Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)

Last Update 20 hours ago Total Questions : 1337

The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 20 hours ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.

Question # 251

What tern describes an intentional activity to modify a nonconforming product or product component?

A.

Preventive action

B.

Corrective action

C.

Defect repair

D.

Updates

Question # 252

In Project Cost Management, which input is exclusive to the Determine Budget process?

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Question # 253

Which tools and techniques should a project manager use to monitor risks?

A.

Expert judgment, data analysis, and interpersonal and real skills

B.

Data analysis, audits, and decision making

C.

Expert judgement, audits, and decision making

D.

Meetings, data gathering, and expert judgment

Question # 254

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

A.

What-if scenario analysis

B.

Simulation

C.

Alternatives analysis

D.

Reserve analysis

Question # 255

What are the objectives of Initiation processes?

A.

Initiation processes are performed in order to develop the project charier and Identify stakeholders.

B.

Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.

C.

Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders ' goals.

D.

Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.

Question # 256

In project management, a temporary project can be:

A.

Completed without planning

B.

A routine business process

C.

Long in duration

D.

Ongoing to produce goods

Question # 257

Which item is an example of personnel assessment?

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Question # 258

What three strategies are used to respond to threats?

A.

Escalate, accept, and mitigate

B.

Accept share, and avoid

C.

Escalate, transfer, and exploit

D.

Mitigate, accept, and prioritize

Question # 259

The precedence diagramming method (PDM) is also known as:

A.

Arrow Diagram.

B.

Critical Path Methodology (CPM).

C.

Activity-On-Node (AON).

D.

schedule network diagram.

Question # 260

As the project progresses, which of the following is routinely collected from the project activities?

A.

Communication management activities

B.

Change requests

C.

Configuration verification and audit

D.

Work performance information

Question # 261

The progressive detailing of the project management plan is called:

A.

expert judgment.

B.

rolling wave planning.

C.

work performance information.

D.

specification.

Question # 262

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.

Which type of life cycle would the project manager use in this case?

A.

Predictive life cycle

B.

Waterfall life cycle

C.

Hybrid life cycle

D.

Product life cycle

Question # 263

What is the common factor among portfolios, programs, and projects, regardless of the hierarchy within an organization?

A.

Resources and stakeholders

B.

Operations and performance

C.

Subsidiary projects

D.

Project manager

Question # 264

When establishing a contingency reserve, including time, money and resources, how is the risk being handled?

A.

Accepting

B.

Transferring

C.

Avoiding

D.

Mitigating

Question # 265

Which of the following investigates the likelihood that each specific risk will occur?

A.

Risk register

B.

Risk audits

C.

Risk urgency assessment

D.

Risk probability and impact assessment

Question # 266

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

A.

adaptive

B.

reflexive

C.

predictive

D.

iterative

Question # 267

Which is the correct hierarchy in a project environment, from most to least Inclusive?

A.

Projects, portfolios, then programs

B.

Portfolios, programs, then projects

C.

Portfolios, projects, then programs

D.

Projects, programs, then portfolios

Question # 268

Which statement summarizes the role of the change control board?

A.

The change control board is responsible for presenting the change for approval.

B.

The change control board will analyze the change impact in terms of cost and schedule.

C.

The change control board is responsible for managing the change management and configuration management systems.

D.

The change control board is responsible for reviewing and approving changes to the project.

Question # 269

At the start of a typical project life cycle, costs are:

A.

low, peak as work is carried out, and drop as the project nears the end.

B.

low, become steady as work is carried out, and increase as the project nears the end.

C.

high, drop as work is carried out, and increase as the project nears the end.

D.

high, become low as work is carried out, and drop as the project nears the end.

Question # 270

What tool or technique is primarily used to plan risk responses ' ?

A.

Risk categorization

B.

Project risk document updates

C.

Strategies for overall project risk

D.

Risk management plan

Question # 271

Progressively elaborating high-level information into detailed plans is performed by the:

A.

project management office

B.

portfolio manager

C.

program manager

D.

project manager

Question # 272

Which characteristic defines the Delphi technique of group decision-making?

A.

The participants must use their expertise to determine the best option.

B.

The decision is based on eliminating the options that are too expensive.

C.

The decision is based on a predefined algorithm and the highest score.

D.

The participants must create a list of options, rank them, and then vote.

Question # 273

How many Project Management Process Groups are there?

A.

3

B.

4

C.

5

D.

6

Question # 274

An input to Close Project or Phase is:

A.

Accepted deliverables,

B.

Final products or services,

C.

Document updates,

D.

Work performance information.

Question # 275

Typical outcomes of a project include:

A.

Products, services, and improvements.

B.

Products, programs, and services.

C.

Improvements, portfolios, and services.

D.

Improvements, processes, and products.

Question # 276

A construction project is underway with three months left to complete the building. A public authority responsible for approving the final stage is stalling the project. What should the project manager do?

A.

Discuss this with the department head and arrive at an acceptable solution to expedite the approval process.

B.

Report the issue to major stakeholders and explore possible corrective actions along with legal assistance.

C.

Mitigate the risk by requesting an alternative public authority to participate in the approval process.

D.

Visit the public authority headquarters and formally petition them, demanding an explanation about the delay.

Question # 277

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Question # 278

Which set of activities should a project manager use as part of the Develop Team process?

A.

Training and establishing ground rules

B.

Networking activities and estimating team resources

C.

Conflict management activities and tracking team performance

D.

Recruit new team members and training

Question # 279

A project team for a marketing company is acquiring leaflets and materials from competitors. The team is working on a project to release new products, and they are trying to get ideas on how to most efficiently market these new products.

Which activity is the project team conducting?

A.

Project execution

B.

Benchmarking

C.

Brainstorming

D.

Project initiation

Question # 280

Following a project planning meeting with the team, a few team members approach the project manager to follow up on actions required. How can the project manager assess the effectiveness of the meeting?

A.

Send the meeting minutes to all team members to verify that the required information is readily available.

B.

Ask the team members to provide feedback for meetings in the phase retrospective.

C.

Review the actions from the meeting with each of the project team members to ensure their understanding.

D.

Consult the communications management plan to determine the success criteria for meetings.

Question # 281

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Question # 282

A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

A.

Push communication

B.

Pull communication

C.

Interactive communication

D.

Stakeholder communication

Question # 283

After missing a weekly communication meeting hosted by the project manager, a stakeholder looks at the latest report in the common repository.

What is the communication type used in this scenario?

A.

Pull

B.

Verbal

C.

Written

D.

Push

Question # 284

Which process determines the risks that may affect the project and documents their characteristics?

A.

Control Risks

B.

Plan Risk Management

C.

Plan Risk Responses

D.

Identify Risks

Question # 285

The number of potential communication channels for a project with 5 stakeholders is:

A.

10.

B.

12.

C.

20.

D.

24.

Question # 286

During a project ' s execution phase, the project manager reviews the communications management plan for communication technology factors. What can affect the choice of communications?

A.

Legal requirements

B.

Politics and power structures

C.

Internal information needs

D.

Sensitivity and confidentiality of the information

Question # 287

The project manager is working in the Resource Management process. Which items may the project manager need to include in the team charter?

A.

Cultural norms, roles and responsibilities, and organizational chart

B.

Assumption logs, resource calendars and training schedule

C.

Communication guidelines, conflict resolution process, and team agreements

D.

Company policies, recognition plan, and roles and responsibilities

Question # 288

Completion of the product scope is measured against the product:

A.

prototypes

B.

requirements

C.

analyses

D.

benchmarks

Question # 289

An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float.

What is the likelihood the team will complete all 20 story points in the upcoming sprint?

A.

50-75%

B.

25-50%

C.

75-100%

D.

0-25%

Question # 290

In which type of organizational structure are staff members grouped by specialty?

A.

Functional

B.

Projectized

C.

Matrix

D.

Balanced

Question # 291

Which of the following Project Communication Management processes uses performance reports as an input?

A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

Question # 292

Perform Quality Control is accomplished by:

A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Question # 293

A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

A.

Bottom-up estimating

B.

Three-point estimating

C.

Analogous estimating

D.

Parametric estimating

Question # 294

Which of these is true of project integration management?

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

Question # 295

A team has been tasked with designing a product to address a problem they have never faced before. The project team is struggling to get traction as the solutions are not clear. What should the project manager do next?

A.

Add the risk to the project risk register, as the lack of solutions could impact how the product is built.

B.

Add the issue to the project issue log, as it will impact the project performance.

C.

Facilitate a brainstorming session for the team to discuss ideas to solve the problem.

D.

Meet with the project sponsor to understand their vision on how to address the problem.

Question # 296

A project team is reviewing project performance. During the execution phase, the project team discovers that there is an off-the-shelf (OTS) product, which could reduce the timeline for development.

What should the project manager do next?

A.

Update the project management plan.

B.

Add the discovery to the assumptions.

C.

Evaluate the risk with the project team.

D.

Conduct an opportunity analysis with the team.

Question # 297

Project management processes ensure the:

A.

alignment with organizational strategy

B.

efficient means to achieve the project objectives

C.

performance of the project team

D.

effective flow of the project throughout its life cycle

Question # 298

Which of the following are outputs of Develop Project Team?

A.

Human resources plan changes and project staff assignment updates

B.

Project management plan updates and enterprise environmental factor updates

C.

Resource calendars and project management plan updates

D.

Team performance assessments and enterprise environmental factor updates

Question # 299

A project management office manages a number of aspects including the:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Question # 300

Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project ' s:

A.

Level of control.

B.

Communication channels.

C.

Scope.

D.

Strategic alignment.

Go to page: