Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

PMI Risk Management Professional (PMI-RMP) Exam

Last Update 17 hours ago Total Questions : 284

The PMI Risk Management Professional (PMI-RMP) Exam content is now fully updated, with all current exam questions added 17 hours ago. Deciding to include PMI-RMP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMI-RMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-RMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Risk Management Professional (PMI-RMP) Exam practice test comfortably within the allotted time.

Question # 51

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?

A.

Add more float to the key activity

B.

Add more contingency to the project

C.

Review the plans for the key activity

D.

Increase the budget for the key activity

Question # 52

The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

A.

Ensuring that the project sponsor is kept well-informed

B.

Arranging periodic risk: management process audits

C.

Communicating the status of risks regularly to stakeholders

D.

Monitoring costs with intervention when necessary

Question # 53

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

A.

Assess the identified secondary risk.

B.

Implement the risk response plan.

C.

Implement the risk contingency plan.

D.

Communicate the identified residual risk.

Question # 54

During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

A.

Engage with the team to present the actual results to the sponsor.

B.

Prepare a management of change (MOC) to adjust the project cost and duration.

C.

Move forward with the lessons learned from the sprint.

D.

Review the assumptions to understand any change.

Question # 55

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

A.

Probability of a response triggering a secondary risk

B.

How the response will affect the quality of the components

C.

If the risk response is tied to an activity on the critical path

D.

Verify due dates for the actions have been identified

Question # 56

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

A.

Wait until the weather improves before sending the equipment.

B.

Ask the project sponsor to approve shipping the equipment.

C.

Proceed with the planned risk response to move the equipment.

D.

Request the shipment of the equipment to satisfy the client.

Question # 57

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

A.

Strengths, weakness, opportunities, and threats (SWOT) analysis

B.

Delphi technique

C.

Decision tree analysis

D.

Probability impact matrix

Question # 58

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.

Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?

A.

Schedule and resource assumptions

B.

Contingency reserves

C.

Work breakdown structure (WBS)

D.

Risk impact matrix

Question # 59

A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.

What should the risk manager do first?

A.

Remove the activity padding.

B.

Review the risk response plan.

C.

Update the risk contingency plan.

D.

Update the schedule constraints. 

Question # 60

A risk manager schedules workshops for identifying risks about an initiative involving multiple business units, recruitments for different roles, procurements, technological uplift, training, and changes in the ways of working. Who should participate in the risk management activity?

A.

Core project team

B.

Internal and external stakeholders

C.

Key business stakeholders

D.

Internal stakeholders only

Go to page: