You'll find that our PgMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PgMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Program Management Professional (PgMP) practice test comfortably within the allotted time.

Question # 31

Which of the following program process outputs includes causes of variances from the program management plan, corrective actions taken and their outcomes, risk mitigations, and other information of value to management and stakeholders of future programs?

A.

Lessons learned

B.

Supporting details

C.

Program management plan updates

D.

Assumptions

Question # 32

A program manager needs to establish direction and identify the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined, assessed, and documented.

Which document will be created to support this activity?

A.

Program resource management plan

B.

Program management plan

C.

Program master schedule

D.

Program scope statement

Question # 33

You are the program manager for your organization. This program will last for two years and has eight projects. The cost of your program is $4 million and there are some risk concerns that may affect the overall cost of the program. Management is concerned with how long it will take the program to reach the management horizon. What is management horizon also known as?

A.

Payback period

B.

Cost performance index

C.

Cost-to-benefits ratio

D.

Return on investment

Question # 34

A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?

A.

.93

B.

.82

C.

$323,889 D. -$38,889

Question # 35

An organization is embarking on a new program aligned with its strategic objectives. The new program has a high level of risk due to the rapidly changing technical landscape in which the organization operates. The organization has mature program management capabilities, as measured by its resources, intellectual assets, and management processes.

Given the organization’s history of delivering successful programs, what should the program manager do as part of the planning process?

A.

Interview the program managers and stakeholders of previous programs to learn from their experiences.

B.

Review the organization’s strategic objectives, risk tolerance, and compliance processes, which may provide knowledge about past programs.

C.

Consult the repository developed as part of the organization’s knowledge management initiative to capture best practices and lessons learned.

D.

Hire independent industry specialists and subject matter experts (SMEs) to provide additional information about market trends and uncertainties in the external environment.

Question # 36

You are the program manager for your organization. You have created a program that will create things for the organization throughout the program not only at program closure. All of the following are elements that you may transfer to the organization throughout the program ' s life cycle except for which one?

A.

Benefits

B.

Risk management outcomes

C.

Program personnel

D.

Outputs from team development

Question # 37

Donna is the project manager for her organization. She is preparing a plan to manage changes to the project

should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna ' s plan?

A.

Quality Management System

B.

Change Control System

C.

Project Management Information System

D.

Integrated Change Control System

Question # 38

After an organization initiates a strategic program, several project managers express interest in joining the program team. The program manager’s supervisor recommends a list of project managers to be part of the team.

What should the program manager do to select the project managers?

A.

Complete a skill set inventory and select the most suitable resource(s)

B.

Ask interested project managers for their CV or résumé and conduct interviews

C.

Accept the recommendation of the program manager’s supervisor

D.

Contact the human resource manager for project managers’ availability

Question # 39

A company CEO issues a mandate to automate a new-client onboarding process to replace manual and paper-based procedures. After the program sponsor and program manager obtain formal acceptance of the program charter, what should be done next?

A.

Deploy a team to develop the program management plan.

B.

Develop estimates for scope, resources, and cost.

C.

Identify the program management components, and develop the resource management plan.

D.

Review and update the benefits management plan and link it to program outcomes.

Question # 40

Alice is the project manager of the NHQ Project and is entering the project ' s closing processes. The project, she has managed, has been for another organization in a contractual relationship. Her organization requires Alice to complete performance reviews of the project team, review the deliverables with the project customer, and to obtain formal signoff of the project deliverables. There may be other conditions and activities that Alice likely will need to do in this final project phase. Where can Alice check regarding this project?

A.

Project Integration Plan

B.

Project Contract

C.

Project Quality Control procedures

D.

Project Communications Management Plan