You'll find that our PgMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PgMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Program Management Professional (PgMP) practice test comfortably within the allotted time.

Question # 81

After taking over a program, a program manager reviews the program’s status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000.

Based on this information, the program manager determines which of the following?

A.

The schedule is US$30,000 under budget

B.

The cost is US$20,000 under budget

C.

The schedule is US$10,000 over budget

D.

The cost is US$20,000 over budget

Question # 82

Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B’s program manager has just advised that program B has been closed.

What should program A’s program manager update and review first with the stakeholders?

A.

Benefits sustainment plan

B.

Benefits register

C.

Benefits management plan

D.

Benefits transition plan

Question # 83

An organization must accelerate a product to market. The program manager completes the preliminary program steps and holds a kick-off meeting. Project managers submit their preliminary schedules for review.

What should the program manager do next?

A.

Assign resources to the schedule and report the revised delivery date to the project managers.

B.

Work with the project managers to refine the project schedules and deliverables to align with the program milestones.

C.

Revise the project schedules to meet the program schedule and communicate to stakeholders.

D.

Integrate the project schedules into the program schedule and report the revised delivery date to the project managers.

Question # 84

You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that can happen in any order?

A.

Finish on constraints

B.

Discretionary dependencies

C.

Mandatory dependencies

D.

Benefits management dependencies

Question # 85

Program management has several themes that the program manager must be aware of. Which one of the following is not a program management theme?

A.

Benefit management

B.

Stakeholder management

C.

Program governance

D.

Organizational planning

Question # 86

Kelly ' s program is slipping on its schedule. Management is worried that the program will be late and this will cost the organization several thousand dollars in fines and penalties. They ' ve asked Kelly to use a schedule duration compression technique that will help the program finish on time. The technique that Kelly can use, however, should not add costs to the program. What duration compression technique should Kelly use in this instance?

A.

Crash the program

B.

Add lead time to the program

C.

Trim the program scope

D.

Fast track the program

Question # 87

You are the program manager for your program and are creating a communications management plan. Management wants you to address the type of communications based on the number of communication channels you ' ll have within the program. Currently there are 345 stakeholders in your program but next week you ' ll have 387 stakeholders. How many more communication channels will you have next week in your program?

A.

59,340

B.

15,351

C.

861

D.

74,691

Question # 88

Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

A.

Fast tracking

B.

Compressing

C.

Float

D.

Crashing

Question # 89

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent

$789,000. The program is supposed to be 35 percent complete but do to some delays you ' re slightly behind schedule. Based on this information, what is the schedule variance (SV) of this program?

A.

-$85,230

B.

$821,065

C.

-$284,100

D.

-$117,295

Question # 90

What would prevent a program manager from completing program closure once a program has been completed?

A.

Failure to update the financial management plan

B.

Failure to update the benefits register

C.

Incomplete realization of all program benefits

D.

Failure to obtain program steering committee approval