You'll find that our PMI-SP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-SP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PMI Scheduling Professional practice test comfortably within the allotted time.

Question # 71

What is the term assigned to graphic in the figure given below?

A.

Communications bull ' s eye

B.

Performance goals

C.

Earned value management goals

D.

Project exception report

Question # 72

A construction company is about to start a new project. It requires hiring a project manager for this project. Which of the following are the most important skills that a person must have to be selected as a project manager?

A.

Problem solving

B.

Team building and human resources

C.

Leading

D.

Communication

E.

Negotiation and influential

Question # 73

You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?

A.

Expert Judgment

B.

Decomposition

C.

Rolling Wave Planning

D.

Templates

Question # 74

Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is the best example of apportioned effort?

A.

Adding features to the project ' s product that is not included in the project scope.

B.

Managing the day-to-day events of a project.

C.

Creating software as defined in the project scope.

D.

Completing project activities as start-to-start events.

Question # 75

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

A.

Archive the project records.

B.

Summarize the project risks costs.

C.

Summarize the project variance.

D.

Close the project office.

Question # 76

You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will you record for this activity?

A.

48

B.

20o, 45m, 90p

C.

90

D.

45

Question # 77

You are the project manager for your organization. You are meeting with your customers to discuss the project performance. In this meeting, you will have eight project customers, the project sponsor, and ten members of your project team. What type of communication method are you using in this instance?

A.

Interactive communication

B.

Active communication

C.

Pull technique

D.

Push technique

Question # 78

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:

A.

Communications bull ' s eye

B.

Performance goals

C.

Earned value management goals

D.

Project exception report

Question # 79

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy ' s project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

A.

-$75,000

B.

-$42,000

C.

-$45,000

D.

-$65,000

Question # 80

Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?

A.

Perform resource leveling for the project.

B.

Crash the project schedule.

C.

Fast track the project.

D.

Remove things from the project scope.

Go to page: