Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

PMI Scheduling Professional

Last Update 16 hours ago Total Questions : 323

The PMI Scheduling Professional content is now fully updated, with all current exam questions added 16 hours ago. Deciding to include PMI-SP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMI-SP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-SP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Scheduling Professional practice test comfortably within the allotted time.

Question # 31

You work as the project manager for BlueWell Inc. You are reviewing and regulating the progress to meet the performance objectives defined in the project management plan. Mark, a trainee, has a doubt related to the inputs of monitor and control project work. Which of the following is the input to monitor and control project work?

A.

Project document updates

B.

Expert judgment

C.

Performance report

D.

Project management plan updates

Question # 32

Which of the following processes involves the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress and performance as well as to forecast the project results?

A.

Identify stakeholders

B.

Performance reporting

C.

Plan communications

D.

Stakeholder analysis

Question # 33

You are the project manager for your organization. Your current project has a schedule variance of -$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project performance?

A.

Your project is likely to be late and over budget.

B.

Your project is performing well.

C.

Your project has a planned value of $600,000.

D.

Your project is six percent off schedule and has a considerable schedule variance.

Question # 34

You are the project manager of the OOI Project and you ' re forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should at the 45 percent milestone today, but due to some early delays you ' re running late. What is the schedule variance of your project?

A.

-$29,350

B.

-$117,282

C.

-$938,260

D.

-$11,740

Question # 35

You are the project manager for your project. Your project is scheduled to last for one year and you are currently forty percent complete with the project. Based on your current performance measurements you have an SPI of .95 and a cost variance of -$24,000. You need to report this information to the management, but you will also need a solution to present with the variance information. Which one of the following can you present to the management as a part of the control schedule tools and techniques for variances?

A.

Work performance measurements

B.

Corrective actions

C.

Trim the project scope

D.

Causes of variances

Question # 36

Holly is the project manager for her organization. Her current project is running late and her project customer has asked Holly to find a method to apply corrective actions to the project schedule. Holly is exploring the concept of crashing the project. Which of the following statements is true about crashing the activities in Holly ' s project?

A.

The activities to be crashed must have additional quality control metrics associated with them.

B.

The activities to be crashed cannot be of fixed duration.

C.

The activities to be crashed cannot have risks associated with them greater than 0.80.

D.

The activities cannot be on the critical path in order to be crashed.

Question # 37

Mark is the project manager of the NHQ Project. Mark wants to create a salience model as part of his communications planning and scheduling. What does a salience model do for a project?

A.

Describes classes of stakeholders based on their power, urgency, and legitimacy.

B.

Classifies stakeholders based on their influence and impact.

C.

Describes classes of stakeholders based on their power and influence.

D.

Groups stakeholders based on their power and interest.

Question # 38

You are project manager of HHK project. Examine the network diagram given below:

A vendor reports that he will be four days late on the materials you ' ll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?

A.

Four days

B.

Six days

C.

Five days

D.

Zero, it is on the critical path.

Question # 39

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly ' s schedule variance for this project?

A.

$163,626

B.

$130,901

C.

-$985,040

D.

0.16

Question # 40

Which of the following techniques is used to perform progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure?

A.

Imminent activity management

B.

Predecessor-only diagramming

C.

Rolling wave planning

D.

Decomposition

Go to page: