Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

PMI Risk Management Professional (PMI-RMP) Exam

Last Update 17 hours ago Total Questions : 284

The PMI Risk Management Professional (PMI-RMP) Exam content is now fully updated, with all current exam questions added 17 hours ago. Deciding to include PMI-RMP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMI-RMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-RMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Risk Management Professional (PMI-RMP) Exam practice test comfortably within the allotted time.

Question # 21

Which statement describes the risk portrayed on the risk matrix heat map below?

A.

The risk has a probability of 60% of occurrence and a medium impact rating.

B.

The risk has a probability of 40% of occurrence and a high impact rating.

C.

The risk has a high impact and probability of occurring.

D.

The risk has a low probability and high impact rating.

Question # 22

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

A.

US$18,000

B.

US$72.000

C.

US$30,000

D.

US$48,000

Question # 23

A project manager is leading a complex, high-risk construction project in the city center. To address risk based on lessons learned from similar past building projects, the risk manager assigns a team member to assess and confirm risk thresholds for the project.

What should the risk manager do?

A.

Develop risk assessment processes and tools to quantify risk thresholds.

B.

Work with stakeholders to achieve consensus on risk thresholds.

C.

Use subject matter experts and historical data to estimate risk thresholds.

D.

Review regulatory requirements and the contract to identify risk thresholds.

Question # 24

The major investor in a road construction project is constantly asking project team members for information about the project ' s execution. This has resulted in the project team working 20% of their day preparing project reports for the stakeholders.

What should the risk manager do to enhance the project team ' s approach to risk reports?

A.

Talk to the project team and ensure they avoid direct communication with this stakeholder.

B.

Engage with the team to enhance the project risk reports sent to the stakeholders.

C.

Highlight to the stakeholders the agreed predetermined frequency of risk reports.

D.

Work with the project sponsor to ensure stakeholders avoid directly influencing the project team.

Question # 25

A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.

What type of risk response is this?

A.

Transfer

B.

Accept

C.

Mitigate

D.

Avoid 

Question # 26

A risk manager faces resistance as they try to implement the project ' s risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

A.

Continue to implement the risk strategy

B.

Meet with team members to address their concerns.

C.

Reduce the number of risk management activities.

D.

Raise the concerns with the project sponsor,

Question # 27

When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

A.

Select the strategies with the least overall impact to resources.

B.

Select the strategies with the least financial impact.

C.

Select the strategies with the greatest overall positive influence.

D.

Select the strategies with the greatest benefit to stakeholders.

Question # 28

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project ' s risk register and asks the risk manager for an analysis of its effectiveness.

What two actions should the risk manager do next? (Choose two.)

A.

Check to ensure that the risk is supported by a Monte Carlo simul-ation.

B.

Check to ensure that the risks are gathered using Delphi technique.

C.

Check for risk classification and that probability and impact are identified.

D.

Check to ensure that risk origin, triggering event, and ownership is identified.

E.

Check to ensure the risk meeting agenda and supporting documents are distributed.

Question # 29

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

A.

Each cause has a degree of uncertainty

B.

Each cause has well defined owner

C.

The causes represent actual conditions

D.

The causes must be validated by the risk owner

Question # 30

What should the risk owner use as an effective information-gathering technique during the planning session?

A.

Monte Carlo analysis

B.

Update risk register

C.

Brainstorming

D.

Cost and time estimating

Go to page: