You'll find that our PMI-100 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-100 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM)® practice test comfortably within the allotted time.

Question # 181

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

A.

Bottom-up

B.

Three-point

C.

Parametric

D.

Analogous

Question # 182

An output of Control Schedule is:

A.

A project schedule network diagram

B.

A schedule management plan

C.

Schedule data

D.

Schedule forecasts

Question # 183

Which Process Group typically consumes the bulk of a project ' s budget?

A.

Monitoring and Controlling

B.

Executing

C.

Planning

D.

Initiating

Question # 184

A procurement management plan is a subsidiary of which other type of plan?

A.

Resource plan

B.

Project management plan

C.

Cost control plan

D.

Expected monetary value plan

Question # 185

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Question # 186

Which of the following tools or techniques is used for Estimate Activity Durations?

A.

Critical path method

B.

Rolling wave planning

C.

Precedence diagramming method

D.

Parametric estimating

Question # 187

The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Question # 188

At the end of the project, what will be the value of SV?

A.

Positive

B.

Zero

C.

Negative

D.

Greater than one

Question # 189

Inputs to the Plan Risk Management process include the:

A.

cost management plan.

B.

risk management plan,

C.

activity list,

D.

risk register.

Question # 190

Which of the following is an input to Direct and Manage Project Execution?

A.

Performance reports

B.

Project charter

C.

Outputs from planning processes

D.

Enterprise environmental factors

Question # 191

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

A.

Sensitivity analysis

B.

Three-point estimate

C.

Modeling and simulation

D.

Expected monetary value analysis

Question # 192

Prototype development may be used as a tool for which of the following risk response strategies?

A.

Avoid

B.

Accept

C.

Mitigate

D.

Exploit

Question # 193

Which of the following is a strategy to deal with positive risks or opportunities?

A.

Mitigate

B.

Transfer

C.

Exploit

D.

Avoid

Question # 194

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

A.

Forming

B.

Storming

C.

Norming

D.

Performing

Question # 195

Which characteristics do effective project managers possess?

A.

Project management knowledge, performance skills, and personal effectiveness

B.

Preparedness, project management knowledge, and personality characteristics

C.

General management, preparedness, and project management knowledge

D.

Assertiveness, collaboration, and performance skills