You'll find that our PMI-SP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-SP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Scheduling Professional practice test comfortably within the allotted time.

Question # 11

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your schedule variance for this project?

A.

$11,667

B.

1.02

C.

$7,000

D.

$-111,750

Question # 12

You are the project manager for your organization. You have worked with the project team to create the project scope statement. The key stakeholders have signed off on the project scope and they are eager for you and the project team to begin creating the deliverables identified within the project scope. What process must you and the project team complete next in this scenario?

A.

Create the activity list.

B.

Create the WBS.

C.

Create the risk assessment.

D.

Determine the project budget.

Question # 13

Mary is the project manager for her organization. She is working with the project team to define the project activities. She is concerned about some of the dependencies of the project work, which may affect the project schedule. Which one of the following is the best example of a project constraint that will likely affect the project ' s ability to finish by a given deadline?

A.

The project must use internal team members to complete the project work.

B.

The project must adhere to several regulations.

C.

The project must use the BGH company to deliver the software portion of the project.

D.

The project must not exceed $1,250,000.

Question # 14

You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

MeasurementsValues

BCWP (or EV)325

BCWS (or PV) 300

ACWP (or AC)410

What is the schedule variance (SV) of the project at the current point of time?

A.

+110

B.

-25

C.

-110

D.

+25

Question # 15

Fill in the blank with an appropriate phrase. The _______contains the schedule components and the rules for relating and using the components to represent the process for completing a project.

Question # 16

You are the project manager for your organization. You are coaching Allen, a junior project manager, on how the details of the project ' s critical path are calculated. Examine the figure given below:

What is the critical path of this project?

A.

ABEHJ

B.

ACFGJ

C.

ADGJ

D.

ACFIJ

Question # 17

You work as a project manager for BlueWell Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?

A.

Ideas to action

B.

Problem definition

C.

Problem solution generation

D.

Solution action planning

Question # 18

You are the project manager of a research project. Because much of the project work will be based on what is discovered in each stage of the project work, you are directing the project time to focus on creating time estimates for the most imminent research work and broad estimates for the project work that is coming later in the project. What type of planning are you using in this project?

A.

Milestone planning

B.

Rolling wave planning

C.

Phase gates

D.

Decomposition

Question # 19

You are the project manager for your organization. You have been recording the actual results of activity duration for your project. Many of the results are late and this is causing your project to be late on reaching its milestones. What tool and technique can you use as a part of controlling the schedule to help you review various scenarios to bring the schedule into alignment with the plan?

A.

What-if scenario analysis

B.

Root cause analysis

C.

Schedule analysis

D.

Resource leveling

Question # 20

Della works as a Project Manager for BlueWell Inc. A number of projects are running under her guidance. You, being a team leader of a project, provide Della the performance indexes of your project. The schedule variance (SV) of your project is zero. What does this figure depict?

A.

Project is right on target.

B.

Project is ahead of the schedule.

C.

Project is behind the schedule.

D.

Costs are higher than planned.