Labour Day Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

Which process determines the risks that may affect the project and documents their characteristics?

A.

Control Risks

B.

Plan Risk Management

C.

Plan Risk Responses

D.

Identify Risks

Full Access
Question # 5

Which type of graphic is displayed below?

A.

Work breakdown structure

B.

Context diagram

C.

Control chart

D.

Pareto diagram

Full Access
Question # 6

Project Scope Management is primarily concerned with:

A.

Developing a detailed description of the project and product.

B.

Determining how requirements will be analyzed, documented, and managed.

C.

Defining and controlling what is and is not included in the project.

D.

Formalizing acceptance of the completed project deliverables.

Full Access
Question # 7

Which is an output from Distribute Information?

A.

Earned value analysis

B.

Trend analysis

C.

Project records

D.

Performance reviews

Full Access
Question # 8

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

A.

Complete project phase

B.

Project life

C.

The project life cycle

D.

Project cycle

Full Access
Question # 9

The following is a network diagram for a project.

The critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

17

Full Access
Question # 10

Which is an example of Administer Procurements?

A.

Negotiating the contract

B.

Authorizing contractor work

C.

Developing the statement of work

D.

Establishing evaluation criteria

Full Access
Question # 11

The following is a network diagram for a project.

The free float for Activity E is how many days?

A.

2

B.

3

C.

5

D.

8

Full Access
Question # 12

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

A.

Direct and Manage Project Work

B.

Develop Project Management Plan

C.

Plan Quality Management

D.

Monitor and Control Project Work

Full Access
Question # 13

Which action should a project manager take to ensure that the project management plan is effective and current?

A.

Conduct periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards.

D.

Complete the quality control checklist.

Full Access
Question # 14

Which of the following inputs is required for the WBS creation?

A.

Project Quality Plan

B.

Project Schedule Network

C.

Project Management Software

D.

Project Scope Management Plan

Full Access
Question # 15

When should quality planning be performed?

A.

While developing the project charter

B.

In parallel with the other planning processes

C.

As part of a detailed risk analysis

D.

As a separate step from the other planning processes

Full Access
Question # 16

Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

A.

updates.

B.

defect repairs.

C.

preventive actions.

D.

corrective actions.

Full Access
Question # 17

During project selection, which factor is most important?

A.

Types of constraints

B.

Internal business needs

C.

Budget

D.

Schedule

Full Access
Question # 18

Inputs to the Plan Risk Management process include the:

A.

cost management plan.

B.

risk management plan,

C.

activity list,

D.

risk register.

Full Access
Question # 19

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Full Access
Question # 20

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

A.

Schedule

B.

Quality

C.

Communications

D.

Cost

Full Access
Question # 21

The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Full Access
Question # 22

What is the critical chain method?

A.

A technique to calculate the theoretical early start and finish dates and late start and finish dates

B.

A schedule network analysis technique that modifies the project schedule to account for limited resources

C.

A schedule compression technique that analyzes cost and schedule trade-offs to determine how to obtain the greatest amount of compression for the least incremental cost

D.

A technique to estimate project duration when there is a limited amount of detailed information about the project

Full Access
Question # 23

When the business objectives of an organization change, project goals need to be:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

Full Access
Question # 24

Schedule milestones and a predefined budget are examples of:

A.

Project constraints.

B.

Requirements documentation.

C.

Organizational process assets.

D.

Activity cost estimates.

Full Access
Question # 25

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

A.

Estimate Costs

B.

Estimate Activity Resources

C.

Control Costs

D.

Determine Budget

Full Access
Question # 26

Which schedule development technique modifies the project schedule to account for limited resources?

A.

Human resource planning

B.

Fast tracking

C.

Critical chain method

D.

Rolling wave planning

Full Access
Question # 27

When cost variance is negative and schedule variance is positive, the project is:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.

Full Access
Question # 28

Which technique is commonly used for the Quantitative Risk Analysis activity?

A.

Brainstorming

B.

Strategies for Opportunities

C.

Decision Tree Analysis

D.

Risk Data Quality Assessment

Full Access
Question # 29

Which items are an output of the Perform Integrated Change Control process?

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Full Access
Question # 30

What defines the portion of work included in a contract for items being purchased or acquired?

A.

Procurement management plan

B.

Evaluation criteria

C.

Work Breakdown Structure (WBS)

D.

Contract Statement of Work (SOW)

Full Access
Question # 31

Which of the following are outputs of Develop Project Team?

A.

Human resources plan changes and project staff assignment updates

B.

Project management plan updates and enterprise environmental factor updates

C.

Resource calendars and project management plan updates

D.

Team performance assessments and enterprise environmental factor updates

Full Access
Question # 32

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

Full Access
Question # 33

An input to the Control Quality process is:

A.

Activity attributes

B.

Quality control measurements

C.

Enterprise environmental factors

D.

Deliverables

Full Access
Question # 34

Which of the following events would result in a baseline update?

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Full Access
Question # 35

Change requests are processed for review and disposition according to which process?

A.

Control Quality

B.

Control Scope

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Full Access
Question # 36

Budgets reserved for unplanned changes to project scope and cost are:

A.

Contingency reserves.

B.

Management reserves.

C.

Authorized budgets.

D.

Cost baselines.

Full Access
Question # 37

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

A.

Cost Plus Incentive Fee (CPIF)

B.

Fixed Price Incentive Fee (FPIF)

C.

Cost Pius Award Re (CPAF)

D.

Time and Material (T&M)

Full Access
Question # 38

Activity cost estimates are quantitative assessments of the probable costs required to:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Full Access
Question # 39

Which of the following are the components of the scope baseline?

A.

Project charter, project scope statement, and work breakdown structure (WBS)

B.

Project charter, project management plan, and plan procurement

C.

Project scope statement, work breakdown structure (WBS), and WBS dictionary

D.

Project management plan, plan procurement, and contract administration

Full Access
Question # 40

The CPI is .92, and the EV is US$172,500. What is the actual cost of the project?

A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Full Access
Question # 41

Which quality control technique illustrates the 80/20 principle?

A.

Ishikawa diagram

B.

Control chart

C.

Run chart

D.

Pareto chart

Full Access
Question # 42

A tool and technique used during the Perform Qualitative Risk Analysis process is:

A.

risk data quality assessment.

B.

variance and trend analysis.

C.

data gathering and representation techniques.

D.

risk audits.

Full Access
Question # 43

Which baselines make up the performance measurement baseline?

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Full Access
Question # 44

Administer Procurements is part of which Process Group?

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Closing

Full Access
Question # 45

Which process occurs within the Monitoring and Controlling Process Group?

A.

Cost Control

B.

Quality Planning

C.

Quantitative Risk Analysis

D.

Cost Budgeting

Full Access
Question # 46

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

Full Access
Question # 47

The Monitoring and Controlling Process Group includes processes that:

A.

Establish the scope, objectives, and course of action of a project,

B.

Define a new project or a new phase of an existing project.

C.

Track, review, and regulate the progress and performance of a project.

D.

Complete the work defined in the project management plan.

Full Access
Question # 48

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

A.

enterprise environmental factors.

B.

organizational process assets.

C.

project management plan,

D.

project funding requirements.

Full Access
Question # 49

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

A.

Performance organizations

B.

Schedule baselines

C.

Work performance measurements

D.

Change requests

Full Access
Question # 50

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

A.

Activity cost estimates

B.

Earned value management

C.

Cost management plan

D.

Cost baseline

Full Access
Question # 51

Change requests are an output from which Project Integration Management process?

A.

Direct and Manage Project Execution

B.

Develop Project Management Plan

C.

Close Project

D.

Develop Project Charter

Full Access
Question # 52

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

A.

Project sponsor

B.

Project manager

C.

Person responsible for project scheduling

D.

Person who is most familiar with the task

Full Access
Question # 53

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Full Access
Question # 54

Which of the following are three inputs to the risk register?

A.

Risk register updates, stakeholder register, and quality management plan

B.

Communication management plan, enterprise environmental factors, and activity duration estimates

C.

Risk management plan, activity cost estimates, and project documents

D.

Project scope statement, organizational process assets, and scope baseline

Full Access
Question # 55

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

Full Access
Question # 56

Create WBS is part of which of the following Knowledge Areas?

A.

Project Integration Management

B.

Project Scope Management

C.

Project Time Management

D.

Project Cost Management

Full Access
Question # 57

An imposed date for completion of the project by the customer is an example of a project:

A.

deliverable

B.

assumption

C.

constraint

D.

exclusion

Full Access
Question # 58

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

A.

divided among each of the phases or subprojects.

B.

repeated for each of the phases or subprojects.

C.

linked to specific phases or subprojects.

D.

integrated for specific phases or subprojects.

Full Access
Question # 59

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

A.

Historical relationships

B.

Dependency determination

C.

Bottom-up estimating

D.

Rolling wave planning

Full Access
Question # 60

An input to the Perform Integrated Change Control process is:

A.

expert judgment

B.

seller proposals

C.

the project charter

D.

the project management plan

Full Access
Question # 61

Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

A.

Budget plan

B.

Resource plan

C.

Scope plan

D.

Strategic plan

Full Access
Question # 62

Which tool or technique is used to develop the human resource management plan?

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Full Access
Question # 63

Which of the following types of a dependency determination is used to define the sequence of activities?

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

Full Access
Question # 64

Which characteristic do projects and operational work share in common?

A.

Performed by systems

B.

Constrained by limited resources

C.

Repetitiveness

D.

Uniqueness

Full Access
Question # 65

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

A.

start-to-start (SS)

B.

start-to-finish (SF)

C.

finish-to-start (FS)

D.

finish-to-finish (FF)

Full Access
Question # 66

The Perform Quality Assurance process occurs in which Process Group?

A.

Executing

B.

Monitoring and Controlling

C.

Initiating

D.

Planning

Full Access
Question # 67

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

A.

Product scope description

B.

Procurement statement of work

C.

Project schedule

D.

Work breakdown structure (WBS)

Full Access
Question # 68

Which of the following correctly describes when organizations and stakeholders are willing to accept varying degrees of risk?

A.

Risk analysis

B.

Risk tolerance

C.

Risk management

D.

Risk attitude

Full Access
Question # 69

Within project integration management, the statement of work (SOW) references which aspects of the project?

A.

Strategic plan, business need, and product scope description

B.

Contract, enterprise environmental factors, and organizational process assets

C.

Business plan, project management plan, and project schedule

D.

Product lifecycle, business objective, and management strategy

Full Access
Question # 70

Projects can intersect with an organizationā€™s operations at various points during the product life cycle such as:

A.

When there is an operations shutdown (i.e. a strike).

B.

When developing new products, upgrading products, or expanding outputs.

C.

When a project transitions from a temporary to a permanent status.

D.

When the project manager is promoted to operations manager.

Full Access
Question # 71

In complex projects/ initiating processes should be completed:

A.

Within a work package.

B.

In each phase of the project.

C.

To estimate schedule constraints.

D.

To estimate resource allocations.

Full Access
Question # 72

Which type of analysis would be used for the Plan Quality process?

A.

Schedule

B.

Checklist

C.

Assumption

D.

Cost-Benefit

Full Access
Question # 73

For a stakeholder with low interest and high power, the project manager should:

A.

Monitor the stakeholder.

B.

Manage the stakeholder closely.

C.

Keep the stakeholder satisfied.

D.

Keep the stakeholder informed.

Full Access
Question # 74

To which process is work performance information an input?

A.

Administer Procurements

B.

Direct and Manage Project Execution

C.

Create WBS

D.

Perform Qualitative Risk Analysis

Full Access
Question # 75

As the project progresses, which of the following is routinely collected from the project activities?

A.

Communication management activities

B.

Change requests

C.

Configuration verification and audit

D.

Work performance information

Full Access
Question # 76

A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?

A.

What-if scenario analysis

B.

Critical chain method

C.

Schedule crashing

D.

Resource leveling

Full Access
Question # 77

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

A.

Critical path method

B.

Critical chain method

C.

Resource leveling

D.

Schedule network analysis

Full Access
Question # 78

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

A.

Project document updates

B.

Activity list

C.

Activity attributes

D.

Project calendars

Full Access
Question # 79

Which of the following involves making information available to project stakeholders in a timely manner?

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Full Access
Question # 80

Quality and credibility of the qualitative risk analysis process requires that different levels of the riskā€™s probabilities and impacts be defined is the definition of what?

A.

Risk breakdown structure (RBS)

B.

Risk probability and impact

C.

Qualitative risk analysis

D.

Risk response planning

Full Access
Question # 81

Who is responsible for developing the project management plan and all related component plans?

A.

Project team

B.

Portfolio manager

C.

Project manager

D.

Project management office

Full Access
Question # 82

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Full Access
Question # 83

In a typical project, project managers spend most of their time:

A.

Estimating

B.

Scheduling

C.

Controlling

D.

Communicating

Full Access
Question # 84

Which cost estimate technique includes contingencies to account for cost uncertainty?

A.

Vendor bid analysis

B.

Three-point estimates

C.

Parametric estimating

D.

Reserve analysis

Full Access
Question # 85

An output of the Close Project (or Close Phase) process is:

A.

accepted deliverables

B.

organizational process asset updates

C.

work performance information

D.

project management plan updates

Full Access
Question # 86

The end point of a project phase can be referred to as:

A.

project failure

B.

closing process

C.

stage gate

D.

lifecycle

Full Access
Question # 87

A reward can only be effective if it is:

A.

Given immediately after the project is completed.

B.

Something that is tangible.

C.

Formally given during project performance appraisals.

D.

Satisfying a need valued by the individual.

Full Access
Question # 88

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

A.

Result

B.

Product

C.

Service

D.

Improvement

Full Access
Question # 89

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Full Access
Question # 90

The project management processes presented in the PMBOK GuideĀ® should:

A.

always be applied uniformly.

B.

be selected as appropriate by the sponsor.

C.

be selected as appropriate by the project team.

D.

be applied based on ISO guidelines.

Full Access
Question # 91

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

A.

Compromising

B.

Collaborating

C.

Smoothing

D.

Problem Solving

Full Access
Question # 92

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

A.

Force/direct

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Collaborate/problem solve

Full Access
Question # 93

Which of the following characteristics are found in a functional organizational structure?

A.

Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget

B.

Limited project manager authority, limited resource availability, and a part-time project manager's role

C.

Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role

D.

High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Full Access
Question # 94

What is a technique used in the performance reporting process?

A.

Expert judgment

B.

Project management methodology

C.

Stakeholder analysis

D.

Status review meetings

Full Access
Question # 95

Which organizational process assets update is performed during the Close Procurements process?

A.

Procurement audit

B.

Lessons learned

C.

Performance reporting

D.

Payment requests

Full Access
Question # 96

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

Full Access
Question # 97

An input to Close Project or Phase is:

A.

Accepted deliverables,

B.

Final products or services,

C.

Document updates,

D.

Work performance information.

Full Access
Question # 98

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Full Access
Question # 99

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

A.

One

B.

Five

C.

Six

D.

Seven

Full Access
Question # 100

In which Process Group are lessons learned documented?

A.

Planning

B.

Closing

C.

Executing

D.

Initiating

Full Access
Question # 101

When closing a project or phase, part of the process may require the use of which type of analysis?

A.

Reserve analysis

B.

Regression analysis

C.

Document analysis

D.

Product analysis

Full Access
Question # 102

Those who enter into a contractual agreement to provide services necessary for a project are:

A.

buyers

B.

sellers

C.

business partners

D.

product users

Full Access
Question # 103

The cost benefit analysis tool is used for creating:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Full Access
Question # 104

Lessons learned are created and project resources are released in which Process Group?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Full Access
Question # 105

Procurement audits, negotiated settlements, and a records management system are tools and techniques used in which Procurement Management process?

A.

Close Procurements

B.

Administer Procurements

C.

Plan Procurements

D.

Conduct Procurements

Full Access
Question # 106

The Closing Process Group includes which of the following Knowledge Areas?

A.

Project Risk Management and Project Procurement Management

B.

Project Integration Management and Project Procurement Management

C.

Project Risk Management and Project Integration Management

D.

Project Integration Management and Project Quality Management

Full Access
Question # 107

The completion of the project scope is measured against the:

A.

requirements documentation.

B.

project scope statement.

C.

project management plan.

D.

work performance measurements.

Full Access
Question # 108

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

A.

Cost-reimbursable contracts

B.

Time and Material contracts (T&M)

C.

Fixed-price contracts

D.

Cost Plus Fixed Fee Contracts (CPFF)

Full Access
Question # 109

Exhibit A is an example of which of the following types of Sequence Activities?

A.

Activity-on-arrow diagramming

B.

Precedence diagramming

C.

Project schedule network diagramming

D.

Mathematical analysis diagramming

Full Access
Question # 110

Which Knowledge Areas include processes from the Closing Process Group?

A.

Project Quality Management and Project Time Management

B.

Project Scope Management and Project Risk Management

C.

Project Stakeholder Management and Project Cost Management

D.

Project Integration Management and Project Procurement Management

Full Access
Question # 111

Which of the following is an example of the simplest fixed-price contract?

A.

Purchase requisition

B.

Purchase order

C.

Verbal agreement

D.

Request for quote

Full Access
Question # 112

Which of the following is a complete set of indexed contract documentation, including the closed contract?

A.

Procurement package

B.

Negotiated settlements

C.

Procurement file

D.

Procurement management plan

Full Access
Question # 113

Plan Risk Management is the process of defining how to:

A.

Communicate identified risks to the project stakeholders.

B.

Conduct risk management activities for a project.

C.

Analyze the impact a specific risk may have on the project.

D.

Address unexpected risks that may occur during a project.

Full Access
Question # 114

What characteristic do project and operational work share in common?

A.

Performed by systems

B.

Constrained by limited resources

C.

Repetitiveness

D.

Uniqueness

Full Access
Question # 115

What process determines which risks might affect the project?

A.

Qualitative risk analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Quantitative risk analysis

Full Access
Question # 116

A risk that arises as a direct result of implementing a risk response is called a:

A.

contingent risk

B.

residual risk

C.

potential risk

D.

secondary risk

Full Access
Question # 117

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

A.

Earned value management.

B.

Forecasting.

C.

Critical chain methodology.

D.

Critical path methodology.

Full Access
Question # 118

Which of the following is the primary output of the Identify Risks process?

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

Full Access
Question # 119

An output of the Develop Project Team process is:

A.

change requests

B.

team performance assessments

C.

project staff assignments

D.

project documents updates

Full Access
Question # 120

What type of project structure is a hierarchically organized depiction of the resources by type?

A.

Organizational breakdown structure (OBS)

B.

Resource breakdown structure (RBS)

C.

Work breakdown structure (WBS)

D.

Project breakdown structure (PBS)

Full Access
Question # 121

The scope of a project cannot be defined without some basic understanding of how to create the specified:

A.

objectives

B.

schedule

C.

product

D.

approach

Full Access
Question # 122

Which statement is true about the project management body of knowledge?

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Full Access
Question # 123

Projects are undertaken by an organization to support the:

A.

Product performance.

B.

Budget process.

C.

Collective capabilities.

D.

Organizational strategy.

Full Access
Question # 124

Which of the following is a narrative description of products, services, or results to be delivered by a project?

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

Full Access
Question # 125

Projects are separated into phases or subprojects; these phases include:

A.

feasibility study, concept development, design, and prototype.

B.

initiate, plan, execute, and monitor.

C.

Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.

D.

Identify Stakeholders, develop concept, build, and test.

Full Access
Question # 126

In which process group is the scope first defined?

A.

Initiating

B.

Planning

C.

Executing

D.

Controlling

Full Access
Question # 127

Most experienced project managers know that:

A.

every project requires the use of all processes in the PMBOKĀ® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

Full Access
Question # 128

Who selects the appropriate processes for a project?

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Full Access
Question # 129

What is project management?

A.

A logical grouping of project management inputs, outputs, tools, and techniques

B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

C.

Launching a process that can result in the authorization of a new project

D.

A formal, approved document that defines how the project is executed, monitored, and controlled

Full Access
Question # 130

In the Initiating Process Group, at what point does the project become officially authorized?

A.

When the project charter is signed

B.

When all the stakeholders agree on the scope of the project

C.

When the project manager is appointed

D.

When the necessary finance or funding is obtained

Full Access
Question # 131

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

A.

improvement

B.

program

C.

result

D.

portfolio

Full Access
Question # 132

What are the five Project Management Process Groups?

A.

Initiating, Planning, Executing, Monitoring and Controlling, and Closing

B.

Introduction, Planning, Executing, Monitoring and Controlling, and Closing

C.

Initiating, Planning, Executing, Monitoring and Controlling, and Ending

D.

Introduction, Planning, Implementation, Monitoring and Controlling, and Closure

Full Access
Question # 133

A project lifecycle is defined as:

A.

a collection of generally sequential and sometimes overlapping project phases.

B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

C.

a recognized standard for the project management profession.

D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Full Access
Question # 134

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

A.

Scope baseline

B.

Scope management plan

C.

Change management plan

D.

Cost baseline

Full Access
Question # 135

In which Project Management Process Group is the project charter developed?

A.

Monitoring and Controlling

B.

Executing

C.

Initiating

D.

Planning

Full Access
Question # 136

An issue log is an input to which Project Human Resource Management process?

A.

Manage Project Team

B.

Acquire Project Team

C.

Plan Human Resource Management

D.

Develop Project Team

Full Access
Question # 137

Which of the following is TRUE about most project life cycles?

A.

Staffing level is highest at the start.

B.

The stakeholders' influence is highest at the start.

C.

The level of uncertainty is lowest at the start.

D.

The cost of changes is highest at the start.

Full Access