Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)

Last Update 16 hours ago Total Questions : 1320

The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 16 hours ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.

Question # 351

As the project progresses, which of the following is routinely collected from the project activities?

A.

Communication management activities

B.

Change requests

C.

Configuration verification and audit

D.

Work performance information

Question # 352

A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence.

What should the project manager do first?

A.

Extend an iteration review invite to the new stakeholder.

B.

Perform qualitative risk analysis.

C.

Engage with the new stakeholder.

D.

Allow team members to share project status reports.

Question # 353

What tern describes an intentional activity to modify a nonconforming product or product component?

A.

Preventive action

B.

Corrective action

C.

Defect repair

D.

Updates

Question # 354

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

A.

Control Scope

B.

Collect Requirements

C.

Create WBS

D.

Define Scope

Question # 355

A project manager should consider the impact of project..............manager following

A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?

A.

Project Cost Management

B.

Project Integration Management

C.

Project Resources Management

D.

Project Scope Management

Question # 356

During project execution, a key resource leaves the team for another job. What should the project manager do in this situation?

A.

Submit a change request for additional budget to secure a project resource.

B.

Consult with the functional manager for a replacement resource.

C.

Distribute work to other team members to reduce impact to the project schedule.

D.

Consult the risk register for an appropriate risk response.

Question # 357

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

A.

Add the milestones to the risk register, as time is short.

B.

Add the two milestones to the project plan, as they are mandatory.

C.

Calculate the duration of the two milestones stated in the contract.

D.

Start the project as soon as possible, as time is short.

Question # 358

Which of the following is an output of Define Scope?

A.

Project scope statement

B.

Project charter

C.

Project plan

D.

Project schedule

Question # 359

Which of the following reduces the probability of potential consequences of project risk events?

A.

Preventive action

B.

Risk management

C.

Corrective action

D.

Defect repair

Question # 360

The milestone list is an input to which process from the Planning Process Group?

A.

Define Activities

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Question # 361

Tools and techniques used for Plan Communications include the communication:

A.

requirements analysis, communication technology, communication models, and communication methods.

B.

methods, stakeholder register, communication technology, and communication models.

C.

requirements, communication technology, communication requirements analysis, and communication methods.

D.

management plan, communication technology, communication models, and communication requirements analysis.

Question # 362

When should quality planning be performed?

A.

While developing the project charter

B.

In parallel with the other planning processes

C.

As part of a detailed risk analysis

D.

As a separate step from the other planning processes

Question # 363

Two resources are performing a peer review of an artifact. What should be the outcome of the peer review?

A.

All business rules and data requirements for each process are documented.

B.

All relevant business rules for each process are documented.

C.

The resulting documentation adheres to established organizational standards.

D.

The data requirements for each process are documented.

Question # 364

A new business analyst has joined the team in the middle of a project and the requirements traceability matrix has been updated. What should the business analyst do next?

A.

Review the project management plan.

B.

Share the requirements traceability matrix the same way it was shared previously.

C.

Consult the business analysis communications management plan.

D.

Ask the project manager to share the updated requirements traceability matrix at the next meeting.

Question # 365

Which tool or technique is used in the Perform Integrated Change Control process?

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Question # 366

A project team is closing out a phase and updating the organizational knowledge base What organizational process asset (OPA) will the team update?

A.

Traceability matrixB Lessons learned

B.

Change control proceduresD Resource availability

Question # 367

A new game development process must have three versions. Each version is to be developed in approximately five iteration cycles with a duration of one month each. This will help this small enterprise to have a return on investment (ROI) as the project runs from the first cycle. Which methodology should the project manager adopt and implement in the project?

A.

Feature-driven development (FDD) as it will deliver product segments and the milestones are controlled by the development manager.

B.

Kanban as it will provide flexibility to the team for working at their own pace in the time frame requested.

C.

Scrum as it uses sprints and retrospectives, maximizing time delivery and the value of the product.

D.

Extreme Programming (XP) as it will help deliver more quickly since developers will work in pairs.

Question # 368

What is an objective of the Develop Project Team process?

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers becoming more involved

Question # 369

Which process is engaged when a proiect learn inember makes a change to project budget with the project manager ' s approval?

A.

Manage Cost Plan

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Question # 370

What do top project managers do to maximize their sphere of influence within a project team?

A.

Consider management standards, economic factors, and sustainability strategies

B.

Contribute knowledge and expertise to others within the profession

C.

C Address political and strategic issues that impact the project ' s viability or quality

D.

D Demonstrate superior relationship and communication skills while displaying a positive attitude

Question # 371

An input of the Create WBS process is:

A.

requirements documentation.

B.

scope baseline.

C.

project charter.

D.

validated deliverables.

Question # 372

A program consists of four agile teams. Each team has a separate daily standup. Later each day, there is another standup meeting attended by one member from each team.

Which Scrum technique is this?

A.

Scaled Agile Framework (SAFe®)

B.

Disciplined Agile® (DA™)

C.

Large Scale Scrum (LeSS)

D.

Scrum of Scrums

Question # 373

During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three)

A.

End user

B.

Product owner

C.

Subject matter experts (SMEs)

D.

Project sponsor

E.

Project team

Question # 374

At the start of a typical project life cycle, costs are:

A.

low, peak as work is carried out, and drop as the project nears the end.

B.

low, become steady as work is carried out, and increase as the project nears the end.

C.

high, drop as work is carried out, and increase as the project nears the end.

D.

high, become low as work is carried out, and drop as the project nears the end.

Question # 375

Which document in the project management plan can be updated in the Plan Procurement Management process?

A.

Budget estimates

B.

Risk matrix

C.

Requirements documentation

D.

Procurement documents

Question # 376

What conflict resolution technique involves delaying the issue or letting others resolve it?

A.

Smooth/accommodate

B.

Collaborate/problem solve

C.

Withdraw/avoid

D.

Force/direct

Question # 377

The project management processes presented in the PMBOK Guide® should:

A.

always be applied uniformly.

B.

be selected as appropriate by the sponsor.

C.

be selected as appropriate by the project team.

D.

be applied based on ISO guidelines.

Question # 378

Quality metrics are an output of which process?

A.

Plan Quality

B.

Perform Quality Control

C.

Perform Quality Assurance

D.

Perform Qualitative Risk Analysis

Question # 379

Which defines the portion of work included in a contract for items being purchased or acquired?

A.

Procurement management plan

B.

Evaluation criteria

C.

Work breakdown structure

D.

Procurement statement of work

Question # 380

The project manager is creating the communications management plan Which group of inputs Is required to begin?

A.

Work performance reports, change requests, and risk register

B.

Work performance data, project documents, and stakeholder engagement plan

C.

Project charter, project management plan, and project documents

D.

Work performance data, stakeholder register, and team management plan

Question # 381

Which of the following is used as input to prepare a cost management plan?

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Question # 382

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Question # 383

A project team is evaluating criteria to determine project viability. Which of these activities will provide insight into making a go/no-go decision to start the project?

A.

Cost of quality (COQ)

B.

Lessons learned

C.

Cost-benefit analysis

D.

Benchmarking

Question # 384

Which of the following involves making information available to project stakeholders in a timely manner?

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Question # 385

Why is a project undertaken?

A.

To create a unique product, service, or result

B.

To teach the discipline of program and portfolio management

C.

To increase the understanding of project management

D.

To achieve better management of resources

Question # 386

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

A.

Salience

B.

Influence/impact

C.

Power/interest

D.

Power/influence

Question # 387

Which of the following is an input to the Perform Qualitative Risk Analysis process?

A.

Risk register

B.

Risk data quality assessment

C.

Risk categorization

D.

Risk urgency

Question # 388

Inputs to the Plan Schedule Management process include:

A.

Organizational process assets and the project charter,

B.

Enterprise environmental factors and schedule tools.

C.

Time tables and Pareto diagrams.

D.

Activity attributes and resource calendars.

Question # 389

A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?

A.

The project manager should identify and deal with stakeholders only during the execution phase.

B.

Stakeholder satisfaction should be identified immediately and managed as a project objective.

C.

The project manager should focus on project objectives and deal with stakeholders as a secondary priority.

D.

Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.

Question # 390

An input to the Plan Cost Management process is:

A.

Cost estimates.

B.

Resource calendars,

C.

The project charter,

D.

The risk register.

Question # 391

One of the tools and techniques of the Manage Project Team process is:

A.

organization charts.

B.

ground rules.

C.

organizational theory,

D.

conflict management.

Question # 392

A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

A.

create the project management plan.

B.

identify the project objectives.

C.

review and update stakeholder engagement.

D.

create the schedule baseline.

Question # 393

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

A.

Complete project phase

B.

Project life

C.

The project life cycle

D.

Project cycle

Question # 394

Which contract type is least desirable to a vendor?

A.

Fixed price with economic price adjustment (FPEPA)

B.

Firm fixed price (FFP)

C.

Cost plus fixed fee (CPFF >

D.

Cost plus award fee (CPAF >

Question # 395

What is the purpose of the project schedule management.

A.

Estimates specific time and the deadline when the products, services and results will be delivered.

B.

Determines in details the resources and time that each task will require to be done

C.

Represents how and when the project will deliver the results defined in the project scope.

D.

It provides the relationships among the project activities and their risks.

Question # 396

An adaptive project manager is told that a new industry regulation will affect an upcoming deliverable. Where should this be recorded?

A.

Risk register

B.

Sprint board

C.

Sprint planning

D.

User story

Go to page: