Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

PMI Scheduling Professional

Last Update 16 hours ago Total Questions : 323

The PMI Scheduling Professional content is now fully updated, with all current exam questions added 16 hours ago. Deciding to include PMI-SP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMI-SP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-SP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Scheduling Professional practice test comfortably within the allotted time.

Question # 41

You work as the project manager for BlueWell Inc. Mark, a project team member, has some doubts related to the outputs of the control schedule process. Which of the following is an output of the control schedule process?

A.

Project schedule

B.

Lessons learned

C.

Change request

D.

Activity resource requirement

Question # 42

Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project ' s outcome. How stakeholders are usually identified?

A.

Stakeholders are usually identified through a stakeholder register.

B.

Stakeholders are identified by the project team, project sponsor, and management.

C.

Stakeholders are identified through the project customers.

D.

Stakeholders are usually identified by interviewing identified stakeholders and expanding the list until all potential stakeholders are included.

Question # 43

You are the project manager of the NQQ project. You are working with your project team to create the activity duration estimates for the project. For each reported activity duration, your project team offers you an addition of five percent extra time for risks, errors, or aggressive estimating. What does Parkinson ' s Law state about this scenario?

A.

Work expands to fulfill the amount of time allotted to it.

B.

Risks will be allowed into activities in which management creates risk provisions.

C.

Laborers will create errors when time has been allotted for errors to exist.

D.

Errors will be allowed into assignments when management creates error opportunity.

Question # 44

You are the project manager for the GRT Project in your organization. You have created your time duration estimates based on historical information, but the estimates are not holding true in your current project. Unfortunately, many activities are late. You have decided to create a PERT estimate with your project team for each of their activities. What is the formula used for PERT?

A.

O+M+P

B.

(O+M+P)/3

C.

(O+4M+P)/6

D.

Average of the estimates

Question # 45

Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?

A.

Contract

B.

Reserve analysis

C.

Scope baseline

D.

Project schedule

Question # 46

Beth works as a project manager for BlueWell Inc. Which of the following tools and techniques of Administer Procurements process will Beth use to manage contracts, and procurement documentation and records?

A.

Records Management System

B.

Performance reporting

C.

Inspection and Audit

D.

Payment System

Question # 47

Bonnie is the project manager for her organization. She is developing a strategy to manage the project stakeholders. She wants to identify the key stakeholders, their influence over the project, their interest in project, and an assessment of methods. What can Bonnie create to gain support from the stakeholders in her project?

A.

Stakeholder identification tools

B.

Expert judgment

C.

Stakeholder Analysis Matrix

D.

Communications management plan

Question # 48

Tom is the project manager of the GHQ Project for his organization and he is working on recovering the project schedule. As Tom examines his schedule, he is especially aware of project activities with hard logic. What is hard logic?

A.

Hard logic describes activities that can be completed in any order but are positioned with finish-to-start relationships.

B.

Hard logic describes activities that have external constraints, such as a vendor.

C.

Hard logic describes activities that must be completed in a particular order unless additional resources with comparable skill sets can be added to the project.

D.

Hard logic describes activities that must be completed in a particular order.

Question # 49

Which of the following techniques is used in businesses to determine the effect different costs or investments have on profit and other financial indicators?

A.

Schedule analysis

B.

Resource leveling

C.

What-if scenario analysis

D.

Root cause analysis

Question # 50

You are the project manager for the NQQ Project for your organization. You and the project team are creating the activity list for the NQQ Project. You have instructed the project team members that they should include an activity identifier and a scope of work description for each activity in the activity list. Why is this information needed?

A.

To track the work to the project requirements

B.

To maintain profit and loss statements for the project

C.

To help the project team understand what work is required to be completed

D.

To communicate the work to be completed to the project stakeholders

Go to page: