Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Associate in Project Management (CAPM)

Last Update 20 hours ago Total Questions : 1337

The Certified Associate in Project Management (CAPM) content is now fully updated, with all current exam questions added 20 hours ago. Deciding to include CAPM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CAPM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CAPM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) practice test comfortably within the allotted time.

Question # 301

What is the purpose of an adaptive standup meeting?

A.

To review what work has been completed, remove impediments, and calculate velocity

B.

To ask the team what work has been completed, calculate velocity, and determine what work will be completed

C.

To ask the team what work has been completed, ask what work will be completed, and report impediments

D.

To update the burndown chart, calculate velocity, and report impediments

Question # 302

A project team is meeting to seek solutions on a new problem that occurred recently. The meeting is comprised of two parts: the first is a generation of ideas and the second is an analysis.

Which technique is the team using?

A.

Checklists

B.

Interview

C.

Focus group

D.

Brainstorming

Question # 303

Which statement describes the Monitor Communications process?

A.

Evaluates the differences between the communications management plan and the reality of communications in a project

B.

Ensures that the information needs of the project and the stakeholders are met

C.

Ensures that project information is created, collected, and distributed in a timely and appropriate manner

D.

Develops an appropriate approach and plan for communication of project activities

Question # 304

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

A.

Crashing

B.

Fast tracking

C.

Leads and lags adjustment

D.

Parallel task development

Question # 305

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Question # 306

Recently, the government published a new tax law giving companies one year to implement the changes. A project was initiated to change the accounting system. Which delivery approach is most suitable in this context?

A.

Predictive, because of the high risk that the company can be fined.

B.

Predictive, because the requirements are clearly defined up-front.

C.

Adaptive, because the government will provide constant feedback.

D.

Adaptive, because the changes have never been implemented before.

Question # 307

A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client ' s project manager. The technical lead is requesting two new developers.

Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?

A.

Cost management plan

B.

Business management plan

C.

Stakeholder engagement plan

D.

Resource management plan

Question # 308

Which project risk listed in the table below is most likely to occur?

A.

1

B.

2

C.

3

D.

4

Question # 309

A project manager is working on the communications management plan. Which of these documents are inputs to consider?

A.

Stakeholder engagement plan and organizational process assets

B.

Project schedule and stakeholder register

C.

Quality management plan and risk register

D.

Basis of estimates and scope baseline

Question # 310

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

A.

Stakeholder register

B.

Scope management plan

C.

Stakeholder management plan

D.

Project charter

Question # 311

A project manager called for a team meeting...................method did the team use

A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?

A.

Rolling wave planning

B.

Expert Judgement

C.

Decomposition

D.

Data analysis

Question # 312

Which of the following is a category of organizational process assets?

A.

Government standards

B.

Organizational culture

C.

Employee capabilities

D.

Organizational knowledge bases

Question # 313

Recognition and rewards are tools and techniques of which process?

A.

Develop Team

B.

Manage Team

C.

Control Resources

D.

Plan Resource Management

Question # 314

What is project management?

A.

A logical grouping of project management inputs, outputs, tools, and techniques

B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

C.

Launching a process that can result in the authorization of a new project

D.

A formal, approved document that defines how the project is executed, monitored, and controlled

Question # 315

The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?

A.

Monitor Communications

B.

Plan Communications Management

C.

Manage Communications

D.

Manage Stakeholder Engagement

Question # 316

Which of the following is an input to the Perform Qualitative Risk Analysis process?

A.

Risk register

B.

Risk data quality assessment

C.

Risk categorization

D.

Risk urgency

Question # 317

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

A.

Organizational breakdown structure (OBS)

B.

Work performance information

C.

Work package

D.

Work breakdown structure (WBS)

Question # 318

A project manager has recently been assigned a new agile project and needs to determine an appropriate leadership style. The project manager aims to empower the team members so they feel committed and motivated to deliver value.

Which leadership style should be used for this project?

A.

A servant leadership style

B.

A laissez-faire leadership style

C.

A collaborative leadership style

D.

A directive leadership style

Question # 319

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

A.

Project document updates

B.

Activity list

C.

Activity attributes

D.

Project calendars

Question # 320

The individual or group that provides resources and support for a project and is accountable for success is the:

A.

sponsor

B.

customer

C.

business partners

D.

functional managers

Question # 321

A project veers off track due to scope creep. The project management team requests an immediate response from the major stakeholders.

What should the project manager do next to avoid project failure?

A.

Adopt a change management approach and delay the project to decide on the direction.

B.

Develop a focus group to face the issue and decide on the appropriate direction.

C.

Request a meeting with top management to state concerns about their ability to handle the situation.

D.

Delay the project by adopting a fast-fail approach, mitigating the risk of having a bigger impact on the company.

Question # 322

An input to Conduct Procurements is:

A.

Independent estimates.

B.

Selected sellers.

C.

Seller proposals.

D.

Resource calendars.

Question # 323

One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

A.

It represents how and when the project will deliver the products, services, and results defined in the project scope

B.

It creates a formal record of the project and shows the organizational commitment to the project

C.

It describes how the scope will be defined, developed, monitored, controlled and validated

D.

It provides the needs of a stakeholder or stakeholder group

Question # 324

A project manager is assigned to a project during the execution phase and consults the documents created by the previous project manager.

Which document should the project manager study to identify the ownership of the project outcome?

A.

The lessons learned repository

B.

The project charter

C.

The business case

D.

The organizational plan

Question # 325

In an agile and adaptive project, which scope management entity invokes stakeholder engagement?

A.

Collect Requirements

B.

Create work breakdown structure (WBS)

C.

Plan Scope Management

D.

Scope Baseline

Question # 326

Reserve analysis is a tool and technique used in which process?

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Question # 327

Which subsidiary management plan.... during the project ilfe cycle?

Which Subsidiary management plan would a project manager create to manage Information dissemination during the project life cycle?

A.

Stakeholder Engagement Plan

B.

Quality Management Plan

C.

Communications Management Plan

D.

Scope Management Plan

Question # 328

What is the key benefit of the Monitor Stakeholder Engagement process?

A.

Ensures that the informational needs of the project and its stakeholders are met through implementation and the development of artifacts

B.

Ensures that the project includes all the work required and only the work required—to complete the project successfully

C.

Increases the probability and/or impact of positive risks, and decreases the probability and/or Impact of negative risks or issues

D.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves

Question # 329

The activity tailoring is necessary because:

A.

the members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide, this is required for all projects

B.

each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide

C.

the members of the project team need to understand the PMBOK Guide processes, which are applied to all projects

D.

each project is unique, and the project team must plain how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide

Question # 330

An output of the Manage Stakeholder Engagement process is:

A.

change requests

B.

enterprise environmental factors

C.

the stakeholder management plan

D.

the change log

Question # 331

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

A.

Force/direct

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Collaborate/problem solve

Question # 332

What is the primary purpose of Project Scope Management?

A.

Determining and managing stakeholder needs

B.

Contorting the status of the product scope and managing changes to its be seine

C.

Defining and controlling what is and is not included in the project

D.

Differentiating between the product scope and project scope

Question # 333

A project team is brainstorming about the best methods and practices to adopt for an upcoming project. What is the project team trying to follow?

A.

Portfolios

B.

Standards

C.

Concepts

D.

Programs

Question # 334

Who defines the scope of the product

A.

The client

B.

The project manager

C.

The team

D.

The program manager

Question # 335

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

A.

The customer and functional managers

B.

The risk owners and stakeholders

C.

The sponsors and stakeholders

D.

The project management team

Question # 336

What type of stakeholder is part of a project manager ' s sphere of influence on a project?

A.

Customers

B.

Sponsors

C.

Directors

D.

Resource managers

Question # 337

The process of prioritizing risks for further analysis or action is known as:

A.

Plan Risk Management.

B.

Plan Risk Responses.

C.

Perform Qualitative Risk Analysis.

D.

Perform Quantitative Risk Analysis.

Question # 338

It you established a contingency reserve including time, money, and resources, how are you handling risk?

A.

Accepting

B.

Transferring

C.

Avoiding

D.

Mitigating

Question # 339

Conflict should be best addressed in which manner?

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Question # 340

Which risk response strategy is common for both positive and negative risks?

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Question # 341

A project is in the planning phase and ready for plan review and approval when a sponsor switch happens. What should the next course of action be?

A.

Plan Communications Management

B.

Plan Stakeholder Engagement

C.

Perform Integrated Change Control

D.

Perform Qualitative Risk Analysis

Question # 342

Which cost is associated with nonconformance?

A.

Liabilities

B.

Inspections

C.

Training

D.

Equipment

Question # 343

Which of the following includes how requirements activities will be planned, tracked, and reported?

A.

Configuration management plan

B.

Scope baseline

C.

Requirements management plan

D.

Schedule baseline

Question # 344

Which technique helps to determine the risks that have the most potential impact on a project?

A.

Cost risk simulation analysis

B.

Expected monetary value analysis

C.

Modeling and simulation

D.

Sensitivity analysis

Question # 345

Which procurement management process includes obtaining seller response, seller selection, and contract awarding?

A.

Plan Procurement

B.

Manage Procurement

C.

Conduct Procurements

D.

Perform Procurement

Question # 346

Development of the benefits management plan occurs in which stage of the project life cycle?

A.

Starting the project

B.

Organizing the project

C.

Completing pre-project work

D.

Executing the product

Question # 347

What causes replanning of the project scope?

A.

Project document updates

B.

Project scope statement changes

C.

Variance analysis

D.

Change requests

Question # 348

Work performance information and cost forecasts are outputs of which Project Cost Management process?

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

Question # 349

An organization is faced with increasing demand from the board of directors. They say budgets are flexible as long as the work gets completed.

What project management approach should the organization use?

A.

Predictive

B.

Hybrid

C.

Iterative

D.

Adaptive

Question # 350

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?

A.

Escalate this issue to the project management office (PMO).

B.

Escalate this issue to the chief financial officer (CFO).

C.

Escalate this issue to the procurement team.

D.

Escalate this issue to the project sponsor.

Go to page: