You'll find that our PMI-002 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-002 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) Certification practice test comfortably within the allotted time.

Question # 151

The cost effective rule for shortening a project is to crash the:

A.

Critical tasks-

B.

Non-critical tasks.

C.

Tasks with lowest cost.

D.

Tasks with highest cost.

Question # 152

Based on the PMBOK, who is ultimately responsible for the project quality?

A.

Project team

B.

Project manager

C.

QA manager

D.

Validation engineer

Question # 153

As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is which of the following?

A.

Documenting and meeting the requirements

B.

Reporting project status regularly and in a timely manner

C.

Documenting and meeting the performance measurements

D.

Reporting changes and updating the project plan and other project documents where appropriate

Question # 154

The party that needs the change resulting from the project, and who will be its custodian on completion is the _________.

A.

Owner

B.

client

C.

Sponsor

D.

Customer

Question # 155

As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is which of the following?

A.

Documenting and meeting the requirements

B.

Reporting project status regularly and in a timely manner

C.

Documenting and meeting the performance measurements

D.

Reporting changes and updating the project plan and other project documents where appropriate

Question # 156

Which process involves monitoring, measuring, and taking corrective action?

A.

Executing processes

B.

Planning processes

C.

Controlling Processes

D.

Closing processes

Question # 157

Which of the following is required for Control Scope?

A.

Risk mitigation

B.

Charter update

C.

Verify Scope

D.

Cost-benefit analysis

Question # 158

You are in process of developing an approximation of the costs of resources needed to complete each schedule activity. Which of the following is the least helpful input?

A.

WBS, WS dictionary

B.

Market place conditions, commercial databases

C.

Estimate Costs policies/ templates, historical information, project team knowledge

D.

Activity cost estimates, activity cost estimate supporting detail

Question # 159

Which of the following are not tools and techniques of source selection ?

A.

a weighting system.

B.

Organizational policies

C.

Independent estimates.

D.

A screening system.

Question # 160

You have been assigned to a project where the objective is to create a new building. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. You have been hired on contract and will be released at the completion of the demolition phase. What type of organizational structure you are working for?

A.

Projectized organization

B.

Weak matrix organization

C.

Balanced matrix organization

D.

Functional organization

Question # 161

Which of the following conflict resolution approaches is likely to lead to the MOST long-lasting solutions?

A.

Negotiating

B.

Smoothing

C.

Problem solving

D.

Compromising

Question # 162

The MOST important selection criterion to select a project manager for a large project in a technical industry is:

A.

Communication and Integration skills.

B.

Specific technical specialization.

C.

Financial management experience.

D.

Industry and business experience.

Question # 163

Bar charts generally illustrate:

A.

Progress of status.

B.

The critical path.

C.

Budget relation ships.

D.

Logical relationships.

Question # 164

To determine the impact of a change that has occurred, which of the following should be taken?

A.

Re-evaluate the work breakdown structure.

B.

Assess the communication policy.

C.

Review the earned value

D.

Performance measurement

Question # 165

All of the statements regarding control accounts and planning packages are true EXCEPT:

A.

Control accounts and planning packages are tools and techniques of Develop Schedule process.

B.

A control account is an assigned WBS level used to monitor cost and schedule performance of significant element of work.

C.

Planning packages reflect a future segment of work within a control account that has not yet been decomposed into detailed work packages.

D.

As work becomes more clearly defined, planning packages are converted into work packages.