Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

PMI Risk Management Professional (PMI-RMP) Exam

Last Update 13 hours ago Total Questions : 278

The PMI Risk Management Professional (PMI-RMP) Exam content is now fully updated, with all current exam questions added 13 hours ago. Deciding to include PMI-RMP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PMI-RMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-RMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Risk Management Professional (PMI-RMP) Exam practice test comfortably within the allotted time.

Question # 31

A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?

A.

Updated probability and impact matrix

B.

Updated risk register

C.

Updated mitigation plans

D.

Updated project schedule 

Question # 32

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

A.

US$18,000

B.

US$72.000

C.

US$30,000

D.

US$48,000

Question # 33

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization ' s risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

A.

Implement the secondary risk response and update the project documents.

B.

Conduct meeting with all stakeholder to agree on post impact solutions.

C.

Set the corresponding trigger conditions to the secondary risk.

D.

Engage the project manager to authorize the secondary risk ' s response.

E.

Update and communicate assessments of the secondary risk ' s impact.

Question # 34

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

A.

Review project schedule estimates.

B.

Change the response strategies.

C.

Reduce the contingency reserves.

D.

Conduct a risk planning workshop.

Question # 35

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

A.

Reduce the probabilities of those risks on the risk register

B.

Transfer ownership of those risks to the customer

C.

Implement the risk handling strategies for those risks

D.

Request additional management reserve for those risks

Question # 36

A company has been awarded a large government contract to develop a new transportation system. There is uncertainty surrounding the project ' s timeline. The project team is struggling to finalize the project ' s budget due to unclear estimates from vendors. An updated vendor price list detailing the costs of available technologies is an essential component in determining the project ' s final cost. The project team will not be able to finalize the project ' s timeline until the budget is finalized.

What should the risk manager do?

A.

Request an extension to mitigate schedule constraints.

B.

Register the risks as vendor issues and avoid further action.

C.

Log the risk and the response strategies in the risk register.

D.

Catalog the risks as assumptions and avoid further action.

Question # 37

A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?

A.

Earned value management (EVM) variance metrics

B.

A risk burndown chart showing remaining risks

C.

The format established in the risk management plan

D.

An itemized list of remaining risks and their scores 

Question # 38

A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.

What should the project risk manager monitor closely?

A.

Risk thresholds

B.

Risk response strategies

C.

Risk management reports

D.

Risk breakdown structure (RBS)

Question # 39

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

A.

Review the agreed-upon risk tolerance

B.

Perform a sensitivity analysis of the risk

C.

Find out the stakeholders’ risk appetite

D.

Use industry standard risk thresholds

Question # 40

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?

A.

Escalate the problem to the project sponsors.

B.

Execute the approved risk response plan.

C.

Negotiate with the supplier to resolve the problem.

D.

Assign a team member to update the issue leg.

Go to page: