You'll find that our PMI-ACP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-ACP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Agile Certified Practitioner (PMI-ACP) practice test comfortably within the allotted time.

Question # 51

How can an agile project manager ensure that all stakeholders have a clear understanding of the release plan by the end of a release planning meeting? (Choose two.)

A.

Stated understanding of the release goal

B.

Complete vision of the end product

C.

Timeline of the project

D.

List of the user stories that will be part of the next releases

E.

Complete roadmap of the next iterations

Question # 52

A graphic designer on an agile team does not attend most meetings. When asked the reason for not attending, the designer told the agile practitioner that the scrum master could represent them in meetings if needed. The team is frustrated and does not agree with this approach.

Which conflict resolution method would work best in this scenario?

A.

Avoidance

B.

Forcing

C.

Accommodation

D.

Collaborating

Question # 53

Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project.

How should the agile practitioner explain to senior management the benefits of this approach?

A.

It ensures a consistent level of detail is available in the project schedule

B.

It prevents a wasteful buildup of requirements inventory that may never be processed

C.

It provides a concrete definition of project scope, cost and duration

D.

It allows the team to lock down the stories to be included in a release

Question # 54

Who should the Scrum Master invite to the meeting?

A.

The core team and the customer

B.

The product owner and key stakeholders

C.

The customer and the sponsor

D.

The core team and the product owner

Question # 55

An agile project manager is planning the initial scope, schedule, and cost range estimates on a new project. The team will be using Kanban to control work.

What metrics should the team use to measure performance?

A.

Lead time, throughput, and due date performance

B.

Work in progress limits, Kanban board, and time boxes

C.

Work item types, sprint cadences, and defect classes

D.

Burndown charts, scatter diagrams, and throughput

Question # 56

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

A.

Schedule a meeting to engage stakeholders to prepare for kickoff

B.

Schedule a meeting to agree to the goals for all future iterations.

C.

Guide the team to work collaboratively and share learnings.

D.

Organize a sprint planning meeting to define actions.

E.

Organize a meeting to outline roles and responsibilities.

Question # 57

An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.

Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).

A.

Code is unit tested, code is peer reviewed, functional testing is passed, business testing is passed, and all acceptance criteria are met.

B.

Code is unit tested, all acceptance criteria are met, business testing passed, code is merged, code is peer reviewed, and documentation is updated.

C.

All acceptance criteria are met, documentation is updated, functional testing is passed, business testing is passed, and code is peer reviewed.

D.

Code is unit tested, all acceptance criteria are met, business testing is passed, functional testing is passed, code is merged, and documentation is updated.

Question # 58

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative ' s current status.

Which summaries are correct and will be presented during the monthly project review? (Refer to

the email and exhibits to the Team Manager)

A.

MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

B.

MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

C.

MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

D.

MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

Question # 59

How should the agile team address this?

A.

Conduct an internal review to validate functionality before shipping

B.

Audit the quality control process to ensure that the product adheres to requirements

C.

Lengthen iterations to ensure there is sufficient time to build functionality

D.

Hold product review sessions with the client to obtain product acceptance

Question # 60

An agile team wants to collectively determine a project ' s size. What will the team be doing if they use the planning poker technique to accomplish this?

A.

Estimating story points by comparing them to similar, past features

B.

Estimating stories by placing them in buckets

C.

Using the number of dots for votes to estimate story points

D.

Estimating the relative size of stories by using story points