Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)

Last Update 16 hours ago Total Questions : 1320

The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 16 hours ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.

Question # 301

If a project manager effectively manages project knowledge, a key benefits is that:

A.

all stakeholders have access to the same information.

B.

the project team is able to understand the project status.

C.

project stakeholders have a clear picture of the project.

D.

new knowledge is added to organizational process assets.

Question # 302

Most experienced project managers know that:

A.

every project requires the use of all processes in the PMBOK® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

Question # 303

With regard to a project manager ' s sphere of influence in a project, which of the following does the project manager influence most directly?

A.

Suppliers

B.

Customers

C.

Governing bodies

D.

Project team

Question # 304

Which actions should a project manager follow to manage stakeholders?

A.

Identify the key stakeholders and keep them informed at all times.

B.

Identify the stakeholders, planning, managing and monitoring their engagement

C.

Meet and keep informed any person related to the project, at all times

D.

Identify the stakeholders and monitor their level of satisfaction

Question # 305

Which of the following is an output of the Define Activities process?

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

Question # 306

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Question # 307

Which of the following events would result in a baseline update?

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Question # 308

In an interactive communication model, how is the sender ensured that the message was understood by the receiver?

A.

The receiver decodes the message

B.

The receiver responds to the message with feedback.

C.

The receiver transmits the message

D.

The receiver acknowledges their receipt of the message

Question # 309

What is the first step in the Stakeholder Management process?

A.

Plan Stakeholder Engagement

B.

Identify Stakeholders

C.

Manage Stakeholder Responsibility

D.

Monitor Stakeholder Activity

Question # 310

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

A.

Sensitivity analysis

B.

Three-point estimate

C.

Modeling and simulation

D.

Expected monetary value analysis

Question # 311

Plan-do-check-act is also known as:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

Question # 312

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

A.

Determine Budget.

B.

Baseline Budget.

C.

Control Costs.

D.

Estimate Costs.

Question # 313

Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?

A.

Power interest grid

B.

Stakeholder cube

C.

Salience model

D.

Directions of influence

Question # 314

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

A.

Earned value management.

B.

Enterprise environmental factors.

C.

Organizational process assets.

D.

Work performance information.

Question # 315

Howls program success measured?

A.

By delivering the benefit of managing the program ' s projects in a coordinated manner

B.

By the quality, timeliness, cost-etfectiveness. and customer saDstaction of the product or service

C.

By completing the right projects to achieve objectives rather than completing projects the right way

D.

By aggregating the successes of the individual projects in the program

Question # 316

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

A.

Direct

B.

Interactive

C.

Pull

D.

Push

Question # 317

What process is performed periodically throughout the project as needed?

A.

Plan Risk Management

B.

Plan Communications Management

C.

Plan Resource Management

D.

Plan Cost Management

Question # 318

Which process uses expert judgment to manage project resources?

A.

Plan Resource Management

B.

Estimate Activity Resources

C.

Manage Team

D.

Both A and B

Question # 319

Which is an example of Administer Procurements?

A.

Negotiating the contract

B.

Authorizing contractor work

C.

Developing the statement of work

D.

Establishing evaluation criteria

Question # 320

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

A.

Plan Cost Management

B.

Plan Scope Management

C.

Plan Stakeholder Management

D.

Plan Schedule Management

Question # 321

Project reporting is a tool that is most closely associated with which process?

A.

Communicate Plan

B.

Manage Communications

C.

Report Performance

D.

Control Communications

Question # 322

What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

A.

Failure modes and effects analysis

B.

Design of experiments

C.

Quality checklist

D.

Risk analysis

Question # 323

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

A.

Project Integration Management

B.

Project Communications Management

C.

Project Information Management System (PIMS)

D.

Project Scope Management

Question # 324

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

A.

Business case

B.

Work breakdown structure

C.

Requirements documentation

D.

Risk register

Question # 325

The Perform Integrated Change Control process occurs in which Process Group?

A.

Initiating

B.

Executing

C.

Monitoring and Controlling

D.

Planning

Question # 326

A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?

A.

Informal

B.

Unofficial

C.

Formal

D.

Hierarchical

Question # 327

A project team identifies defects that will require a modification to a tool ' s functionality. What process should the project manager follow to obtain stakeholder buy-in?

A.

Control Schedule

B.

Perform Qualitative Risk Analysis

C.

Perform Integrated Change Control

D.

Control Scope

Question # 328

Another name for an Ishikawa diagram is:

A.

cause and effect diagram.

B.

control chart.

C.

flowchart.

D.

histogram.

Question # 329

A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure an effective requirements elicitation.

What should the business analyst do?

A.

Organize a workshop with the sponsor and major stakeholders.

B.

Engage a consultant that is familiar with the community needs.

C.

Ask the project coordinator to facilitate some of the workshops.

D.

Invite both internal and external stakeholders to the workshops.

Question # 330

The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

A.

1.33

B.

2

C.

0.75

D.

0.5

Question # 331

In which process might a project manager use risk reassessment as a tool and technique?

A.

Perform Qualitative Risk Analysis

B.

Monitor and Control Risk

C.

Monitor and Control Project Work

D.

Plan Risk Responses

Question # 332

What does the creation of a project management plan accomplish?

A.

Defines the basis of all project work and how it will be performed

B.

Acknowledges the existence of a project and defines its high-level information

C.

Authorizes the project manager to apply organizational resources to project activities

D.

Provides the project manager with organizational standards, policies, processes, and procedures

Question # 333

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost

A.

High-level deliverables

B.

Success criteria

C.

Project objectives

D.

Phase transitions

Question # 334

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

A.

Three-point

B.

Bottom-up

C.

Parametric

D.

Analogous

Question # 335

A tool or technique in Perform Quality Control that a project manager would use is:

A.

quality audits.

B.

process analysis.

C.

benchmarking.

D.

inspection.

Question # 336

Which of the following best correspond to the organizational process assets (OPAs) that affect the project?

A.

Policies and lessons learned from other projects

B.

Information technology software and employee capability

C.

Resource availability and employee capability

D.

Marketplace conditions and legal restrictions

Question # 337

Which of the following is an example of facit knowledge?

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Question # 338

Which process should be conducted from the project inception through completion?

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Question # 339

In complex projects/ initiating processes should be completed:

A.

Within a work package.

B.

In each phase of the project.

C.

To estimate schedule constraints.

D.

To estimate resource allocations.

Question # 340

A business analyst is working on a project that follows an adaptive life cycle. Due to budgetary constraints, the sponsor asks the team to focus on critical requirements. What should the business analyst do?

A.

Prioritize requirements.

B.

Document requirements.

C.

Trace requirements.

D.

Validate requirements.

Question # 341

A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and product acceptance criteria. Which activity is being performed?

A.

Inspection

B.

Prototyping

C.

Decision making

D.

Brainstorming

Question # 342

Plan Risk Management is the process of defining how to:

A.

Communicate identified risks to the project stakeholders.

B.

Conduct risk management activities for a project.

C.

Analyze the impact a specific risk may have on the project.

D.

Address unexpected risks that may occur during a project.

Question # 343

Which items are an output of the Perform Integrated Change Control process?

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Question # 344

What is the name of a graphic display of project team members and their reporting relationships?

A.

Role dependencies chart

B.

Reporting flow diagram

C.

Project organization chart

D.

Project team structure diagram

Question # 345

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

A.

Eleven weeks

B.

Nine weeks

C.

Eight weeks

D.

Ten weeks

Question # 346

An output of the Create WBS process is:

A.

Scope baseline.

B.

Project scope statement.

C.

Organizational process assets.

D.

Requirements traceability matrix.

Question # 347

In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

A.

Predictive

B.

Adaptive

C.

A mix

D.

Agile

Question # 348

Tailoring considerations for project scope management may include:

A.

requirements management, stability of requirements, development approach, and validation and control.

B.

WBS guidelines, requirements templates, deliverable acceptance forms, and verified deliverables.

C.

business needs, product descriptions, project restrictions, and project management plan.

D.

issues defining and controlling what is included in the project, vended deliverables, and quality reports.

Question # 349

A project manager held a meeting and listed all team members ' ideas for improving the product on a white board. What data gathering technique did the project manager apply?

A.

Focus groups

B.

Interviews

C.

Brainstorming

D.

Delphi technique

Question # 350

The project scope statement and resource calendars are inputs to which Project Time Management process?

A.

Sequence Activities

B.

Estimate Activity Resources

C.

Develop Schedule

D.

Control Schedule

Go to page: