Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)

Last Update 16 hours ago Total Questions : 1320

The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 16 hours ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.

Question # 151

Which stakeholder approves a project ' s result?

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Question # 152

Types of internal failure costs include:

A.

inspections.

B.

equipment and training.

C.

lost business.

D.

reworking and scrapping.

Question # 153

Which process requires implementation of approved changes?

A.

Direct and Manage Project Execution

B.

Monitor and Control Project Work

C.

Perform Integrated Change Control

D.

Close Project or Phase

Question # 154

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

A.

Change request

B.

Risk response

C.

Risk management plan

D.

Lessons learned

Question # 155

Conflict should be best addressed in which manner?

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Question # 156

A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterative and hybrid approaches. Which aspect of tailoring would this best represent?

A.

Life cycle approaches

B.

Resource availability

C.

Project dimensions

D.

Technology support

Question # 157

Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?

A.

Hybrid methodologies

B.

Risk register updates

C.

Outsourced project resources

D.

Reliance on lessons learned documents

Question # 158

Which tool and technique is used in Conduct Procurements?

A.

Teaming agreements

B.

Expert judgment

C.

Bidder conferences

D.

Contract types

Question # 159

The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?

A.

If the operation team members were trained externally

B.

If the transition process was agreed upon during the build

C.

If the end-user documentation was more thorough

D.

If the operations manager was invited to all sprint reviews

Question # 160

In order to detect quality Issues earlier in the project life cycle, the project manager is using an agile/adaptive environment. What is the main difference between waterfall and agile/adaptive development approaches tor Project Quality Management?

A.

The frequency of the quality and review steps

B.

The number of deliverables

C.

The duration of each of the quality and review steps

D.

The tools used in the quality and review steps

Question # 161

During project execution, a team member has identified and then analyzed an opportunity that

will yield a net saving of 10% and reduce time in the schedule by 20%

Which strategy should the project manager adopt to accommodate this opportunity?

A.

Escalate to upper management to build awareness of the opportunity.

B.

Exploit the opportunity immediately, since the cost saving makes it worthwhile.

C.

Transfer the opportunity to a partner and start a partner contract.

D.

Create a trail of the opportunity before full adoption, because of the risk associated.

Question # 162

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

A.

Work breakdown structure

B.

Requirements document

C.

Project charter

D.

Project management plan

Question # 163

A tool and technique used during the Perform Qualitative Risk Analysis process is:

A.

risk data quality assessment.

B.

variance and trend analysis.

C.

data gathering and representation techniques.

D.

risk audits.

Question # 164

To which process is work performance information an input?

A.

Administer Procurements

B.

Direct and Manage Project Execution

C.

Create WBS

D.

Perform Qualitative Risk Analysis

Question # 165

Which knowledge area includes the processes to identify, define, and unify the various project management processes?

A.

Project Integration Management

B.

Project Communications Management

C.

Project Qualify Management

D.

Project Risk Management

Question # 166

Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

A.

Affinity

B.

Scatter

C.

Fishbone

D.

Matrix

Question # 167

Specification of both the deliverables and the processes is the focus of:

A.

Change control

B.

Configuration control

C.

Project monitoring and control

D.

Issue control

Question # 168

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Question # 169

Which type of chart is a graphic representation of a process showing the relationships among process steps?

A.

Control

B.

Bar

C.

Flow

D.

Pareto

Question # 170

An input to the Create WBS process is a:

A.

project charter.

B.

stakeholder register.

C.

project scope statement.

D.

requirements traceability matrix.

Question # 171

Which are the main objectives of Project Risk Management?

A.

Increase the probability of positive risks and decrease the probability of negative risks

B.

Avoid all kind of risks

C.

Increase the probability of positive risks and eliminate all negative risks

D.

Identify positive and negative risks

Question # 172

Which is an aspect of the requirements management plan?

A.

Detailed project scope statement

B.

Creation of work breakdown strucure (WBS)

C.

Impact analysis

D.

Duration for implementation

Question # 173

The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

A.

Least cost

B.

Qualifications only

C.

Sole source

D.

Fixed budget

Question # 174

When is a project finished?

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

Question # 175

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

A.

Organizational process assets

B.

A work breakdown structure

C.

The project management plan

D.

Enterprise environmental factors

Question # 176

What type of meeting is held to discuss prioritized product backlog items?

A.

Status

B.

Daily standup

C.

Iteration planning

D.

Release planning

Question # 177

What cost control technique is used to compare actual project performance to planned or expected performance?

A.

Cost aggregation

B.

Trend analysis

C.

Forecasting

D.

Variance analysis

Question # 178

Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?

A.

Project Plan

B.

Responsibility Matrix

C.

Issue Log

D.

Scope Document

Question # 179

Which element does a project charter contain?

A.

Management reserves

B.

Work breakdown structure

C.

Stakeholder list

D.

Stakeholder register

Question # 180

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

A.

Expert judgment.

B.

Analytical techniques.

C.

Earned value management.

D.

Group decision-making techniques.

Question # 181

A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager ' s key responsibility during this phase?

A.

Defining the scope of the project

B.

Building a collaborative environment

C.

Creating a detailed project management plan

D.

Directing the delivery of the project

Question # 182

Due to today ' s competitive global market, organizations require more than technical project management skills. Which of the following skills can support long-range strategic objectives that contribute to the bottom line?

A.

Planning and risk management skills

B.

Communication and time management skills

C.

Business intelligence and leadership skills

D.

Strategic and business management skills

Question # 183

A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure effective requirements elicitation. What should the business analyst do?

A.

Ask the project coordinator to facilitate some of the workshops.

B.

Invite both internal and external stakeholders to the workshops.

C.

Engage a consultant that is familiar with the community needs.

D.

Organize a workshop with the sponsor and major stakeholders.

Question # 184

A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype. Who should the project manager invite to provide expert advice?

A.

The subject matter experts (SMEs) identified in the stakeholder register

B.

The senior experts with high status in the academic community

C.

The major stakeholders nominated by the project sponsor

D.

The usual review participants holding recognized certifications

Question # 185

A project manager needs to request outside support......manager need to create

A project manager needs to request outside support for a statement ot work (SOW) that is not precise. Which kind of contract does the project manager need to create?

A.

Time and material (TandM)

B.

Cost plus fixed fee (CPFF)

C.

Fixed price

D.

Cost plus award fee (CPAF)

Question # 186

Which can be used to convert a verified deliverable to an accepted deliverable?

A.

Decomposition

B.

Reporting

C.

Voting

D.

Brainstorming

Question # 187

Company A’s accountant sends notification about a change in the company’s tax classification.

What would a project have to be initiated?

A.

To change business and technological strategies

B.

To improve processes and services

C.

To meet regulatory and legal requirements

D.

To satisfy stakeholder requests

Question # 188

A project team has missed a milestone.

Which response strategy should be implemented?

A.

Communications

B.

Stakeholder

C.

Contingent

D.

Risk

Question # 189

Which of the following is TRUE about most project life cycles?

A.

Staffing level is highest at the start.

B.

The stakeholders ' influence is highest at the start.

C.

The level of uncertainty is lowest at the start.

D.

The cost of changes is highest at the start.

Question # 190

The three processes of Project Cost Management are:

A.

Estimate Costs, Control Schedule, and Control Costs.

B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.

C.

Determine Budget, Control Schedule, and Estimate Activity Resources.

D.

Estimate Costs, Determine Budget, and Control Costs.

Question # 191

A weighting system is a tool for which area of Conduct Procurements?

A.

Plan contracting

B.

Requesting seller responses

C.

Selecting seller ' s

D.

Planning purchase and acquisition

Question # 192

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

A.

Acquisition

B.

Negotiation

C.

Virtual team

D.

Pre-assignment

Question # 193

The links between the processes in the Process Groups are often:

A.

Intuitive

B.

Iterative

C.

Measured

D.

Monitored

Question # 194

Which of the following does a portfolio combine?

A.

Projects, programs, and operations

B.

Operations, strategies, and business continuity

C.

Projects, programs, and risks

D.

Projects, change management, and operations

Question # 195

Which of the following factors is lowest at the start of the project?

A.

Cost of changes

B.

Stakeholder influences

C.

Risk

D.

Uncertainty

Question # 196

The project manager is looking at a precedence diagram.... the duration of this task?

The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.

What is the outcome of the duration of this task ' ?

A.

The task will be completed on time.

B.

The task will not be completed on time.

C.

Activity A is not a critical path task

D.

The precedence diagram cannot be used to provide answers for duration calculations

Question # 197

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

A.

Informal communication

B.

Internal communication

C.

Formal communication

D.

Horizontal communication

Question # 198

What tool or technique can improve a products final characteristics?

A.

Design for X (DfX)

B.

Problem solving

C.

Process analysis

D.

Risk report

Question # 199

A project team is working on a complex product and the work breakdown structure (WBS) is finalized. The team determines that the best approach is to use an adaptive delivery method and is now tasked with converting the WBS for adaptive delivery.

How can the team manage the conversion of the existing WBS to an adaptive approach?

A.

Generate use cases for each WBS element and prepare a requirements document.

B.

Produce a release plan for each WBS element and organize them into iterations for delivery.

C.

Create themes for each WBS element and organize them into iterations for delivery.

D.

Organize the WBS into a set of related themes, epics, and user stories.

Question # 200

Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?

A.

Product

B.

Cost-benefit

C.

Stakeholder

D.

Research

Go to page: