the execution phase. During a team

meeting, the project manager realizes that there are two team members who lack the

technical skills required for some of the upcoming tasks.

What should the servant leader project manager do next?

A.

Recommend to the team members to upskill themselves on the requirements for theproject.

B.

Discuss with the human resource (HR) manager about the possibility of changing teammembers.

C.

Inform the sponsor about a possible delay due to the lack of skills in the team.

D.

Explore a training program that is within the project budget for the team members.

Question # 404

A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.

What should the project manager do?

A.

Provide a software for instant messaging.

B.

Document all information on the team wiki.

C.

Promote the use of remote site syndication.

D.

Facilitate regular conference calls.

Question # 405

A customer interacts directly with a Scrum team and continually requests changes in

priorities. This causes confusion among the team members and they complain to the project

manager.

What should the project manager do?

A.

Advise the customer to discuss changes with the product owner.

B.

Document this issue in the sprint backlog for discussion at a team meeting.

C.

Ask the customer to submit a change request to the project sponsor.

D.

Encourage the team to clarify the requests with the customer.

Question # 406

A project manager is leading an integration project for a retail company. The project

demands a lot of time from the stakeholders to make important business decisions. The

project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this

project?

A.

Schedule meetings with all of the stakeholders to make business decisions whenneeded.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholdersahead of time.

C.

Work with the available stakeholders to make business decisions and keep allunavailable stakeholders informed.

D.

Add time reserve in the project schedule to allow extra time for the stakeholders tomake decisions.

Question # 407

A company is conducting a digital transformation project that has a hard deadline.

The marketing team wants to combine this implementation with a new product, and the newly

assigned project manager is not aware of all the dependencies.

Using a hybrid approach, what should the project manager do to ensure the dependencies are

taken into consideration?

A.

Implement a project newsletter so the different team members can be informed aboutthe progress of each project.

B.

Combine all of the small projects into one big project so the team can collaboratebetter as one big team.

C.

Facilitate communication promoting a Scrum of Scrums so the different teams areaware of the dependencies and progress.

D.

Make sure that each individual project schedule is aligned with the common deadlines.

Question # 408

A customer calls the project manager to express concern about a project team

member who has been making changes within the live environment without approval. The

team member mentioned that the customer called and asked them to make the changes.

What should the project manager do next?

A.

Reinforce the value of documenting and approving all change requests and ask thecustomer to issue these through the agreed channels.

B.

Organize a meeting to mediate the relationship between the customer and the teammember to ensure no feelings are hurt.

C.

Ask the customer to email all requests directly to you and you will ensure they areactioned by the correct team member.

D.

Explain to the customer that the team member was just trying to help and the changescan be reverted if necessary.

Question # 409

A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided

details to the customer 2 weeks ago and set up a weekly conference call to effectively

communicate with them, but the customer has not been participating in the calls.

How should the project manager handle this situation?

A.

Request a change in the contract to include the shipment in the project managementplan.

B.

Find the root cause of the issue and discuss the customer ' s current engagement.

C.

Inform the customer that subsequent packages cannot be manufactured.

D.

Request a delivery date extension from the customer

Question # 410

A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies

When should the risks be reviewed to ensure alignment between the project team and the stakeholders ' ?

A.

During the risk register update

B.

During the retrospectives

C.

During each steering committee meeting

D.

During each iteration and review

Question # 411

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?

A.

Analyze the problem with both teams to figure out If pan of the work must be redone.

B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.

C.

Demand that the business team stop wasting time and define final requirements for the product.

D.

Tell the business team and Scrum team to continue following the initial plan.

Question # 412

During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?

A.

Let the product go to market and wait for customer feedback regarding quality

B.

Ask the quality manager to include the final user tests in the quality management plan.

C.

Submit a change request to analyze a new set of quality tests

D.

Ask the product manager to include the final user tests in the quality management plan

Question # 413

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

A.

Ask the procurement department to supply a different resource.

B.

Change the schedule according to the availability of the resource.

C.

Ask the sponsor to obtain the resource as originally planned.

D.

Contact the other project manager to request the resource.

Question # 414

A project manager is in the process of creating a strengths-based team and is

organizing a series of workshops to identify and document the strengths of each project team

member. During this session, there are multiple team members who are not actively

participating. These meetings are becoming futile due to a lack of participation.

What should the project manager do?

A.

Have a one-on-one discussion with each team member to emphasize their individualtalents.

B.

Document the behavior of the team members and highlight it during their performancereviews.

C.

Identify the team members who are not participating and reprimand them.

D.

Explain the benefits of the approach and the effects of positive psychology.

Question # 415

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?

A.

Perform stakeholder engagement with the virtual team

B.

Add status reports to the communications management plan

C.

Convene an on-site meeting for both of the teams

D.

Add status report creation as a product backlog item

Question # 416

During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?

A.

Reviewed the risk register to identify a response plan for the audit

B.

Assigned a project team member to ensure all project documentation was updated

C.

Updated the project management plan regularly and had it securely shared with all stakeholders

D.

Kept documentation in the project management information system (PMIS) and shared it with appropriate stakeholders

Question # 417

During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?

A.

Design a set of metrics including velocity, which is a good measure of value delivered.

B.

Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP)

C.

Promote a productive environment where everybody can work without interruptions from the rest of the team members

D.

Create a reward system recognizing group contributions to get people motivated and improve performance

Question # 418

An issue reoccurs six months after a project ' s go-live date despite being resolved

during the project life cycle. What should the project manager have done in the previous

phase to avoid this issue?

A.

Ensured the project team documented lessons learned about the issue

B.

Ensured the project team applied a long-term solution for the issue

C.

Asked the project team to conduct more testing with users

D.

Discussed the issue with the stakeholders

Question # 419

A project manager finds out that the required project status reports have not been

filled out by most team members. These status reports are urgently needed to compile a

comprehensive status report for the project sponsor.

What should the project manager do to address this situation?

A.

Reprimand the team members who did not fill out the status reports.

B.

Justify the team members ' behavior to the project sponsor.

C.

Quickly put together a report that will satisfy the project sponsor.

D.

Discuss the issue with the team members at fault.

Question # 420

A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation

What should the project manager do next?

A.

Document the issue in the issue log and escalate to the project sponsor

B.

Inform the project sponsor and suggest canceling the project

C.

Review the project goals and eat criteria m the project charter

D.

Ask the leader of research and development to decide on next steps

Question # 421

A project has been running successfully for 2 months. At a regular project meeting,

the team raises several potential obstacles to future progress. The obstacles include vendor

delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

A.

Work with the team and others in the network to assess and prioritize the obstacles.

B.

Engage with the external stakeholders and the other division of the organization toresolve the issues.

C.

Escalate the obstacles to the project sponsor for assistance with resolution.

D.

Determine a change response to identify and resolve the obstacles to move the projectforward.

Question # 422

A team Is experiencing difficulties and has decided to use a spike. Please click on the portion of the burndown chart that corresponds to the spike.

Question # 423

During project completion, a project manager receives a request from the customer for a reduced cost of goods. The customer ' s request will affect the sales department ' s budget and forecast.

In order to reach a consensus and have a successful project completion, what should the

project manager do first?

A.

Analyze the bounds of the negotiation for agreement with both parties.

B.

Identify and satisfy both parties ' underlying wants.

C.

Comply with the customer ' s request to achieve the project mandate.

D.

Initiate a change request to accommodate the revised cost of goods

Question # 424

A company ' s board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

A.

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions

B.

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel

C.

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities

D.

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members

Question # 425

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

A.

Increase the overall project duration to account for the inexperienced team memberson the project.

B.

Ensure planning has accounted for replacing team members in new project roles whodo not deliver on project goals.

C.

Assess the training requirements and ensure time for professional developmenttraining by senior members.

D.

Revisit the project resource allocation to remove the inexperienced team membersassigned to the project.

Question # 426

A protect manager is struggling to obtain participation from key stakeholders who do not usually attend project meetings What should the project manager do1?

A.

Distribute the communications management plan

B.

Reschedule meetings lo align with the stakeholders ' availability

C.

Escalate the issue to senior management

D.

Set clear meeting expectations by sharing agendas in advance

Question # 427

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

A.

Instruct the team to work as planned and Ignore the stakeholder ' s requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

Question # 428

While working on a poorly defined internal project, a project manager receives

multiple change requests from senior management. What should the project manager do first?

A.

Identify how the proposed changes will benefit the project in relation to the businesscase.

B.

Ask for a temporary budget increase to avoid cost overruns.

C.

Keep the team motivated and incentivized to avoid exhaustion from working on alengthy project.

D.

Assess the schedule delay and begin implementation to avoid additional lags

Question # 429

During the sprint planning of a project, the team members have a disagreement

about the comparative size of the backlog items and if they would fit into the next sprint.

Considering a hybrid approach, what should the project manager do?

A.

Ask an external technical leader to provide input and plan the sprint.

B.

Remove the items from the product backlog since the size couldn ' t be estimated.

C.

Make the decision about the backlog items based on what makes more sense.

D.

Facilitate the discussion so that the team members can reach a consensus.

Question # 430

A project sponsor would like to include a new deliverable. The sponsor contacts the project manager in order to seek advice on the most efficient approach to complete the deliverable within the next 2 months.

What should the project manager do?

A.

Change the project methodology in order to achieve completion of the deliverable within 2 months.

B.

Advise the sponsor that it is not the project manager’s job to evaluate the project.

C.

Suggest that the sponsor conduct a cost-benefit analysis to determine feasibility.

D.

Use the management reserve in order to expedite completion of the deliverable within 2 months.

Question # 431

During the testing phase of a project, the project manager is made aware that components delivered from a specific vendor have defects. However, the vendor refuses to fix the defects because it will incur additional costs for them.

What should the project manager do next?

A.

Ask the vendor for revised timelines and cost needs.

B.

Review the acceptance criteria defined with the vendor.

C.

Communicate with the vendor for contract changes.

D.

Request cancellation of the contract with the vendor.

Question # 432

A project team is completing a design, while another team in a different country is performing implementation. How should the project manager communicate the design to the implementation team?

A.

Send a detailed email with the completed design document.

B.

Conduct a workshop with all of the stakeholders.

C.

Conduct a workshop with both of the teams.

D.

Upload the design documents into the project repository.

Question # 433

In a daily standup meeting, a project manager notices that a team member ' s reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.

What should the project manager do?

A.

Coach the team member on how to keep work and personal issues scjparate.

B.

Ask the human resources (HR) manager to speak with this team member.

C.

Reallocate this team member ' s tasks to others for the immediate future.

D.

Understand the team member ' s personal issue and offer them support.

Question # 434

A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned

to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?

A.

Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.

B.

Sequence the tasks with estimates and add standard risk reserves to use for software development.

C.

Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.

D.

Work with the team to understand their views and add the appropriate dependencies and risks.

Question # 435

An agile project will be delivered to a client based on a fixed price in cryptocurrency. Due to the volatility of cryptocurrency, both parties have

agreed to adjust the scope to the value of the cryptocurrency at the end of every iteration and halt the project when the agreed price is reached.

Which approach should be used in this situation?

A.

A flow-based approach starting with the smallest stories.

B.

An iterative approach starting with the highest value epic.

C.

A predictive approach with short phases.

D.

An incremental approach with a minimum viable product (MVP).

Question # 436

A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on

the regulation ' s requirements. Therefore, changes in definitions are to be expected due to uncertainty.

Which life cycle should the project manager use for this project?

A.

A predictive execution strategy

B.

A hybrid execution strategy

C.

An iterative execution strategy

D.

An agile execution strategy

Question # 437

A multinational company is rolling out a new software platform within its subsidiaries. However, the distributed project team struggles to meet regularly. As a result, the project milestones are not being achieved.

What should the project manager do first?

A.

Inform the project sponsor and request additional team members to crash the project schedule to meet the target

B.

Introduce an award system to promote member participation and establish some competition between the subteams

C.

Evaluate the effectiveness of the virtual teams and support them with the necessary technology and equipment

D.

Propose to roll out the new software in one subsidiary and then use the lessons learned to improve the project

Question # 438

As part of its growth strategy, management is providing all of its ongoing projects with junior employees and is requesting experienced team members to mentor them. The experienced employees argue that the mentoring program will not add value to their projects and will limit their ability to deliver.

How should the project manager handle this situation?

A.

Recommend to management that the junior employees should receive formal training and courses.

B.

Schedule time with all of the project team members since it is the role of the project manager to mentor the team.

C.

Allocate specific time for experienced team members to mentor the junior employees.

D.

Assign an instructor to mentor the junior employees so that the experienced team members can focus on project tasks.

Question # 439

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

A.

Assign critical tasks to the most experienced team members.

B.

Review the budget with the team for the needed resources.

C.

Review lessons learned from similar projects with the team.

D.

Explain the higher-level objectives to be assigned to the team.

Question # 440

An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete the job successfully. What should the project manager do to reduce the risk of project failure?

A.

Ask the sponsor to add experienced professionals to the team.

B.

Assign a dedicated resource to check the quality of each deliverable.

C.

Approve the appropriate training program for team members.

D.

Provide team members with the necessary coaching and mentoring.

Question # 441

A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team ' s performance as

a whole is low, especially in terms of group activities.

What should the project manager do?

A.

Negotiate for new team members.

B.

Review and update the communications management plan.

C.

Review and reassign team assignments.

D.

Facilitate communication and team building.

Question # 442

In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?

A.

Give the change to the scrum master to investigate how much additional effort the change will require.

B.

Tell the customer that the requirement change will be put into the next project phase if management approves.

C.

Validate the requirement change with the product owner and development team before redefining the scope.

D.

Escalate to management for approval since the change was not included in the original requirements.

Question # 443

A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product

owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer

features or low quality.

What should the project leader have done to ensure success?

A.

Directed teams to possible solutions that help in removing the impediments and contribute to a timely delivery

B.

Suggested to the team to add impediments as work items in the product backlog to be fixed in the next sprints

C.

Asked the team to create an impediment log and keep it updated for use in the next sprint planning

D.

Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments

Question # 444

A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers

arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.

What does the project manager need to do now?

A.

Inform the relevant stakeholders.

B.

Inform the project team only.

C.

Inform the product owner.

D.

Inform the project sponsor.

Question # 445

In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.

Match the project manager ' s goals on the left with the relevant risk parameter on the right.

Question # 446

A project lead is working on an agile project to build the team ' s vision, including the decision-making process. It was decided that the team will

vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team

makes a decision that the project lead strongly disagrees with.

How should the project lead proceed?

A.

Refuse to let the team proceed with the work based on their decision.

B.

Take the technical team lead aside and try to persuade them to change their vote.

C.

Note the reasons for the disagreement and let the team proceed.

D.

Set up a meeting with the project champion and ask them to intervene.

Question # 447

An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price.

What should the product owner do about this situation?

A.

Reprioritize the backlog based on value and cost of delay divided by duration.

B.

Switch to a predictive approach to prevent any further delays to completion.

C.

Reprioritize the backlog based on story size and competence availability.

D.

Remove low-value items from the backlog to compensate for the higher cost.

Question # 448

A company just started managing a project using an agile approach. Due to this change, the general manager is worried about the scope definition process for upcoming projects.

What should the project manager do to ensure the project scope is completely defined?

A.

Ask the general manager to review every requirement to ensure all projects will deliver the requested products

B.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

C.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations

D.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk

Question # 449

Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.

What should the project manager do?

A.

Assess and prioritize the impact of the new law on the project plan.

B.

Update the project plan because the law is an obligation for the project.

C.

Minimize the scope to catch the cost and schedule baseline.

D.

Meet the sponsor to ask for additional time and budget increase.

Question # 450

A project manager is assigned to a yearlong project. Before the start of the design phase, a competitor announces that they will release a similar deliverable in 8 months, although with fewer features and functionality.

Which two actions should the project manager take next? (Choose 2)

A.

Modify the project management plan with an incremental approach.

B.

Evaluate the impact of incremental deliverables.

C.

Reduce the scope items of the final deliverable.

D.

Discuss and review this external risk with the project sponsor.

E.

Update the project artifacts to include this issue.