Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)

Last Update 16 hours ago Total Questions : 1320

The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 16 hours ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.

Question # 101

Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

A.

Control Quality

B.

Monitor and Control Project Work

C.

Control Scope

D.

Perform Integrated Change Control

Question # 102

Which activity is an input to the Conduct Procurements process?

A.

Organizational process assets

B.

Resource availability

C.

Perform Integrated Change Control

D.

Team performance assessment

Question # 103

The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

A.

quality.

B.

value.

C.

technical performance.

D.

status.

Question # 104

The individual or group that provides resources and support for a project and is accountable for success is the:

A.

sponsor

B.

customer

C.

business partners

D.

functional managers

Question # 105

A product owner reviews the list of stakeholders to confirm their continued involvement with the product team. A new stakeholder is identified as actively involved in the next product release.

What should the project manager do next to engage the new stakeholder?

A.

Add the stakeholder to the communications management plan.

B.

Conduct a one-on-one interview with the stakeholder.

C.

Invite the stakeholder to the sprint-planning meeting.

D.

Send the stakeholder a questionnaire.

Question # 106

The organization ' s perceived balance between risk taking and risk avoidance is reflected in the risk:

A.

Responses

B.

Appetite

C.

Tolerance

D.

Attitude

Question # 107

A team is working on a project using an adaptive approach. During project execution, the project gets delayed by one month due to an unforeseen risk. What should the team do next to deliver this project?

A.

Stop working on the project completely, even if the team can continue working on the tasks with the identified risk.

B.

Accept the project delay and add the risk to the lessons learned document for the next project.

C.

Change the delivery date and deliver the initially agreed-upon scope after mitigation of the identified risk.

D.

Reprioritize the work based on the increased visibility of the current risks.

Question # 108

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

A.

Control Schedule

B.

Define Activities

C.

Develop Schedule

D.

Estimate Activity Resources

Question # 109

An example of a group decision-making technique is:

A.

nominal group technique

B.

majority

C.

affinity diagram

D.

multi-criteria decision analysis

Question # 110

Which Process Group and Knowledge Area include the Sequence Activities process?

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Question # 111

During a project team meeting, one of the team members suggested a product functionality that would immensely benefit the customer. The project manager documents the request for later analysis.

What is this an example of?

A.

Monitoring the traceability matrix

B.

Managing the scope

C.

Maintaining the product backlog

D.

Managing the cost benefit

Question # 112

Activity cost estimates are quantitative assessments of the probable costs required to:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Question # 113

The following is a network diagram for a project.

What is the critical path for the project?

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Question # 114

Which of the following is an example of an internal factor that influences the outcome of the project?

A.

Legal restrictions

B.

Financial considerations

C.

Commercial database

D.

Geographic distribution of facilities

Question # 115

What happens to a stakeholder ' s project influence over time?

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Question # 116

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

A.

Limited

B.

Low to moderate

C.

Moderate to high

D.

High to almost total

Question # 117

An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the product was to be launched in the beta phase. One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.

Why was the product still determined to be ready for delivery?

A.

The development team ran out of time and did not pull the social media story from the backlog.

B.

The development team completed all of the stories identified by the product owner as having the highest customer value.

C.

The sprint demo went smoothly and the team did not find any open issues.

D.

The social media story is a marketing priority and less important than other priorities.

Question # 118

For what project management process is work performance information an output?

A.

Implement Risk Responses

B.

Plan Stakeholder Engagement

C.

Monitor Stakeholder Engagement

D.

Plan Quality Management

Question # 119

Which statement is true about the project management body of knowledge?

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Question # 120

A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract Is this?

A.

Time and material (T8M)

B.

Fixed price incentive fee (FPIF)

C.

Cost plus fixed fee (CPFF)

D.

Cost plus award fee (CPAF)

Question # 121

A project is at risk of delivering the solution late because of poor quality that prevents the user acceptance testing (UAT) from being finalized. The product owner does not want to sign off until all the Severity 1 (S1) defects are fixed. What should the project manager do to manage this risk?

A.

Create a risk in the risk register for each S1 defect and assign actions.

B.

Consult the risk register and implement the risk response actions.

C.

Ask the developers to work longer hours and resolve the defects.

D.

Review the organizational chart to find out who else can sign off UAT.

Question # 122

A sponsor asks a project manager to provide a project ' s expected total costs based on its progress. What formula should the project manager use to determine this?

A.

Earned value (EV) / actual cost (AC)

B.

Estimate at completion (EAC) - AC

C.

Budget at completion (BAC) / cost performance index (CPI)

D.

EV - planned value (PV)

Question # 123

An issue log is an input to which Project Human Resource Management process?

A.

Manage Project Team

B.

Acquire Project Team

C.

Plan Human Resource Management

D.

Develop Project Team

Question # 124

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

A.

Control chart

B.

Earned value

C.

Variance

D.

Trend

Question # 125

An intentional activity to modify a nonconforming product or product component is called:

A.

defect repair

B.

work repair

C.

corrective action

D.

preventive action

Question # 126

Which statement correctly describes the value of a business case?

A.

It provides the necessary information to determine if a project is worth the required investment.

B.

It provides for alternative dispute resolution procedures in event of contract default.

C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D.

It is used to help a project manager understand the scope of commercial advantages.

Question # 127

A project manager was assigned to a project to implement a manufacturing system in a food factory. The main project objective is to deliver machines that are ready to process food. The project manager decides that this particular project does not require the use of timeboxed iterations.

Which method should the project manager adopt?

A.

SAFe®

B.

Kanban

C.

Feature-driven development (FDD)

D.

Scrum

Question # 128

Outputs of the Control Communications process include:

A.

expert judgment and change requests

B.

work performance information and change requests

C.

project management plan updates and work performance information

D.

issue logs and organizational process assets updates

Question # 129

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

A.

Benchmarking.

B.

Context diagrams.

C.

Brainstorming.

D.

Prototyping.

Question # 130

A project team has completed the sprint review and the users are impressed by the demo. However, another functionality included in the sprint that was not discussed in the review is not ready for production deployment.

What should the project team do?

A.

Demo the incomplete feature at the sprint retrospective.

B.

Deploy the functionality that was presented to the users.

C.

Wait to complete all user stories that are in development.

D.

Continue with sprints until the product backlog is empty.

Question # 131

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

A.

Plan Schedule Management.

B.

Develop Project Charter.

C.

Develop Schedule.

D.

Plan Scope Management.

Question # 132

Recognition and rewards are tools and techniques of which process?

A.

Develop Team

B.

Manage Team

C.

Control Resources

D.

Plan Resource Management

Question # 133

Which project documents can determine the budget?

A.

Procurement documents, contracts, requirements documentation, and basis of estimates

B.

Basis of estimates, cost estimates, project schedule, and risk register

C.

Business case, project charter, statement of work, and cost estimates

D.

Scope baseline, resource management plan, activity list, and assumption log

Question # 134

An input to the Collect Requirements process is the:

A.

stakeholder register.

B.

project management plan.

C.

project scope statement.

D.

requirements management plan.

Question # 135

While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.

What should the team do to ensure that this situation is managed?

A.

Implement Appropriate Response

B.

Plan Project Risk Management

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Question # 136

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

A.

lead

B.

lag

C.

mandatory dependency

D.

internal dependency

Question # 137

Which roles does the project manager resemble best?

A.

Orchestra conductor

B.

Facilities supervisor

C.

Functional manager

D.

School principal

Question # 138

A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place. What technique was followed?

A.

Collective decision making

B.

Multicriteria decision analysis

C.

Mind mapping

D.

Affinity diagram

Question # 139

An input to the Identify Stakeholders process is:

A.

The project management plan.

B.

The stakeholder register.

C.

Procurement documents.

D.

Stakeholder analysis.

Question # 140

Which is an enterprise environmental factor?

A.

Marketplace conditions

B.

Policies and procedures

C.

Project files from previous projects

D.

Lessons learned from previous projects

Question # 141

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

A.

8

B.

18

C.

36

D.

40

Question # 142

The process of identifying the stakeholders ' information needs is completed during:

A.

Plan Communications.

B.

Manage Stakeholder Expectations.

C.

Stakeholder Analysis.

D.

Identify Stakeholders.

Question # 143

A stakeholder is reading project documents given by the project manager. The stakeholder is

curious about the difference between a verified deliverable and an accepted deliverable.

Which of the following definitions can the project manager use to explain the difference?

A.

An accepted deliverable is approved by the project team; a verified deliverable is approved and formally signed off by the customer or sponsor.

B.

An accepted deliverable has been checked and confirmed for accuracy through the Control Quality process; a verified deliverable meets acceptance criteria that is formally signed off and approved by the customer or sponsor.

C.

An accepted deliverable meets acceptance criteria and is formally signed off and approved by the customer or sponsor, a verified deliverable is a completed project deliverable that has been checked and confirmed for accuracy through the Control Quality process

D.

An accepted deliverable meets acceptance criteria and is signed off by the project manager; a verified deliverable meets acceptance criteria and is signed off by the customer or sponsor.

Question # 144

What communication methods would a project manager use for overall effective project communication?

A.

Interactive communication, push communication, interpersonal communication

B.

Interactive communication, push communication, pull communication

C.

Push communication, pull communication, interpersonal communication

D.

Pull communication, interactive communication, interpersonal communication

Question # 145

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

Question # 146

Which is an example of analogous estimating?

A.

Estimates are created by individuals or groups with specialized knowledge.

B.

Estimates are created by using information about resources of previous similar projects.

C.

Estimates are created by analyzing data.

D.

Estimates are created at the task level and aggregated upwards.

Question # 147

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

A.

Continuous improvement.

B.

Predictive planning.

C.

Progressive elaboration.

D.

Quality assurance.

Question # 148

The process of prioritizing risks for further analysis or action is known as:

A.

Plan Risk Management.

B.

Plan Risk Responses.

C.

Perform Qualitative Risk Analysis.

D.

Perform Quantitative Risk Analysis.

Question # 149

What process is included in Project Schedule Management?

A.

Estimate Activity Durations

B.

Create Work Breakdown Structure (WBS)

C.

Direct and Manage Project Work

D.

Estimate Activity Resources

Question # 150

Which type of organizational structure is displayed in the diagram provided?

A.

Balanced matrix

B.

Projectized

C.

Strong matrix

D.

Functional

Go to page: