You'll find that our PgMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PgMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Program Management Professional (PgMP) practice test comfortably within the allotted time.

Question # 121

In preparation for the development and submission of the program master schedule to a client, the program manager meets with the component project manager and master program scheduler to discuss the work breakdown structure (WBS).

During the meeting, the master scheduler indicates that the master program schedule should include which of the following?

A.

Program benefits and all component project activities

B.

Component resources and their activity assignment/responsibility metrics

C.

Program-level activities and integrated component projects

D.

Program activities, component activities, and all other work

Question # 122

A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager’s attempts to reach the stakeholder via email also fail.

What should the program manager do next?

A.

Escalate the issue to the stakeholder’s supervisor

B.

Escalate the issue to the program governance board, as delays will impact the program

C.

Update the program risk register to reflect a realized risk and execute the documented risk response

D.

Attempt to call the key stakeholder; if unsuccessful, visit their office to identify potential risks

Question # 123

You are the program manager of the NHQ Program for your organization. Your program has 14 constituent projects that are all creating benefits and deliverables for your program. You have recently terminated the GHW Project in your program because you ' ve made trade-offs with other program projects and the deliverables of the GHW Project are no longer affordable. What project management activity should happen in the GHW Project?

A.

Quality audit

B.

Scope verification

C.

Scope control

D.

Financial audit

Question # 124

Your program has just been chartered during the program initiation process. Your program also needs to create three program statements. Which program statement defines how your program will manage tradeoffs, competing objectives, and program and organization decisions?

A.

Value

B.

Vision

C.

Scope

D.

Mission

Question # 125

What is the present value of a program that will be worth $3,567,000 if it lasts for six years and the rate of return is five percent?

A.

$1,550,850

B.

$3,532,000

C.

$2,502,750

D.

$2,661,750

Question # 126

Where are negative risks recorded?

A.

Negative risk register

B.

Risk management plan

C.

Risk register

D.

Issues log

Question # 127

Molly is the program manager for her organization and she is creating a program plan that defines the benefits of the program and how her program and team will create the benefits for the organization. What plan is Molly creating in this scenario?

A.

Quality management plan

B.

Business case

C.

Program management plan

D.

Benefits management plan

Question # 128

You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?

A.

Analogous estimating

B.

Organizational process assets

C.

Parametric scope definition

D.

Template driven

Question # 129

A company is rolling out an innovative program that includes new processes intended to define how the company will manage future programs. While program execution is going well, the program sponsor is concerned that the knowledge acquired needs to be reused for future programs.

What should the program manager do to ensure that the knowledge acquired is captured efficiently?

A.

Record lessons learned in the program management plan

B.

Create training materials summarizing team experiences and lessons learned

C.

Direct the project managers to create event logs to document their experiences and lessons learned

D.

Organize review sessions after each program stage to document successes, issues, and lessons learned

Question # 130

All of the following are resources that you will need to monitor and control in a program environment except for which one?

A.

Staff members

B.

Contracts

C.

Quality

D.

Equipment