You'll find that our PgMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PgMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Program Management Professional (PgMP) practice test comfortably within the allotted time.

Question # 71

During the execution phase of a program, a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects.

What should the program manager do to address the situation?

A.

Review and update the detailed stakeholder list.

B.

Review and update the stakeholder engagement plan.

C.

Execute the component project ' s communications management plan.

D.

Update the risk register.

Question # 72

An organization is considering a new program. The program has a cost of $1,950,000 and will last for three years. What is the minimum future value this organization should expect to receive from this program if it is initiated and the rate of return is six percent?

A.

$2,322,481

B.

$1,950,000

C.

$2,067,000

D.

$1,950,001

Question # 73

Company A acquires company B, which leads to a two-year program to integrate the processes and systems. Company B uses a different project management process, and the company’s staff is unhappy about the acquisition. As a result, company B’s project team fails to provide status and cost data in a format that conforms to the program standards.

What should the program manager do first?

A.

Inform the stakeholders of this issue as soon as possible

B.

Change the program standards, aligning them with the project standards

C.

Work with the reports provided to extract the required information

D.

Remind the project manager of the relevant program standards

Question # 74

You are the program manager of the NQA Program. In this program you ' re planning which contract types you ' ll allow into the program and which ones you will not. One contract type you won ' t accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?

A.

The contract type requires the vendor to provide a fee for the time invested and the materials used.

B.

The contract type allows the vendor to change the price of the work he ' s completed.

C.

The contract type allows is the most dangerous for the buyer.

D.

The contract type requires the vendor to provide a fixed price for the work.

Question # 75

A critical program for a company fails to delivers its intended benefits. The CEO and program sponsor are both held accountable and, ultimately, their employment is terminated by the board of directors.

What should the program manager do before formally closing the program?

A.

Update the benefits register.

B.

Establish a program management information system (PMIS).

C.

Share lessons learned with all program team members.

D.

Transfer all program documentation to the deputy program manager.

Question # 76

Julie is the project manager of the NHQ Project. She and her project team have successfully finished the project and the customers have signed the project closure agreement. Julie has compiled all of the project records and the project ' s lessons learned documentation. What should Julie do with the project ' s lessons learned documentation?

A.

These are for Julie ' s reference when she is reviewed by the project sponsor.

B.

These are given to the project sponsor so he can review the project.

C.

These are given to the project steering committee so they may review the project performance.

D.

These are transferred to the lessons learned knowledge base.

Question # 77

Which of the following shows the ratio between a task ' s budgeted and actual costs?

A.

To-Complete Performance Index (TCPI)

B.

Schedule Variance (SV)

C.

Schedule Performance Index (SPI)

D.

Cost Performance Index (CPI)

Question # 78

You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?

A.

Report Program Performance

B.

Monitor and Control Program Scope

C.

Monitor and Control Program Schedule

D.

Monitor and Control Program Performance

Question # 79

Ben is the program manager for his organization. He ' s working with program team to determine what activities need to be completed in order to move the program into execution. He and the team are subdividing the program scope into smaller, manageable components to determine the activity list. What is Ben and his program team creating by subdividing the program scope in this scenario?

A.

Work breakdown structure

B.

Program network diagram

C.

Program scope baseline

D.

Activity list

Question # 80

Which of the following statements are true regarding program scope statement? (Choose three.)

A.

It defines all the work and only the required work for the program.

B.

It formally authorizes the program.

C.

It sets authorities and limits for the program manager and team.

D.

It represents a common understanding of the program for the purpose of facilitating communication among the stakeholders.