Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)

Last Update 16 hours ago Total Questions : 1320

The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 16 hours ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.

Question # 251

What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?

A.

Project Management

B.

Program Management

C.

Portfolio Management

D.

Operations Management

Question # 252

Why is required in a project?

A.

Because a one-size-fits-all approach avoids complications and saves time.

B.

Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required.

C.

Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project.

D.

Project managers should apply every process in the PMBOK Guide to the project, so failoring is not requires.

Question # 253

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Question # 254

Which of the following items is a technique for data gathering?

A.

Facilitation

B.

Meeting management

C.

Conflict management

D.

Interviews

Question # 255

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

A.

Push

B.

Pull

C.

Interactive

D.

Iterative

Question # 256

Which of the following set of elements is part of an effective communications management plan?

A.

Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information

B.

Phone book directory, stakeholder communication requirements, project charter, glossary of common terminology

C.

Organizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology

D.

Glossary of common terminology, constraints denved from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan

Question # 257

The review of a seller ' s progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

A.

Work performance information.

B.

Inspections and audits.

C.

Payment systems.

D.

Procurement performance reviews.

Question # 258

Which behavior is a management trait?

A.

Asking what and why

B.

Challenging the status quo

C.

Innovating

D.

Relying on control

Question # 259

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three)

A.

High-level deliverables

B.

Phase transitions

C.

Project objectives

D.

Success criteria

E.

Cost

Question # 260

Which project risk listed in the table below is most likely to occur?

A.

1

B.

2

C.

3

D.

4

Question # 261

A project team is meeting to seek solutions on a new problem that occurred recently. The meeting is comprised of two parts: the first is a generation of ideas and the second is an analysis.

Which technique is the team using?

A.

Checklists

B.

Interview

C.

Focus group

D.

Brainstorming

Question # 262

The Perform Quality Assurance process occurs in which Process Group?

A.

Executing

B.

Monitoring and Controlling

C.

Initiating

D.

Planning

Question # 263

Which action should the project manager take after the team finishes executing the scope?

A.

Verify the deliverables to ensure that they are correct and meet the customer ' s satisfaction.

B.

Accept all the deliverables and deliver them to the customer for final acceptance.

C.

Conduct a joint session with the customer, change the deliverables, and then request approval.

D.

Check that all change requests were implemented and release deliverables to the customer.

Question # 264

In which Knowledge Area is the project charter developed?

A.

Project Cost Management

B.

Project Scope Management

C.

Project Time Management

D.

Project Integration Management

Question # 265

What is a tailoring consideration for Project Scope Management ' ?

A.

Life cycle approach

B.

Continuous improvement

C.

Validation and control

D.

Project complexity

Question # 266

A business analyst is evaluating solutions against the expected results and logging defects along the way. The next task is to analyze the discrepancies prior to facilitating a go/no-go decision.

Which technique should be used as a starting point to uncover problem areas?

A.

Elicitation

B.

Opportunity analysis

C.

Cost-benefit analysis

D.

Feasibility analysis

Question # 267

Monte Carlo is which type of risk analysis technique?

A.

Probability

B.

Quantitative

C.

Qualitative

D.

Sensitivity

Question # 268

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Question # 269

The probability and impact matrix is primarily used to:

A.

Quantify risk issues for trends during a quality audit.

B.

Develop a risk register for risk planning.

C.

Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.

D.

Define risk and compare impacts during Perform Quantitative Risk Analysis.

Question # 270

Which input to the Plan Risk Management process provides information on high-level risks?

A.

Project charter

B.

Enterprise environmental factors

C.

Stakeholder register

D.

Organizational process assets

Question # 271

The process of identifying and documenting relationships among the project activities is known as:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

Question # 272

The number of potential communication channels for a project with 5 stakeholders is:

A.

10.

B.

12.

C.

20.

D.

24.

Question # 273

Stakeholder satisfaction should be managed as a key project:

A.

Benefit

B.

Initiative

C.

Objective

D.

Process

Question # 274

Which tool or technique is effective in a project in which the deliverable is not a service or result?

A.

Inspection

B.

Variance analysis

C.

Decomposition

D.

Product analysis

Question # 275

Under which circumstances should multiple projects be grouped in a program?

A.

When they are needed to accomplish a set of goals and objectives for an organization

B.

When they have the same project manager and the same organizational unit

C.

When they have the same scope, budget, and schedule

D.

When they are from the same unit of the organization

Question # 276

Why is tailoring required in a project?

A.

Because a one-size-fits-all approach avoids complications and saves time.

B.

Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required.

C.

Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project.

D.

Project managers should apply every process in the PMBOK Guide to the project, so tailoring is not required.

Question # 277

Which of the following is an example of an organizational system that is arranged based on the job being performed?

A.

Simple

B.

Multi-divisional

C.

Functional

D.

Project-oriented

Question # 278

Which of the following lists of tools and techniques is used when conducting procurements?

A.

Expert judgement, procurement negotiations, bidder conferences, proposal evaluation advertising and independent estimates

B.

Budgeting procurement negotiations, bidder conferences, proposal evaluation and advertising, and seller ' s proposal C. Expert judgement, procurement negotiations bidder conferences, proposal evaluation and advertising, and make-or-buy decisions

C.

Agreements procurement negotiations, bidder conferences, proposal evaluation and advertising selected seller

Question # 279

Which of the following can a project manager use to represent dellned team member roles in a group of tasks?

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Organizational breakdown structure (OBS)

D.

Resource breakdown structure (RBS)

Question # 280

Which tools and techniques will a project manager use to develop a project charter?

A.

Project manager experience, expert judgment, scope statement, and meetings

B.

Lessons learned database. Interpersonal and team skills, cost baseline, and meetings

C.

Expert judgment, data gathering. scope statement, schedule baseline, and meetings

D.

Expert judgment, data gathering. interpersonal and team skills, and meetings

Question # 281

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

A.

Cost Plus Award Fee Contract (CPAF)

B.

Firm-Fixed -Price Contract (FFP)

C.

Time and Material Contract (TandM)

D.

Cost Plus Incentive Fee Contract (CPIF)

Question # 282

Projects are undertaken by an organization to support the:

A.

Product performance.

B.

Budget process.

C.

Collective capabilities.

D.

Organizational strategy.

Question # 283

Information collected on the status of project activities being performed to accomplish the project work is known as what?

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Question # 284

A procurement management plan is a subsidiary of which other type of plan?

A.

Resource plan

B.

Project management plan

C.

Cost control plan

D.

Expected monetary value plan

Question # 285

How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?

A.

Less time spent on defining scope early on

B.

More time spent on defining scope early on

C.

Less time spent on scope management process

D.

Project scope management is the same in all projects

Question # 286

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

A.

Three weeks

B.

Four weeks

C.

Five weeks

D.

Six weeks

Question # 287

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

A.

Work performance reports

B.

Assumptions logs

C.

Network diagrams

D.

Academic studies

Question # 288

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

A.

Strong

B.

Weak

C.

Managed

D.

Balanced

Question # 289

Which tool or technique is used in validating the scope of a project?

A.

Facilitated workshops

B.

Interviews

C.

Inspection

D.

Meetings

Question # 290

Which type of dependency is contractually required or inherent in the nature of the work?

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Question # 291

How can a project manager represent a contingency reserve in the schedule?

A.

Additional weeks of work to account for unknown-unknowns risks

B.

Task duration estimates of the best case scenarios

C.

Addition Duration estimates in response to identified risks that have been accepted

D.

Milestones representing the completion of deliverables

Question # 292

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

A.

Discuss the processes and deliverables needed to meet the project objectives with the team.

B.

Integrate hybrid approach processes and deliverables to meet the short delivery time line.

C.

Identify the processes and deliverables for only the current phase first.

D.

Follow organizational methodology and produce all required deliverables.

Question # 293

A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?

A.

Project plan

B.

Business case

C.

Budget requirement

D.

Project charter

Question # 294

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

A.

Enhance

B.

Share

C.

Exploit

D.

Accept

Question # 295

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

A.

Approved change requests

B.

Verified deliverables

C.

Lessons learned

D.

Work performance data

Question # 296

A required input for Create WBS is a project:

A.

quality plan.

B.

schedule network.

C.

management document update.

D.

scope statement.

Question # 297

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Question # 298

The project manager and the project team are in the process of documenting procurement decisions. Which of the following will be the procurement strategy?

A.

Payment types, delivery methods, and procurement phases

B.

Procurement metrics, make-or-buy decisions, and procurement statement of work

C.

Vendor selection criteria, stakeholder roles and responsibilitys, and prequalified sellers

D.

Timetable procurement activities, product cost, and knowledge transfer schedule

Question # 299

The Define Scope process is in which of the following Process Groups?

A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

Question # 300

Which input will be used when tasked with developing the human resource plan?

A.

Project management plan

B.

Activity resource requirements

C.

Resource calendar

D.

Project staff assignments

Go to page: