You'll find that our PMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Project Management Professional (PMBOK 7th Version) practice test comfortably within the allotted time.
A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.
What should the project manager do?
The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies
What should the project manager do?
A project manager for a large multiyear industrial project has a project with diversified stakeholders from various geographical areas. Recently, the project manager encountered an issue with stakeholder engagement
Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose two)
The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies and the project manager needs the director’s support as the marketing director is a key stakeholder.
What should the project manager do to obtain the support?
During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version
How can the project manager prevent this outcome in the new project?
An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively
What key activity is needed to ensure the project ' s success?
During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation How should the project manager respond?
A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.
What should the project manager do first?
A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.
What should the project manager do?
A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.
What should project manager to do next to minimize the impact on the project?
A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.
What should the project manager do to support the business analyst?
During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?
During the last sprint review, the mam stakeholder complained that the product was missing many features they had been expecting The project team argued that every increment met the acceptance criteria and was approved by the mam stakeholder The cost performance index (CPI) of the project is 1 15 and the schedule performance index (SPI) is 1.43
What should the project manager do?
The following table shows the business value created and the development effort required to implement various features in a product
Which feature should the team prioritize first? Enter the feature name in the box below
A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?
The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right
A project manager is implementing a new software system Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes
What should the project manager have done at the start of the project to prevent this resistance?
Drag the organizational characteristics on the left to the correct scenario on the right
An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost even though it is within the project budget.
What should the project manager do to resolve this issue?
Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement
What should the project manager do next?
A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval
How should the project manager approach this problem?
A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)
In a multinational multi location project with virtual teams a project manager has established a project baseline The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.
What should the project manager calculate to address this critical budgetary situation? (Choose two)
After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch
What should the project manager do to realize benefits?
A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase
How should the business increase the value of the project?
The project manager of an agile project has been asked to reduce the budget by 30% Since this is a small project team, the budget is primarily allocated to resources
What strategy should the project manager use in order to keep delivering value in a restricted environment?
A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization ' s senior management and external stakeholders. What should the project manager do?
A company ' s project management office (PMO) has started to implement iterative tools A project manager is starting a new project and has identified an opportunity to use the iterative tools One of the senior managers is concerned about this modified framework as it is fairly new to the company
What should the project manager do first?
A team is ready to start working on a project with a customer who was very difficult to work with in the past because the customer was unable to describe exactly what they wanted What approach should the project manager take to remove this impediment?
A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?
During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.
What should the project manager do?
After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.
Which technique will help the project manager to accelerate the deliverable?
In a hybrid project, the customer decided on a major change for the project design. This change was approved and the impact on schedule and budget is known The software team leader, who is supposed to develop the software, refuses to commit to delivery dates claiming that they work using an agile approach and cannot commit to a final delivery date The hardware team depends on this software to develop their part of the product
What should the project manager do?
A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint
What should the project manager have done to avoid this situation?
During the initial phase of a construction project, the team is confused about the safety requirements it needs to consider during implementation. The project manager recently met with the client to define the project scope.
How should the project manager share this information?
Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget.
What should the project manager do first to obtain the funding to hire the needed resources?
A project manager recently took over an ongoing project. Within a few weeks on the project, the project manager discovers that there are continuous change requests from different project end users. What is the probable cause for this?
A project manager is leading a highly visible project initiative. A few weeks after kickoff, the project manager starts receiving requests for updates from various stakeholders. What should the project manager do?
A new team member joins the project and fails to apply the project-specific quality assurance (QA) processes. What should the project manager have done to avoid this issue?
During the requirements gathering and analysis stage for the project, the team members are debating some functionality issues that are expected to be included in the scope. Due to this discussion, the planning activity for the scope definition is running late. What should the project manager do?
A project is being planned with two hardware deliverables and one software deliverable that will be used to monitor the operation of the two hardware deliverables. When preparing the consolidated project schedule, what should be the top priority for the project manager?
A project team is continually being asked by stakeholders to perform rework on their deliverables. The project manager discovers that this is due to poor initial quality. What should the project manager do?
During project implementation, a critical performance issue is identified by team members.
What should the project manager do?
A project manager is hired to work on a very large, complex project that requires the team to complete a significant number of specialized tasks. What strategy should the project manager incorporate to help organize, assign, and monitor these tasks?
A project lead accepted an assignment for a project that is still in the feasibility study phase. There are many uncertainties about project specifications, including poor alignment among the project sponsors on the final targets of the project.
Which approach should the project lead choose to deliver business value?
One-on-one interviews with members of an agile team reveal that they distrust an expert member. Their explanations seem to point to the expert’s communication style in daily coordination meetings, which team members interpret as avoiding accountability.
What two actions should the project manager take to address the situation? (Choose 2)
A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?
Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the company’s competitive advantage.
What should the project manager do?
A project manager faces a major conflict within their project team that should be resolved as soon as possible. Which form of communication should the project manager use to deal with the conflict?
A project manager notices a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories. What should the project manager do first?