You'll find that our CA0-001 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CA0-001 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) Certification practice test comfortably within the allotted time.

Question # 121

Purchasing insurance is an example of __________.

A.

Transfer

B.

Acceptances

C.

Mitigation

D.

Contingency

Question # 122

In which type of organization, a project manager is in complete control of the project?

A.

Projectized organization

B.

Balanced Matrix organization

C.

Strong Matrix

D.

Weak Matrix organization

Question # 123

Which of the following is NOT an input of Estimate Costs?

A.

Earn Value Analysis

B.

Scope Baseline

C.

P ' sk Register

D.

Human Resource Plan

Question # 124

Which is not included in Performance improvements :

A.

Improvements in amount of overtime worked

B.

Improvements in individual skills

C.

Improvements in team behaviours

D.

Improvements in team capabilities

Question # 125

What is the purpose of the WBS?

A.

To show which work elements have been assigned to organizational units.

B.

To ensure that all work within a project is identified and defined within a common framework.

C.

To show the organizational structure of a program.

D.

all of the above

Question # 126

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

A.

Start-to-Finish

B.

Finish-to-Start

C.

Start-to-Start

D.

Finish-to-Finish

Question # 127

Which of the following is a common characteristic of most project life cycle descriptions?

A.

Cost and staffing are low at the start, higher towards the end. and drop rapidly as the project nears completion.

B.

The probability of successfully completing the project is highest at the start of the project.

C.

Stakeholders have the most influence on the final characteristics of the product at the end of the project.

D.

a and b

Question # 128

You are the project manager of a project. Project is installing AC to hotel rooms. You have done project cost and time estimates, told the customer that the estimates provided will be accurate if the rooms meet the requirements like (wooden coated). This is an example of which of the following?

A.

Risk

B.

Assumption

C.

Constraint

D.

Budget

Question # 129

A scope management plan In which of the following scope management processes is the scope management plan prepared?

A.

Initiation

B.

Collect Requirements

C.

Define Scope

D.

Verify Scope

Question # 130

Which of the following best describes project scope?

A.

The work that must be done in order to deliver a product with the specified features and functions

B.

The description of the project deliverables

C.

The authorizing document that allows the project manager to move forward with the project and to assign resources to the tasks

D.

The process of planning and executing all of the required work to deliver the project

Question # 131

Information should be communicated to __________.

A.

Everyone in the communication plan

B.

Everyone on the team

C.

Sponsor

D.

Team ' eacl

Question # 132

Which of the following activities is not part of Plan Risk Management?

A.

Updating risk register

B.

Determining risk roles and responsibilities

C.

Identifying risk categories

D.

Developing a risk management plan

Question # 133

The main purpose of project initiation is to ________.

A.

Assign the project manager to the project

B.

Formally describe the project

C.

Produce the project charter

D.

Formally authorize the project

Question # 134

__________ is providing detailed plans for tasks that are about to start in the near future using the most current information and revisiting future activities when they near their starting dates.

A.

Rolling wave planning

B.

Progressive elaboration

C.

Milestone detail planning

D.

Expert judgment

Question # 135

Which of the following provides the least accurate in estimating?

A.

Rough order of magnitude

B.

Budget estimate

C.

WBS estimate

D.

Definitive estimate

Go to page: