Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

PMI Risk Management Professional (PMI-RMP) Exam

Last Update 13 hours ago Total Questions : 278

The PMI Risk Management Professional (PMI-RMP) Exam content is now fully updated, with all current exam questions added 13 hours ago. Deciding to include PMI-RMP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMI-RMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-RMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Risk Management Professional (PMI-RMP) Exam practice test comfortably within the allotted time.

Question # 51

A risk manager has a well-structured risk management process in place for a complex project with a tight schedule. Despite implementing preventive actions, one of the risks identified in the early stages of the project has still occurred and is now an issue.

What should the risk manager do next?

A.

Meet with the project team to brainstorm potential solutions to the problem.

B.

Implement the risk response plan to remedy the problem as soon as possible.

C.

Initiate discussions with the project manager to decide how to manage the problem.

D.

Escalate the problem to the project sponsor to agree on the best course of action. 

Question # 52

During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

A.

Engage with the team to present the actual results to the sponsor.

B.

Prepare a management of change (MOC) to adjust the project cost and duration.

C.

Move forward with the lessons learned from the sprint.

D.

Review the assumptions to understand any change.

Question # 53

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

A.

Risk analysis

B.

Risk identification

C.

Risk treatment

D.

Risk evaluation

Question # 54

A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company ' s business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds.

What should the project manager do next?

A.

Update the project management plan to add contingency.

B.

Perform an assumptions and constraints analysis.

C.

Complete an assessment and confirm the response with the sponsors.

D.

Implement mitigation measures for those risks.

Question # 55

A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.

What should the risk management professional do next?

A.

Perform a sensitivity analysis to the higher-level aggregate activities

B.

Develop a risk breakdown structure (RBS) identifying the potential risk categories

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Perform a base line Monte Carlo simul-ation to address overall threats to project objectives

Question # 56

The customer expresses concern about the increasing likelihood of delays from one of the subcontractors on the project. This risk was previously identified and planned for during the project planning phase. The project sponsor reassured the customer that this is a known risk and will be handled accordingly by the risk manager.

What should the risk manager do?

A.

Call an emergency meeting.

B.

Reinforce the customer relationship.

C.

Implement the risk response plan.

D.

Escalate risk to the owner.

Question # 57

A risk manager has been assigned to a project in a company that is undergoing a significant cultural and organizational change. The risk manager will start planning risk management. activities with stakeholders but is unsure with whom to engage.

What should the risk manager do?

A.

Assign a subset of stakeholders to work on the risk management process.

B.

Leverage the project manager ' s project stakeholder analysis.

C.

Agree with the project manager not to start risk activities.

D.

Send a communication inviting volunteers to join risk activities.

Question # 58

The stakeholders of a building construction project are not comfortable with the project manager ' s handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.

What should the risk manager do first to demonstrate this to the stakeholders?

A.

Gather other project risk historical information.

B.

Gather and reconcile project risk report data.

C.

Work with the sponsor to convince the risks are under control.

D.

Work with the team to ensure the project is in good health. 

Question # 59

A major data center initiative involves performing a sensitivity analysis to determine the center ' s required amount of disaster recovery. Several key stakeholders are in disagreement about which level of disaster recovery is required. The lessons learned disaster recovery plans, and the difference for this data center is its geographical location and unique climate requirements. The database includes examples from previous similar initiatives, as well as the competitor ' s advertised plans.

What should the risk manager do to quantify the risk?

A.

Initiate a 360-degree assessment.

B.

Consult environmental enterprise factors for benchmarks.

C.

Review organizational process assets for guidance.

D.

Consider leveraging the Delphi technique.

Question # 60

A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints

What should the project manager do next to determine risk impact of assumptions and constraints?

A.

Add all assumptions and constraints to the risk register.

B.

Add the risk impact of the assumptions in the risk register.

C.

Add the assumptions and constraints to the assumption log.

D.

Add the assumptions and constraints in the project charter.

Go to page: