Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM) Certification

Last Update 21 hours ago Total Questions : 748

The Certified Associate in Project Management (CAPM) Certification content is now fully updated, with all current exam questions added 21 hours ago. Deciding to include PMI-002 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMI-002 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-002 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) Certification practice test comfortably within the allotted time.

Question # 196

Purchasing insurance is an example of __________.

A.

Transfer

B.

Acceptances

C.

Mitigation

D.

Contingency

Question # 197

Which of the following statement is true about Strategic planning?

A.

Strategic planning determines which projects will be choosing in order to achieve the organizational goals

B.

Strategic planning determines which projects will be sponsor in order to achieve the organizational goals

C.

Strategic planning determines these are the projects that get chosen and funded

D.

Al1 of the above

Question # 198

What is a corrective action?

A.

An action that brings future project events Into alignment with the project plan

B.

An action to correct something in the project

C.

An action to prevent something in the project

D.

Corrective action is not related to project

Question # 199

You are project manager of a project and as part of the team acquisition process; you hire a new employee and assigns him to your project team. According to Maslow ' s hierarchy of needs, what needs level he most likely is at?

A.

Social need

B.

Physical need

C.

Safety and security

D.

Security

Question # 200

You have a piece of equipment that was purchased for your project recently for $5,000 and is expected to last 5 years in production. At the end of the five years the expected worth of the equipment is $2,000. Using straight-line deprecation, what is the amount that can be written off each year?

A.

$600

B.

$1200

C.

$3000

D.

Zero

Question # 201

Make-or-buy decisions measure the costs of both options. What are the two options?

A.

Direct ar|d Indirect

B.

Tactical and Strategic

C.

Management and Project

D.

0n|y Tactical

Question # 202

Which of the following best describes project scope?

A.

The work that must be done in order to deliver a product with the specified features and functions

B.

The description of the project deliverables

C.

The authorizing document that allows the project manager to move forward with the project and to assign resources to the tasks

D.

The process of planning and executing all of the required work to deliver the project

Question # 203

What is the communication channel delta if the members in the communication plan are increased from 5 to 10?

A.

35

B.

5

C.

15

D.

75

Question # 204

When Identify Risks should be performed?

A.

During Concept Phase

B.

During Development Phase

C.

During Implementation Phase

D.

Identify Risks should be performed on a regular basis throughout the project

Question # 205

Which of the following is NOT a tool or technique used during the Perform quantitative risk analysis Process?

A.

Expected Monetary Value Analysis

B.

Risk Categorization

C.

Interviewing

D.

Sensitivity Analysis

Question # 206

Project Risk Management includes all of the following processes EXCEPT ________.

A.

Plan Risk Management

B.

Identify Risks

C.

Risk Analysis

D.

Plan R^ Response

Question # 207

A scope management plan describes __________.

A.

An assessment of the stability of the stakeholder environment

B.

A highly detailed approach to managing the work breakdown structure scope

C.

How the project scope will be managed and how scope changes will be integrated into the project

D.

The stakeholder ' s expectation on how changes will be identified and by what priority they will be addressed

Question # 208

Estimate Costs_____________.

A.

Involves developing an estimate of the costs of the resources needed to complete project activities

B.

Cost estimates are generally expresses in unit of some currency.

C.

Involves allocating the overall estimates to individual work items

D.

All of the above

Question # 209

Which of the following is NOT considered as strategy for negative risk ?

A.

Avoid

B.

Transfer

C.

Accept

D.

ExPlot

Question # 210

A Strong Matrix is _____.

A.

A balanced matrix organization

B.

Where all team members are brought together in one location

C.

Where functional managers operate in a dual reporting structure reporting to both their own departments and to the project manager

D.

Power reset with Functional Manager

Go to page: