Weekend Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)

Last Update 3 hours ago Total Questions : 1326

The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 3 hours ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.

Question # 201

A project team identifies defects that will require a modification to a tool ' s functionality. What process should the project manager follow to obtain stakeholder buy-in?

A.

Control Schedule

B.

Perform Qualitative Risk Analysis

C.

Perform Integrated Change Control

D.

Control Scope

Question # 202

The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?

A.

Plan Cost Management

B.

Estimate Activity Resources

C.

Estimate Costs

D.

Determine Budget

Question # 203

What scenario describes when a project must be created due to market demand?

A.

A public company authorizes a project to create a new service for electric car sharing to reduce pollution.

B.

A car company authorizes a project to build more fuel-efficient cars in response to gasoline shortages.

C.

Researchers develop an autonomous car. with several new features to be commercialized in the future.

D.

Stakeholders request that raw matenais be changed due to locally high costs.

Question # 204

Match the project life cycle type with its corresponding definition.

Question # 205

In a project, the cost performance indicator (CPI) is less than 1 and the schedule performance indicator (SPI) is more than 1. What is the status of the project?

A.

The project is over budget and behind schedule.

B.

The project is over budget and ahead of schedule.

C.

The project is under budget and behind schedule.

D.

The project is under budget and ahead of schedule.

Question # 206

Which of the following set of items belongs to the communications management plan?

A.

Escalation processes and meeting management

B.

Project schedule and glossary of common terminology

C.

Escalation processes and stakeholder communication requirements

D.

Interactive communication model and information to be communicated

Question # 207

The Define Scope process is in which of the following Process Groups?

A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

Question # 208

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Question # 209

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

A.

Forming

B.

Storming

C.

Norming

D.

Performing

Question # 210

Which document includes the project scope, major deliverables, assumptions, and constraints?

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

Question # 211

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

A.

Start-to-start (SS)

B.

Start-to-finish (SF)

C.

Rnish-to-finish (FF)

D.

Finish-to-start (FS)

Question # 212

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Question # 213

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

A.

Salience

B.

Influence/impact

C.

Power/interest

D.

Power/influence

Question # 214

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

A.

100

B.

120

C.

1,000

D.

1,200

Question # 215

A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence.

What should the project manager do first?

A.

Extend an iteration review invite to the new stakeholder.

B.

Perform qualitative risk analysis.

C.

Engage with the new stakeholder.

D.

Allow team members to share project status reports.

Question # 216

Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

A.

Collaboration

B.

Negotiation

C.

Decision making

D.

Influencing

Question # 217

Which is a tool or technique used in Define Scope?

A.

Templates, forms, and standards

B.

Change requests

C.

Product analysis

D.

Project assumptions

Question # 218

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

Question # 219

What does a CPI value greater than 1.0 indicate?

A.

Cost right at the estimated value

B.

Cost under the estimated value

C.

Cost right at the actual value

D.

Cost over the estimated value

Question # 220

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

A.

8

B.

18

C.

36

D.

40

Question # 221

In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?

A.

Hold a face-to-face meeting with the project manager and warn them.

B.

Point the director to a link where they can take a look at the reports.

C.

Invite stakeholders to attend monthly progress review meetings.

D.

Ask the project manager to update the monthly status report distribution list.

Question # 222

A project manager is reviewing the change requests, deliverables, and the project plan in Which project management process does this review belong?

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Closes Project or Phase

D.

Perform itegrated Change Control

Question # 223

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Question # 224

Which of the following techniques is used during Control Scope?

A.

Cost-benefit analysis

B.

Variance analysis

C.

Reserve analysis

D.

Stakeholder analysis

Question # 225

What is a tool or technique used in the Control Quality process?

A.

Attribute sampling

B.

Parametric estimating

C.

Statistical sampling

D.

Expert judgment

Question # 226

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Question # 227

Which of the following is a tool and technique for Estimate Activity Durations?

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Alternatives analysis

D.

Bottom-up estimating

Question # 228

Which Manage Communications tool or technique focuses on identifying and managing barriers?

A.

Communication methods

B.

Information technology

C.

Communication models

D.

Information management systems

Question # 229

A project manager builds consensus and overcomes obstacles by employing which communication technique?

A.

Listening

B.

Facilitation

C.

Meeting management

D.

Presentation

Question # 230

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

A.

Efficient

B.

Effective

C.

Push

D.

Pull

Question # 231

At which point of the project is the uncertainty the highest and the risk of failing the greatest?

A.

Final phase of the project

B.

Start of the project

C.

End of the project

D.

Midpoint of the project

Question # 232

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Question # 233

Activity cost estimates are quantitative assessments of the probable costs required to:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Question # 234

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

A.

event.

B.

response,

C.

perception.

D.

impact.

Question # 235

The primary benefit of the Plan Schedule Management process is that it:

A.

provides guidance to identify time or schedule challenges within the project.

B.

tightly links processes to create a seamless project schedule.

C.

guides how the project schedule will be managed throughout the project.

D.

creates an overview of all activities broken down into manageable subsections.

Question # 236

In which domain of project management would a Pareto chart provide useful information?

A.

Project Scope Management

B.

Project Time Management

C.

Project Communications Management

D.

Project Quality Management

Question # 237

A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager ' s key responsibility during this phase?

A.

Defining the scope of the project

B.

Building a collaborative environment

C.

Creating a detailed project management plan

D.

Directing the delivery of the project

Question # 238

For a stakeholder with low interest and high power, the project manager should:

A.

Monitor the stakeholder.

B.

Manage the stakeholder closely.

C.

Keep the stakeholder satisfied.

D.

Keep the stakeholder informed.

Question # 239

A project manager engages a highly specialized resource who is in a different location and cannot join the regular team meetings. This is leading to delays in productivity. How can the project manager assist the team to resolve the issue?

A.

Request the new resource be relocated with the rest of the team and document a change request forthe project.

B.

Ask the team to identify possible options to resolve the issue with minimal impact to the new resource.

C.

Log this issue in the issue log and escalate it to the management team, asking them to replace the new team member.

D.

Consult the communications management plan to review available options, such as special virtual meetings, with the new resource.

Question # 240

An executive sponsor wants to be briefed on how the product will change over time. Which document should the business analyst use to prepare their presentation?

A.

Project charter

B.

Product roadmap

C.

Project management plan

D.

Product requirements

Question # 241

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

A.

Discussing with management

B.

Escalating to the sponsors

C.

Engaging regularly with stakeholders

D.

Engaging only with decision makers

Question # 242

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

Question # 243

Which tool or technique is used in the Plan Scope Management process?

A.

Document analysis

B.

Observations

C.

Product analysis

D.

Expert judgment

Question # 244

Which document can help a project manager to leverage historical project information?

A.

Lessons learned register

B.

Schedule baseline

C.

Work performance data

D.

Deliverable acceptance forms

Question # 245

A tool or technique in Perform Quality Control that a project manager would use is:

A.

quality audits.

B.

process analysis.

C.

benchmarking.

D.

inspection.

Question # 246

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

A.

Procurement documents

B.

Communications plan

C.

Project charter

D.

Stakeholder register

Question # 247

How can working in iterations increase the quality of the product being built?

A.

Teams have to do less planning and focus more on quality.

B.

The project manager has more time to document goals in advance.

C.

Less testing is required since it is done at the end of the project.

D.

Requirements are frequently clarified by users of the product.

Question # 248

How does planning for prevention costs assist in meeting stakeholder needs and expectations, while still providing required performance and reliability?

A.

It details product or service failures experienced by the customer

B.

It clarifies the costs associated with assessing the quality of the product or service

C.

It accounts for costs used to avoid poor quality in the product or service

D.

It communicates product or service failures discovered by the project team

Question # 249

Which item is an input to the Define Activities process?

A.

Schedule data

B.

Activity list

C.

Risk register

D.

Scope baseline

Question # 250

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

A.

Requirements documentation

B.

Requirements traceability matrix

C.

Project management plan updates

D.

Project documents updates

Go to page: