Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)

Last Update 20 hours ago Total Questions : 1337

The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 20 hours ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.

Question # 151

The milestone list is an input to which process from the Planning Process Group?

A.

Define Activities

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Question # 152

A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?

A.

Iteration planning

B.

Retrospective

C.

Backlog refinement review

D.

Daily standup

Question # 153

The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?

A.

If the operation team members were trained externally

B.

If the transition process was agreed upon during the build

C.

If the end-user documentation was more thorough

D.

If the operations manager was invited to all sprint reviews

Question # 154

Which is the order of steps in the Procurement Management process?

A.

Identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, contracting with selected vendors, and controlling procurements

B.

Identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, obtaining quotes or proposals, and controlling procurements

C.

Controlling procurements, identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, and contracting with selected vendors

D.

Obtaining quotes or proposals, identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, and controlling procurements

Question # 155

What cost control technique is used to compare actual project performance to planned or expected performance?

A.

Cost aggregation

B.

Trend analysis

C.

Forecasting

D.

Variance analysis

Question # 156

A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.

Which modeling tool best describes this process?

A.

Traceability

B.

User interface design

C.

Use case

D.

Wireframe

Question # 157

Which process requires implementation of approved changes?

A.

Direct and Manage Project Execution

B.

Monitor and Control Project Work

C.

Perform Integrated Change Control

D.

Close Project or Phase

Question # 158

Which format can a network diagram take?

A.

Flow chart

B.

Control chart

C.

Affinity diagram

D.

Cause-and-effect diagram

Question # 159

Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.

A.

2.0

B.

45

C.

0.5

D.

15

Question # 160

Requirements documentation will typically contain at least:

A.

Stakeholder requirements, staffing requirements, and transition requirements.

B.

Business requirements, the stakeholder register, and functional requirements.

C.

Stakeholder impact, budget requirements, and communications requirements.

D.

Business objectives, stakeholder impact, and functional requirements.

Question # 161

The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

A.

stakeholder management strategy.

B.

communications management plan,

C.

stakeholder register,

D.

performance report.

Question # 162

What is the total float of the critical path?

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Question # 163

What purpose does the hierarchical focus of stakeholder communications serve?

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the focus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Question # 164

A stakeholder is reading project documents given by the project manager. The stakeholder is

curious about the difference between a verified deliverable and an accepted deliverable.

Which of the following definitions can the project manager use to explain the difference?

A.

An accepted deliverable is approved by the project team; a verified deliverable is approved and formally signed off by the customer or sponsor.

B.

An accepted deliverable has been checked and confirmed for accuracy through the Control Quality process; a verified deliverable meets acceptance criteria that is formally signed off and approved by the customer or sponsor.

C.

An accepted deliverable meets acceptance criteria and is formally signed off and approved by the customer or sponsor, a verified deliverable is a completed project deliverable that has been checked and confirmed for accuracy through the Control Quality process

D.

An accepted deliverable meets acceptance criteria and is signed off by the project manager; a verified deliverable meets acceptance criteria and is signed off by the customer or sponsor.

Question # 165

At what stages of project should the identify Stakeholder process be performed?

A.

When beginning each phase of the project

B.

At the beginning of the project only

C.

Only when the project manager is concerned about stakeholder satisfaction

D.

When the project charter is produced, at the beginning of each phase, and when significant changes occur

Question # 166

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

A.

Perform Quality Control

B.

Quality Metrics

C.

Perform Quality Assurance

D.

Plan Quality

Question # 167

A project manager is identifying the risks of a project. Which technique should the project manager use?

A.

Representations of uncertainty

B.

Prompt lists

C.

Audits

D.

Risk categorization

Question # 168

Which three of the following are the most widely used techniques that a business analyst should implement to gather requirements? (Choose three)

A.

Current state analysis

B.

Facilitated workshops

C.

Scheduled interviews

D.

Shop floor observation

E.

Brainstorming sessions

Question # 169

What benefit does the Manage Stakeholder Engagement process offer?

A.

Allows the project manager to increase support and minimize resistance from stakeholders

B.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes

C.

Provides an actionable plan to interact effectively with stakeholders

D.

Enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders

Question # 170

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

A.

Scope baseline

B.

Organizational process assets

C.

Enterprise environmental factors

D.

Risk register

Question # 171

The chart below is an example of a:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Question # 172

The following is a network diagram for a project.

How many possible paths are identified for this project?

A.

3

B.

4

C.

6

D.

7

Question # 173

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Management

D.

Plan Risk Responses

Question # 174

Match the life cycle type to when its requirements are defined.

Question # 175

What organizational process asset (OPA) might impact a project ' s outcome?

A.

Processes, polices, and procedures

B.

Legal restrictions

C.

Infrastructure, resource availability. and employee capability

D.

Financial considerations

Question # 176

The scope of a project cannot be defined without some basic understanding of how to create the specified:

A.

objectives

B.

schedule

C.

product

D.

approach

Question # 177

The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?

A.

Co-location

B.

Lite-cycle

C.

Diversity

D.

Management

Question # 178

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

A.

0.45

B.

0.56

C.

0.70

D.

1.36

Question # 179

Which two processes should be used to influence costs in the early stages of a project?

A.

Estimate Costs and Determine Budget

B.

Plan Cost Management and Estimate Activity Durations

C.

Control Quality and Control Costs

D.

Plan Stakeholder Engagement and Plan Communications Management

Question # 180

An output of Control Schedule is:

A.

A project schedule network diagram

B.

A schedule management plan

C.

Schedule data

D.

Schedule forecasts

Question # 181

What is one reason why stakeholders must be identified when performing business analysis?

A.

To identify project timelines through business reviews

B.

To allow the business analyst to determine the project budget

C.

To identify who should define the business requirements for the project

D.

To determine a cost-benefit analysis for the project

Question # 182

When can we say that a project is completed?

A.

When the planned time duration is completed

B.

When the project objectives have been reached

C.

When the project manager has left the team

D.

When the project team decides to stop the work on the project

Question # 183

The following is a network diagram for a project.

The total float for the project is how many days?

A.

3

B.

5

C.

7

D.

9

Question # 184

What should a project manager do to prepare a risk management plan with a lot of technical uncertainty?

A.

Get expert judgment.

B.

Count on personal experience.

C.

Ask project sponsors.

D.

Delay the project until technical uncertainty is clarified

Question # 185

In agile projects while performing scope management. What is the definition of requirements

A.

Metrics

B.

Sprint

C.

Charter

D.

Backlog i

Question # 186

An input to Develop Project Charter is a/an:

A.

Business case.

B.

Activity list.

C.

Project management plan.

D.

Cost forecast.

Question # 187

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

A.

Monitor project stakeholder relationships using engaging strategies and plans

B.

Send all project documents to stakeholders each time they are modified

C.

Schedule monthly meetings with the stakeholders, including team members

D.

Engage only with the project sponsors

Question # 188

Which tool should a project manager use to calculate cost variance for a project?

A.

Contingency analysis

B.

Review lessons learned from similar projects

C.

Expert judgment

D.

Actual cost

Question # 189

Which input will be used when tasked with developing the human resource plan?

A.

Project management plan

B.

Activity resource requirements

C.

Resource calendar

D.

Project staff assignments

Question # 190

A key project team member complains about being left out of the communication loop. In order to ensure that each key member is involved, who should review the business analysis communications management plan?

A.

Business analyst, project manager, and sponsor

B.

Business analyst, project manager, and stakeholders

C.

Business analyst and project manager

D.

Only the business analyst

Question # 191

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

A.

Verified deliverables.

B.

Validated deliverables.

C.

Acceptance criteria.

D.

Activity resource requirements.

Question # 192

Which of the following factors within a company cloud trigger the creation of a project?

A.

Need to lower production costs to remain competitive

B.

Need to submit a warranty claim for a faulty product

C.

Need to submit the monthly production report

D.

Need to define next month ' s production goals

Question # 193

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three)

A.

High-level deliverables

B.

Phase transitions

C.

Project objectives

D.

Success criteria

E.

Cost

Question # 194

The links between the processes in the Process Groups are often:

A.

Intuitive

B.

Iterative

C.

Measured

D.

Monitored

Question # 195

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Question # 196

Which output is the approved version of the time-phased project budget?

A.

Resource calendar

B.

Scope baseline

C.

Trend analysis

D.

Cost baseline

Question # 197

Project managers plan a key role performing integration on the project what are the three different levels of integration?

A.

Process, cognitive

B.

Complexity, understand and change

C.

Interact, insight and leadership

D.

Communication, knowledge and value

Question # 198

A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.

Which of the following project delivery approaches should be recommended?

A.

Adaptive

B.

Hybrid

C.

Extreme

D.

Traditional

Question # 199

In which process is a project manager identified and given the authority to apply resources to project activities?

A.

Acquire Project Team

B.

Develop Project Management Plan

C.

Manage Project Execution

D.

Develop Project Charter

Question # 200

Every project creates a unique product, service, or result that may be:

A.

tangible

B.

targeted

C.

organized

D.

variable

Go to page: