You'll find that our PMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Project Management Professional (PMBOK 7th Version) practice test comfortably within the allotted time.

Question # 651

A project sponsor is transitioning their division to an agile environment and has emphasized that project team members and stakeholders should collaborate to achieve deliverables. On a few occasions, progress has been interrupted by one stakeholder who is unfamiliar with agile approaches. What should the project manager do first?

A.

Report the behavior to the project sponsor and find a replacement.

B.

Note the stakeholder’s attitude as a risk and continue development according to the plan to deliver value.

C.

Consider using a predictive project management framework and report the results to the project sponsor.

D.

Address the stakeholder’s behavior directly and provide feedback.

Question # 652

A new project manager has been assigned to a recently approved project. The project has a multimillion-dollar budget and will require the purchase of expensive equipment. The project manager is aware that some purchase amounts require higher levels of approval. What should the project manager do to properly manage the purchase of equipment?

A.

Agree on a purchasing approval escalation method according to organizational governance

B.

Replace the most expensive equipment with cheaper ones to allow easier purchase approval

C.

Ask the organization to allow the project manager to approve all purchases

D.

Propose that the project sponsor approve all equipment that needs to be purchased

Question # 653

A project team member finishes all assigned tasks in the middle of a sprint. The team member wants to plan tasks for the next sprint to deliver business value earlier. The team member has the abilities and knowledge to execute tasks not yet started by other team members in the current sprint. What should the project manager do?

A.

Validate completeness of the tasks delivered in the current sprint

B.

Increase team velocity to execute tasks for the next sprints

C.

Reassign the team member to other tasks in the current sprint

D.

Encourage the team member to execute the next sprint tasks

Question # 654

A new stakeholder is unaware of the existence of the project a few weeks before the final deliverable and project completion. What should the project manager do first?

A.

Escalate this issue to the project sponsor.

B.

Communicate the full details of the project activities to the stakeholder and solicit input.

C.

Analyze this stakeholder’s interest and impact.

D.

Share the summary of the project activities with the stakeholder and conclude the project.

Question # 655

Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget. What should the project manager do first to obtain the funding to hire the needed resources?

A.

Ask the sponsor for additional financial resources

B.

Introduce a change request

C.

Use management reserves

D.

Update baselines to accommodate the delay

Question # 656

A project manager is leading a contract for a new market that was awarded to their company. The client wants to jump-start the market with the informal sector traders.

What should the project manager do?

A.

Plan the project in phases, starting with the informal sector, to deliver business value to the client quickly.

B.

Divide the project team into groups to execute the project as small parallel projects, including the informal sector.

C.

Execute the projects simultaneously following the project schedule and the communications management plan.

D.

Gather requirements and convert them into backlog items to quickly deliver value to the client.

Question # 657

An experienced project manager has recently joined a jeopardized project. The project is being impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot add a new vendor, and the project must be completed within a maximum of 90 days as agreed.

What should the project manager do?

A.

Reach out to the vendor to determine a plan to get the project back on track.

B.

Review lessons learned from previous projects and take action accordingly.

C.

Request that the vendor provide the servers on time, as penalties may be applied.

D.

Wait until the project deadline is reached in order to use the contingency funds.