Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)

Last Update 16 hours ago Total Questions : 1320

The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 16 hours ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.

Question # 51

An organization is faced with increasing demand from the board of directors. They say budgets are flexible as long as the work gets completed.

What project management approach should the organization use?

A.

Predictive

B.

Hybrid

C.

Iterative

D.

Adaptive

Question # 52

A risk that arises as a direct result of implementing a risk response is called a:

A.

contingent risk

B.

residual risk

C.

potential risk

D.

secondary risk

Question # 53

A project manager is reviewing a few techniques that can be used to evaluate solution results. The intent is to uncover whether the solution responds properly to unintended cases.

Which evaluation technique should be used here?

A.

Exploratory testing

B.

Integration testing

C.

User acceptance testing

D.

Day-in-the-life testing

Question # 54

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

A.

exploit

B.

avoid

C.

mitigate

D.

share

Question # 55

During the execution of a predicted project, the need for a new product feature has been proposed by the customer. What should the project manager do next?

A.

Decline any request by the customer and continue the project as initially planned.

B.

Accept the customer ' s request and continue with elicitation of the new product features.

C.

Investigate the possibility of using the management reserve to pay for the extra hours the team will need to work.

D.

Investigate the effect that such an integration will have on the project plan and propose a change request.

Question # 56

A project manager has been assigned to a project with a short duration and given funding to form a small team. The project manager needs to choose team members based on their availability and other aspects.

What other features should the project manager consider?

A.

Skill set, expertise, and training readiness

B.

Past project performance, wage rate, and network base

C.

Collaborative skills, quality focus, and political connections

D.

Priorities, resource demand, and expertise

Question # 57

In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?

A.

The organization

B.

The project

C.

The industry

D.

The product

Question # 58

A construction project is underway with three months left to complete the building. A public authority responsible for approving the final stage is stalling the project. What should the project manager do?

A.

Discuss this with the department head and arrive at an acceptable solution to expedite the approval process.

B.

Report the issue to major stakeholders and explore possible corrective actions along with legal assistance.

C.

Mitigate the risk by requesting an alternative public authority to participate in the approval process.

D.

Visit the public authority headquarters and formally petition them, demanding an explanation about the delay.

Question # 59

Which document defines how a project is executed, monitored and controlled, and closed?

A.

Strategic plan

B.

Project charter

C.

Project management plan

D.

Service level agreement

Question # 60

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

A.

Portfolio

B.

Process

C.

Project

D.

Program

Question # 61

Tools and techniques used in Direct and Manage Project Work include:

A.

Process analysis and expert judgment

B.

Analytical techniques and a project management information system

C.

Performance reviews and meetings

D.

Expert judgment and meetings

Question # 62

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Question # 63

How is program success measured?

A.

By delivering the benefit of managing the program ' s projects in a coordinated manner

B.

By the quality, timeliness, cost-effectiveness, and customer satisfaction of the product or service

C.

By completing the right projects to achieve objectives rather than completing projects the right way

D.

By aggregating the successes of the individual projects in the program

Question # 64

Technical capability, past performance, and intellectual property rights are examples of:

A.

performance measurement criteria

B.

source selection criteria

C.

product acceptance criteria

D.

phase exit criteria

Question # 65

Which tools and techniques should a project manager use when estimating costs?

A.

Lessons learned register and cost aggregation

B.

Project schedule and resources requirements

C.

Three-point estimating and risk register

D.

Expert judgempnt and decision making

Question # 66

Match each dimension of the communications management plan to its corresponding focus.

Question # 67

Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

A.

Internal enterprise environmental factor

B.

Risk register database

C.

External enterprise environmental factor

D.

Organizational process asset

Question # 68

After winning a large government contract, a company needs to hire a portfolio manager What vital qualification should candidates possess?

A.

Ability to manage strategic goals across multiple projects

B.

Skills to manage a large project

C.

Competency to manage multiple projects that align departments

D.

Capability of managing project schedules

Question # 69

An input of the Plan Procurement Management process is:

A.

Make-or-buy decisions.

B.

Activity cost estimates.

C.

Seller proposals.

D.

Procurement documents.

Question # 70

In agile projects while performing scope management. What is the definition of requirements

A.

Metrics

B.

Sprint

C.

Charter

D.

Backlog i

Question # 71

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

A.

Smooth/accommodate

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Force/direct

Question # 72

What describes the relationship between projects, programs, and portfolios?

A.

Portfolio management focuses on doing the " right " programs and projects.

B.

Project management focuses on doing the " right " programs and portfolios.

C.

Program management focuses on doing the " specific " portfolios and projects.

D.

Portfolio management focuses on doing the ' ' specific’’ programs and projects.

Question # 73

What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?

A.

Expert judgment

B.

Interpersonal skills

C.

Team agreements

D.

Communication skills

Question # 74

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

A.

0.50

B.

0.67

C.

1.50

D.

2.00

Question # 75

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

A.

Negative

B.

Zero

C.

Positive

D.

Free

Question # 76

The Identify Stakeholders process is found in which Process Group?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Executing

Question # 77

Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?

A.

A self-organizing approach to increase team focus and maximize collaboration

B.

A virtual team to minimize feeling of isolation and gaps on sharing knowledge

C.

A distributed team to improve tracking progress, productivity, and performance

D.

A norming approach that requires team members to adjust their behavior and work together

Question # 78

What key component of the project charter defines the conditions for dosing a project phase?

A.

Purpose

B.

Approval requirements

C.

Exit criteria

D.

High-level requirements

Question # 79

An input to Conduct Procurements is:

A.

Independent estimates.

B.

Selected sellers.

C.

Seller proposals.

D.

Resource calendars.

Question # 80

Which of the following documents ate created as part of Project Integration Management?

A.

Project charter and project management plan

B.

Communications management plan and scope management plan

C.

Quality management plan and risk management plan

D.

Project scope statement and communications management plan

Question # 81

Whose approval may be required for change requests after change control board (CCB) approval?

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Question # 82

Which component of the project management plan should be updated if a change occurs?

A.

Project charter

B.

Project baseline

C.

Assumption log

D.

Schedule forecast

Question # 83

What purpose does the hierarchical locus of stakeholder communications serve?

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the tocus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media, and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Question # 84

A project manager is performing a specific process and has..........is being referred to?

A project manager is performing a specific process and has a list of accepted deliverables One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables Which process is being referred to?

A.

Control Quality

B.

Validate Scope

C.

Validate Quality

D.

Control Scope

Question # 85

What should a project manager consider to address the full delivery life cycle for large projects?

A.

A range of techniques utilizing a plan driven approach, adaptive approach or a hybrid or both

B.

Only techniques of an agile/adaptive approach in large organizations

C.

Change the role of the project manager to managing pro|ci I in adaptive nuviionin-

D.

Splitting larger projects into two or more smaller project is which can be addressed in an adaptive method

Question # 86

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

A.

Estimate Costs

B.

Estimate Activity Resources

C.

Control Costs

D.

Determine Budget

Question # 87

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

A.

Mandatory

B.

Discretionary

C.

Internal

D.

External

Question # 88

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Question # 89

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

A.

Develop Schedule

B.

Control Schedule

C.

Estimate Activity Durations

D.

Define Activities

Question # 90

Who is responsible for initiating a project?

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Question # 91

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

A.

Direct and Manage Project Work

B.

Develop Project Management Plan

C.

Plan Quality Management

D.

Monitor and Control Project Work

Question # 92

Which are examples of processes that may be used once or at predefined points in the project life cycle?

A.

Develop Project Charter and Close Project or Phase

B.

Define Activities and Acquire Resources

C.

Control Schedule and Conduct Procurements

D.

Monitor Communications and Control Costs

Question # 93

A project manager needs to determine the schedule variance (SV). The project manager ' s latest schedule indicates 14 units of work completed against a plan of 23 units.

What is the SV?

A.

-9

B.

37

C.

9

D.

322

Question # 94

How is the schedule variance calculated using the earned value technique?

A.

EV less AC

B.

AC less PV

C.

EV less PV

D.

AC less EV

Question # 95

In an organization with a projectized organizational structure, who controls the project budget?

A.

Functional manager

B.

Project manager

C.

Program manager

D.

Project management office

Question # 96

A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.

Which process is the project manager executing?

A.

Manage Quality

B.

Plan Quality Management

C.

Control Quality

D.

Plan Scope Management

Question # 97

How many Project Management Process Groups are there?

A.

3

B.

4

C.

5

D.

6

Question # 98

Who determines which dependencies are mandatory during the Sequence Activities process?

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Question # 99

Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

A.

Budget plan

B.

Resource plan

C.

Scope plan

D.

Strategic plan

Question # 100

The chart below is an example of a:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Go to page: