You'll find that our PMI-SP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-SP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Scheduling Professional practice test comfortably within the allotted time.
You are the project manager for the GHB Organization. Management has asked that you review your recent SPI to determine why there was a schedule variance. They'd also like you to explain what approach you'll do to counteract the SPI going forward in the project. You complete the variance analysis and report to management that you'll be fast tracking a portion of your project work. What will be the management's concern with, when it comes to fast tracking the project?
Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and she needs to express to her project team and to the management the importance of communication in this project. She would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?
You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?
You are the project manager for your organization. Maagement has asked you for this current project. You use the critical chain method to create the project network diagram rather than the more traditional critical path method. What is the critical chain method?
Maurice is the project manager of the NHQ Project and his project team has just finished the project activities. The quality control team reports that the project deliverables are perfect. The only thing left to in the project is to verify scope. This process will be performed by the project stakeholders. Maurice is required to submit a final project report and report on the project performance. Maurice's project had a budget of $234,000 but the project spent $245,000. In the final report management wants to know the project's cost performance index (CPI). What value should Maurice report?
Mark works as a project manager for BlueWell Inc. He is making relevant information available to the project stakeholders as required. According to Mark, which of the following are NOT the tools and techniques of the Distribute Information process?
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what your schedule variance is. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is the schedule variance for this project?