You'll find that our PMI-RMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-RMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Risk Management Professional (PMI-RMP) Exam practice test comfortably within the allotted time.

Question # 11

A risk management team has completed a quantitative analysis, and the individual score in terms of schedule and cost has been identified. The team is consolidating inputs for contingency planning and notices that the available time and funds are not sufficient for all the risks.

What should the risk manager advise the project team?

A.

Ask the project sponsor for more time and funds if needed.

B.

Create a change request if there are additional needs based on the risk responses.

C.

Accept some risks might not be materialized so no extra time and funds will be needed.

D.

Focus on the high-impact risk for contingency planning purposes.

Question # 12

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

A.

Ensure that all project stakeholders have a copy of and understand the project ' s risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register. 

Question # 13

A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (Refer to the email exhibit).

How many total story points is the entire initiative?

A.

72

B.

60

C.

40

D.

32

Question # 14

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

D.

Perform a root-cause analysis. 

Question # 15

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

A.

Risk analysis

B.

Risk identification

C.

Risk treatment

D.

Risk evaluation

Question # 16

A financial service firm adheres to heavily regulated compliance legislation. During the firm ' s latest project, the Chief Financial Officer (CFO) and the Chief Information Officer (CIO) endorsed a risk-based approach. This approach ensured compliance with the legislative requirements for properly storing confidential employee salary information. The risk manager recorded this information in the project ' s risk management plan.

What is the organization ' s risk maturity level?

A.

No maturity

B.

Low maturity

C.

Medium maturity

D.

High maturity

Question # 17

A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time

What should the risk manager do in this situation?

A.

Establish a formal and upfront risk identification process.

B.

Use a detailed and quantitative risk assessment process.

C.

Create an effective and clear risk communication process.

D.

Adopt a dynamic and frequent risk management process.

Question # 18

A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.

Which technique should the risk manager use?

A.

Political, economic, social, technological, legal, and environmental (PESTLE) analysis

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Decision tree analysis

D.

Cost-benefit analysis

Question # 19

In the middle of a project to improve internal workflows, the team realizes that some previously identified challenges, such as lack of stakeholder engagement, have diminished. However, the risk manager determines that concerns related to resource availability and regulatory compliance are becoming more significant.

Which measures should the risk manager implement?

A.

Concentrate on monitoring only high-visibility risks to conserve resources.

B.

Focus on tracking the risks identified at the project ' s start to maintain consistency.

C.

Reassess risk priorities carefully and update the risk register on a regular basis.

D.

Delegate all monitoring responsibilities entirely to individual team members for efficiency.

Question # 20

A project manager is assigned to a new project and is told they need to develop the project ' s risk register. When should the project manager identify the project risks?

A.

Identify risks only at the project ' s midpoint for the stakeholders to review them

B.

Ensure project team members proactively identify risks throughout the project to plan for possible response strategies

C.

Identify risks at the beginning of the project because the risk posture will not change

D.

Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas