Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM) Certification

Last Update 19 hours ago Total Questions : 748

The Certified Associate in Project Management (CAPM) Certification content is now fully updated, with all current exam questions added 19 hours ago. Deciding to include PMI-002 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMI-002 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-002 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) Certification practice test comfortably within the allotted time.

Question # 211

When Identify Risks should be performed?

A.

During Concept Phase

B.

During Development Phase

C.

During Implementation Phase

D.

On a regular basis throughout the project

Question # 212

Human resource administration is the primary responsibility of which of the following:

A.

Project Management Team

B.

Human Resources Department

C.

Executive Manager

D.

Project Manager

Question # 213

Estimated at Completion is determined by ___________.

A.

ETC + ACWP

B.

BAC - ETC

C.

BAC/CPI

D.

Both A and C

Question # 214

The communications management plan is primarily dependent on the ____________.

A.

Length of the project

B.

Physical location of team members

C.

Specific needs of the project

D.

Project deliverables

Question # 215

A document or tool which describes when and how human resources will be brought onto and taken off the project team is called _______.

A.

Staffing Management Plan

B.

Responsibility Assignment Matrix (RAM)

C.

Organizational Breakdown Structure (OBS)

D.

Resource Assignment Chart

Question # 216

In which of the following organizations the project manager role is likely to be part-time?

A.

Weak matrix

B.

Functional

C.

Balanced matrix

D.

Both A and B

Question # 217

Which of the following is not a tool or technique used during the Risk Quantification Process?

A.

Expected Monetary Value

B.

Contingency planning

C.

Decision Trees

D.

Statistical sums

Question # 218

Which of the following is not true about change requests?

A.

They always require additional funding.

B.

They happen while the project work is being done.

C.

They can be written or verbal.

D.

They can be requested by a stakeholder.

Question # 219

The ability of a product to be used for different purposes at different capacities and under different conditions determines its ____________.

A.

Usability

B.

Flexibility

C.

Operability

D.

Availability

Question # 220

Which of the following is a method for quantifying qualitative data in order to minimize the effect of personal prejudice on source selection?

A.

Weighting system

B.

Screening system

C.

Selecting system

D.

None of the above

Question # 221

A cost-plus-incentive-fee (CPIF) contract has an estimated cost of $150,000 with a predetermined fee of $15,000 and a share ratio of 80/20. The actual cost of the project is $130,000. How much profit does the seller make?

A.

$31,000

B.

$19,000

C.

$15,000

D.

None of the above

Question # 222

Which of the following are the outputs of Collect Requirements Process?

A.

Requirements documentation

B.

Requirements management plan

C.

The requirements tractability matrix

D.

Al1 of the above

Question # 223

Your project is moving ahead of schedule. Management elects to incorporate additional quality testing into the project to improve the quality and acceptability of the project deliverable. This is an example of which one of the following?

A.

Scope Creep

B.

Change Control

C.

Quality Assurance

D.

Integrated Change Control

Question # 224

Which of the following is true regarding IRR?

A.

IRR is a constrained optimization method.

B.

IRR assumes reinvestment at the cost of capital.

C.

IRR is the discount rate when NPV is greater than zero.

D.

IRR is the discount rate when NPV is equal to zero.

Go to page: